Audit and Governance Committee, Wednesday 1 February 2017 at 10.15am

Internal Audit progress Report Quarter 3

Noted Finance 1 paper

Audit and Governance Committee noted this item on Wednesday 1 February 2017. Below is the council's own wording, with the papers it was decided on.

Item48

Resolved

RESOLVED That the report be noted.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Audit and Governance Committee, 13 pages

Audit Lincolnshire – Internal Audit Report

For all your assurance needs

Internal Audit - Progress Report Quarter 3 2016/17

Contact Details: Emma Bee Internal Audit Manager : 01507 613107 Date: 1 February 2017  [email protected] Audit Lincolnshire – Internal Audit Report

Introduction 1 The purpose of this report is to:  Advise of progress being made with the Audit Plan  Provide details of the audit work during the period  Provide details of the current position with agreed management actions in respect of previously issued reports  Raise any other matters that may be relevant to the Governance and Audit Committee role

Key Messages and Recommendations

2 We have issued one report for an external client this quarter. Work is ongoing for our other external clients in addition to the East Lindsey audit areas detailed at Section 4 of this report.

Significant work has been undertaken this year in respect of unplanned emerging risk areas in addition to resource required to support the Information Governance function. These factors have had an impact on the 2016/17 audit plan and as a result a number of reviews have been postponed until the beginning of 2017/18. A detailed review of progress is attached at Appendix 4 to this report.

Audits in progress

3 We are currently working on audits for external clients and the following East Lindsey reviews:

Kingfisher Caravan Park Licensing Health and Safety Revenues Audit Lincolnshire – Internal Audit Report

Performance Information

4 Our current performance against targets is shown below:

Actual as at 31 Performance Indicator Target December 2016

Percentage of plan completed. 100% 61%

Percentage of key financial systems 100% 0% completed. Percentage of recommendations 100% 100% agreed. Percentage of recommendations 100% or escalated 85% ¹ implemented

¹ Recommendations continue to be closely monitored by internal audit. A large proportion of recommendations are due March 2017. Audit Lincolnshire – Internal Audit Report

Appendix 1 - Assurance Definitions1

High Our critical review or assessment on the activity gives us a high level of confidence on service delivery arrangements, management of risks, and the operation of controls and / or performance.

The risk of the activity not achieving its objectives or outcomes is low. Controls have been evaluated as adequate, appropriate and are operating effectively.

Substantial Our critical review or assessment on the activity gives us a substantial level of confidence (assurance) on service delivery arrangements, management of risks, and operation of controls and / or performance.

There are some improvements needed in the application of controls to manage risks. However, the controls have been evaluated as adequate, appropriate and operating sufficiently so that the risk of the activity not achieving its objectives is medium to low.

Limited Our critical review or assessment on the activity gives us a limited level of confidence on service delivery arrangements, management of risks, and operation of controls and / or performance.

The controls to manage the key risks were found not always to be operating or are inadequate. Therefore, the controls evaluated are unlikely to give a reasonable level of confidence (assurance) that the risks are being managed effectively. It is unlikely that the activity will achieve its objectives.

Our critical review or assessment on the activity identified significant concerns on Low service delivery arrangements, management of risks, and operation of controls and / or performance.

There are either gaps in the control framework managing the key risks or the controls have been evaluated as not adequate, appropriate or are not being effectively operated. Therefore the risk of the activity not achieving its objectives is high.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit progress Report Quarter 3:Report 13 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at East Lindsey

Search all
  1. Internal Audit progress Report Quarter 3This decision
  2. Internal Audit Progress Report - January 2026Noted
  3. Internal Audit CharterApproved
  4. Internal Audit Plan 2025/26Noted
  5. Internal Audit Progress ReportNoted
  6. Internal Audit Report Section 106 Agreements Follow Up AuditAgreed

More from East Lindsey Audit and Governance Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 2026/27 Q1 Treasury UpdateThat the report be noted. Noted Open
9 Sep 2026 Q1 Risk report 2026/27That the Q1 Risk Report - 2026/27 Report be noted. Noted Open
9 Sep 2026 Local Code of Corporate GovernanceThat the updated Local Code of Corporate Governance be approved. Approved Open
9 Sep 2026 Audit & Governance Committee Annual Report 2025/26That the Audit and Governance Committee's Annual Report 2025/26 be approved and presented to Full Council in October ... Approved Open
9 Sep 2026 Annual Governance Statement 2025/26That the draft Annual Governance Statement 2025/26 be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies