N/038/01628/13

Approved Planning 3 papers

Planning Committee approved this item on Thursday 16 January 2014. Below is the council's own wording, with the papers it was decided on.

Item153

Resolved

RESOLVED That planning permission be granted, subject to the following conditions:- 1. Details of the access, appearance, landscaping, layout, and scale, (hereinafter called "the reserved matters") must be submitted to and approved in writing by the Local Planning Authority before any development begins and the development must be carried out as approved. 2. Application for approval of all reserved matters must be made not later than the expiration of three years beginning with the date of this permission and the development must be begun no later than: The expiration of two years from the final approval of all reserved matters or, in the case of approval on different dates, the final approval of the last such matter to be approved. 3. Notwithstanding the submitted details, a schedule of the external materials and the finished colour of those materials for the buildings hereby permitted must be submitted to and approved in writing by the Local Planning Authority. Only the details within the approved schedule must be used and retained thereafter. 4. The trees along the south and west boundaries must be protected during the construction period by adhering to the following measures: i ) a chestnut pale or similar fencing 1.5 metres in height shall be provided along the entire Root Protection Area, as shown on drawing .02B received by the Local Planning Authority on the 21st August 2013, prior to any development commencing. No materials, equipment, site huts, fuels or other items shall be placed or stored within the areas enclosed by the fencing so erected and the ground levels within those areas shall not be altered, nor shall any excavation be made, without the prior written consent of the Local Planning Authority; ii) no burning of materials or other items shall take place within the said Root Protection Area; and iii) no services shall be routed within the said Root Protection Area without the prior written consent of the Local Planning Authority. 5. No more than two dwellings shall be erected on ... view the full minutes text for item 153.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Planning Committee, 4 pages

[11] Outline Planning Permission

N/038/01628/ 13 APPLICANT: [name removed],

VALID: 22/08/2013 AGENT: Dieter Nelson Planning Consultancy Ltd.

PROPOSAL: Outline erection of 2 no. dwellings, existing outbuildings to be demolished. LOCATION: HARBOUR COTTAGE, NEWBRIDGE LANE, COVENHAM ST MARY, LOUTH, LN11 0PQ

1.0REASONS FOR COMMITTEE CONSIDERATION

1.1The application was originally presented to this committee on the 12th December 2013 at the request of Cllr Mossop. The application was recommended for refusal by Officers on grounds relating to the sustainability of Covenham as a whole. However Members were satisfied that Covenham was part of a group of villages that support each other and as such the proposal would enhance and maintain the vitality of the rural communities. Members were satisfied that the proposal was in compliance with para 55 of the National Planning Policy framework (NPPF).

1.2It is the protocol of this committee that the application is referred back to this committee to agree any conditions. The original report is appended to this report.

RECOMMENDATION: Approve

subject to the following conditions:

1 Details of the access, appearance, landscaping, layout, and scale, (hereinafter called "the reserved matters") must be submitted to and approved in writing by the local planning authority before any development begins and the development must be carried out as approved.

Reason: To comply with section 92 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).

2 Application for approval of all reserved matters must be made not later than the expiration of three years beginning with the date of this permission and the development must be begun no later than:

The expiration of two years from the final approval of all reserved matters or, in the case of approval on different dates, the final approval of the last such matter to be approved.

Reason: To comply with section 92 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). 3 Notwithstanding the submitted details, a schedule of the external materials and the finished colour of those materials for the buildings hereby permitted must be submitted to and approved in writing by the Local Planning Authority. Only the details within the approved schedule must be used and retained thereafter.

Reason: To ensure the building's appearance is appropriate for its setting having regard to Policies A5 and H12 of the East Lindsey Local Plan Alteration 1999 and to paragraphs 56-64, 109 of the National Planning Policy Framework.

4 The trees along the south and west boundaries must be protected during the construction period by adhering to the following measures:

• a chestnut pale or similar fencing 1.5 metres in height shall be provided along the entire Root Protection Area, as shown on drawing .02B received by the Local Planning Authority on the 21st August 2013, prior to any development commencing. No materials, equipment, site huts, fuels or other items shall be placed or stored within the areas enclosed by the fencing so erected and the ground levels within those areas shall not be altered, nor shall any excavation be made, without the prior written consent of the Local Planning Authority; • no burning of materials or other items shall take place within the said Root Protection Area; and • no services shall be routed within the said Root Protection Area without the prior written consent of the Local Planning Authority.

Reason: To ensure the protection of trees on the site which are subject to a preservation order and having regard to the valuable role they play in the character of the area. This condition is imposed in accordance with Policy A5 of The East Lindsey Local Plan Alteration 1999.

5 No more than two dwellings shall be erected on the whole of the application site.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(11)N-038-01628-13Report 4 pages DownloadRead as text
PDF
Item 11 1628-13 Appendix 1 (2)Appendix 14 pages Download
PDF
N/038/01628/13:Report 1 pages Download

At this meeting

Whole meeting

More from East Lindsey Planning Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Tree Preservation Order: 137, Eastgate, Louth (105.36)That 137 Eastgate, Louth (105.36) Tree Preservation Order be confirmed (made permanent). Decided Open
2 Sep 2026 Tree Preservation Order: Land adjacent 116C Horncastle Road, Roughton Moor (215.31)That land adjacent to 116C Horncastle Road, Roughton Moor (215.31) Tree Preservation Order be confirmed (made permane... Decided Open
2 Sep 2026 00489/26/fulThat the application be approved. Approved Open
2 Jul 2026 03860/25/fulThat this Council resolve to grant planning permission with the application being referred to the Secretary of State ... Decided Open
20 May 2026 Election of ChairmanThat Councillor Stephen Eyre be elected Chairman of the Planning Committee for the Council year 2026/27. Decided Open