Planning Committee, Thursday 23 May 2013 at 10.00am

N/084/00642/10

Refused Planning 2 papers

Planning Committee refused this item on Thursday 23 May 2013. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED That the appeal be continued based on the original reason for refusal and, as part of that process, that the evidence base submitted to the original Inquiry be revisited and updated where necessary.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Planning Committee, 3 pages

Background

2.1Members will be aware that the above proposal is the subject of appeal. There have been to date some 4 adjournments, the last due to the tragic death of the Inspector.

2.2As a result of the long delays in the overall appeal process (the planning decision was made in March 2010), there have been three particular changes in the evidence base for the appeal that need to be considered. That consideration stems from the Appeals Procedure Rules.

2.3The three particular issues are;

a) The revocation of the Regional Plan; b) The revocation of PPS 22 and its replacement by the NPPF (National Planning Policy Framework); and c) The Inspector's decision on the Gayton le Marsh planning appeal.

2.4The single reason for refusal stated;

It is considered that the cumulative effect of this proposed wind farm with other built, consented and proposed wind farms, both on and off-shore, would have a significant harmful effect on the locally distinctive character and appearance of the local area and on the wider landscape, including views to and from the Lincolnshire Area of Outstanding Natural Beauty, which would outweigh any benefits the scheme might have in meeting regional and national targets on the production of renewable energy. This harm would be contrary to Policies A4 and A5 in the East Lindsey Local Plan Alteration 1999 and to Policies 26 and 40 in the East Midlands Regional Plan 2009 and would fail to comply with the requirements of Planning Policy Statement 22 - Renewable Energy.

I have highlighted the last element as this refers to the issues raised in the report.

3.0REGIONAL PLAN

3.1The relevant Policies contained within the Regional Plan related to both renewable energy and landscape. The renewable energy policies were quite specific, to the point that targets were set for the provision of renewable energy within the region and those targets were further itemised by technology. (The targets were however stated to be minimum targets) ELDC have been to date rigorous in presenting those targets as having been satisfied within the region and in particular the on-shore wind target being met. The background information that went into the formulation of the Regional Plan and in particular the draft review which never really 'got off the ground' is however still some of the most up to date formal evidence relating to the issue.

3.2The NPPF makes reference to each of those issues.

4.0REVOCATION OF PPS 22 AND ITS REPLACEMENT BY NPPF

4.1PPS 22 gave detailed government advice relating to renewable energy and underpinned the approach that ELDC have taken in appeals. The Companion Guide to PPS22 (Planning for Renewable Energy) remains in play.

4.2The NPPF now provides the only policy base upon which we rely in relation to renewable energy. However, despite its presumption in favour of sustainable development, does retain protection of landscape as one of the parameters against which schemes are judged.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(04)Special Item 642-10Report 3 pages DownloadRead as text
PDF
N/084/00642/10:Report 1 pages Download

At this meeting

Whole meeting

More from East Lindsey Planning Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Tree Preservation Order: 137, Eastgate, Louth (105.36)That 137 Eastgate, Louth (105.36) Tree Preservation Order be confirmed (made permanent). Decided Open
2 Sep 2026 Tree Preservation Order: Land adjacent 116C Horncastle Road, Roughton Moor (215.31)That land adjacent to 116C Horncastle Road, Roughton Moor (215.31) Tree Preservation Order be confirmed (made permane... Decided Open
2 Sep 2026 00489/26/fulThat the application be approved. Approved Open
2 Jul 2026 03860/25/fulThat this Council resolve to grant planning permission with the application being referred to the Secretary of State ... Decided Open
20 May 2026 Election of ChairmanThat Councillor Stephen Eyre be elected Chairman of the Planning Committee for the Council year 2026/27. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies