CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
East Lindsey District Council
Planning Committee, Thursday 10 March 2016 at 10.00am

S/094/01984/15

Approved Planning 2 papers

Planning Committee approved this item on Thursday 10 March 2016. Below is the council's own wording, with the papers it was decided on.

Item152

Resolved

That Outline Planning Permission be granted in line with officer recommendation with the following conditions: 1. Application for approval of appearance, landscaping and scale must be made not later than the expiration of three years beginning with the date of this permission and the development must be begun no later than: The expiration of two years from the final approval of all reserved matters or, in the case of approval on different dates, the final approval of the last such matter to be approved. 2. Before the commencement of the development hereby granted, full details of the proposed means of foul and surface water disposal to ... view the full minutes text for item 152.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Planning Committee, 7 pages

Consultation

4.1Set out below are the consultation responses that have been received on this application. These responses may be summarised and full copies are available for inspection separately.

Publicity

4.2The application has been advertised by means of Site Notice and neighbour notification and has been included on the weekly list.

Consultees

4.3KIRKBY ON BAIN PARISH COUNCIL – Object to the application primarily because it is a flood risk.

4.4LCC as PLANNING AND CONSERVATION – No comments received.

4.5ENVIRONMENTAL HEALTH (Drainage) – Details of discharge for surface water and details of watercourse before comment.

4.6ENVIRONMENTAL HEALTH (Contaminated Land) – No comments.

4.7ENVIRONMENTAL HEALTH (Noise) – No comments. 4.8 LCC HIGHWAYS AND SUSTAINABLE DRAINAGE SYSTEMS – No objection, advise conditions.

4.9ENVIRONMENT AGENCY – The application has been assessed as having a relatively low environmental risk. Therefore have no further comments on the current application.

4.10LINCOLNSHIRE FIRE AND RESCUE – Advise an informative.

4.11WITHAM THIRD INTERNAL DRAINAGE BOARD – There is a flood problem in the area, the ditch to the southern and eastern boundaries of the site will be adopted by the Board on commissioning of the planned flood alleviation scheme.

Neighbours

4.122 letters of objection have been received, citing the following concerns -

 The development has inadequate surface water drainage;  The proposal does not incorporate a SUDS system;  The area floods;

5.0The Ward Member is aware of the application via the Weekly List.

6.0CONSULTATION ON AMENDED PROPOSALS

6.1The application has been the subject of a further round of re-consultations involving all of the consultees. The revised information related to drainage information which was presented to the Planning and Drainage (PAD) meeting.

Consultees

6.2KIRKBY ON BAIN PARISH COUNCIL – Object to the application.

6.3LCC as PLANNING AND CONSERVATION – No comments received.

6.4ENVIRONMENTAL HEALTH (Drainage) – No comments received.

6.5ENVIRONMENTAL HEALTH (Contaminated Land) – No comments.

6.6ENVIRONMENTAL HEALTH (Noise) – No comments.

6.7LCC HIGHWAYS AND SUSTAINABLE DRAINAGE SYSTEMS – No comments received.

6.8ENVIRONMENT AGENCY – The application has been assessed as having a relatively low environmental risk. Therefore have no further comments on the current application.

6.9LINCOLNSHIRE FIRE AND RESCUE – No comments received.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
S 094 01984 15Report 7 pages DownloadRead as text
PDF
S/094/01984/15:Report 1 pages Download

At this meeting

Whole meeting

More from East Lindsey Planning Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Tree Preservation Order: 137, Eastgate, Louth (105.36)That 137 Eastgate, Louth (105.36) Tree Preservation Order be confirmed (made permanent). Decided Open
2 Sep 2026 Tree Preservation Order: Land adjacent 116C Horncastle Road, Roughton Moor (215.31)That land adjacent to 116C Horncastle Road, Roughton Moor (215.31) Tree Preservation Order be confirmed (made permane... Decided Open
2 Sep 2026 00489/26/fulThat the application be approved. Approved Open
2 Jul 2026 03860/25/fulThat this Council resolve to grant planning permission with the application being referred to the Secretary of State ... Decided Open
20 May 2026 Election of ChairmanThat Councillor Stephen Eyre be elected Chairman of the Planning Committee for the Council year 2026/27. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies