RESOLVED That the application be refused: 1. Policy C15 of the East Lindsey Local Plan Alteration 1999 states that development in coastal conservation areas will only be permitted where it is essential in that location or relates to an outdoor recreational use or is a minor extension to an existing building and in all cases the development should not harm the amenities or character of the area. Policy A5 of the ... view the full minutes text for item 36.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
N/005/00439/ 15 APPLICANT: Friends of Time and Tide Bell for Lincolnshire,
VALID: 09/03/2015 AGENT:
PROPOSAL: Planning Permission - Erection of a time and tide bell to a maximum height of 4 metres. LOCATION: SECTION OF BEACH EAST OFF, SANDY LANE, ANDERBY CREEK, SKEGNESS, LINCOLNSHIRE.
1.0REASONS FOR COMMITTEE CONSIDERATION
1.1This application was called in to be heard at Planning Committee by Cllr Fiona Brown on the grounds of the opportunity to discuss the need for beach furniture, the merits of this an attraction and any noise implications for residents.
2.0THE SITE AND SURROUNDINGS
2.1The site is within the coastal hamlet of Anderby Creek on the beach and within the coastal conservation area as defined on Inset 51 in the East Lindsey Local Plan Alteration 1999. Anderby is small coastal holiday resort with a small number of chalet parks and caravan parks and attracts day trippers. It has an attractive sandy beach which provides opportunities for the usual beach recreational activities. The site is on the beach approximately 200 metres north of where the path emerges from the cloud bar and half way between high and low tide lines. The beach area is open and the only other man-made feature on the beach itself is the out fall to the south. This creates a sense of openness and a very natural environment with long distance views along the beach and out to sea. There are dunes to the west and beyond the dunes are residential dwellings. To the south of the site some dwellings perch on the top of the raised sea defences.
3.0DESCRIPTION OF THE PROPOSAL
3.1The proposal is for planning permission for the siting of a time and tide bell within a wooden structure on the beach. It would be a maximum height of 4 metres within a wooden frame. This time and tide bell would be the sixth such structure in a series of twelve around the coast of Britain. Other bells have been constructed at Appledore in Devon, Bosta on the Isle of Lewis, Trinity Buoy in London, Aberdyfi in Wales and Cemaes Bay in Anglesey. As the water rises and falls between high tide and low tide the tide drives the clapper to strike the bell. As the tide changes the bell becomes submerged in the rising water so the strikes and pitch of the bell will vary. The aim of the project is to highlight climate change and The Time and Tide Bell project was a finalist for the Climate Change Awards in 2011. 4.0 CONSULTATION
4.1Set out below are the consultation responses that have been received on this application. These responses may be summarised and full copies are available for inspection separately. Some of the comments made may not constitute material planning considerations.
Publicity
4.2The application has been advertised by means of a site notice displayed on a post to the notice board near the access point onto the beach and neighbours have been notified in writing.
Consultees
4.3ANDERBY PARISH COUNCIL – The Parish object to the application on the grounds that: The ground (beach) is not stable enough for such a structure. The first of these structures erected elsewhere is now just a rusty object. It was agreed that the Parish Council did not want this object and no-one has agreed to take responsibility for its maintenance and upkeep. There is no provision for insurance or health and safety inspections. The possible noise pollution to nearby residents. Anderby Creek beach is a child friendly beach and children may injure themselves when climbing on it.
4.4LCC as HIGHWAYS AUTHORITY – It is considered by the Highway Authority that the proposed development would not be detrimental to highway safety or traffic capacity.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.