CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
East Lindsey District Council
Planning Committee, Thursday 6 April 2017 at 10.00am

N/105/00226/17

Approved Planning 2 papers

Planning Committee approved this item on Thursday 6 April 2017. Below is the council's own wording, with the papers it was decided on.

Item173

Resolved

RESOLVED That full planning permission be granted, subject to the following conditions: 1. The development must be begun not later than the expiration of three years beginning with the date of this permission. 2. The development hereby permitted shall be carried out in accordance with the following approved plans; Drawing No: TA/01/2017 Received by the LPA on 07/02/2017. Drawing No: TA/02/2017 Received by the LPA on 07/02/2017. 3. The brickwork and roofing tiles of the development hereby permitted shall match as closely as possible those of the principal existing dwelling on the site. 4. Notwithstanding the details on the approved plans, all foul water from the development hereby approved must be collected and discharged into the existing foul water system, unless otherwise approved in writing by the Local Planning Authority. If it is found that there is insufficient capacity in the existing system then an alternative scheme for the discharge of foul water must be submitted to and approved in writing by the Local Planning Authority and that scheme must be fully implemented before the development is brought into use. 5. Notwithstanding the details on the approved plans, all surface water from the development hereby approved must be collected and discharged into the existing surface water system, unless otherwise approved in writing by the Local Planning Authority. If it is found that there is insufficient capacity in the existing system then an alternative scheme for the discharge of surface water must be submitted to and approved in writing by the Local Planning Authority and that scheme must be fully implemented before the development is brought into use. (Councillor P. Cooper left the Meeting at 12.46pm).
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Planning Committee, 5 pages

[09] Full Planning Permission

N/105/00226/ 17 APPLICANT: [name removed]. & [name removed],

VALID: 10/02/2017 AGENT:

PROPOSAL: Planning Permission - Extension and alterations to existing house to provide an enlarged kitchen and living area. LOCATION: 74 VICTORIA ROAD, LOUTH. LN11 0BX

1.0REASONS FOR COMMITTEE CONSIDERATION

1.1The application has been referred to the Planning Committee due to one of the applicants being a member of staff.

2.0THE SITE AND SURROUNDINGS

2.1The site is situated in a residential area of Louth within the settlement boundary as defined on Inset Map 1 of the East Lindsey Local Plan Alteration 1999. The property on site is a terraced house in a row of six houses. The houses are constructed from red brick with some in slate and others of concrete tiled roofs with white upvc windows and external doors. Each house has a front door with attractive bay window to the side and two windows over. They have small front gardens enclosed by brick walls of varying heights. Typically, the plan form of the dwelling is historically retained with the main building being adjoined by a two storey monopitch rear extension. This is a typical feature of this and the neighbouring terrace block. Although there are some examples where the scale of rear extensions gradually reduces to a single storey element.

2.2To the rear of the house is a one and half storey off-shoot that steps down in height with a single storey lean-to at the end. The site boundaries to the rear are defined by a 1.46 metre wall with a small trellis approximately 620mm attached that runs along the rear dividing boundary of the site to the adjacent property at 76 Victoria Road. All other site boundaries to the rear are all enclosed by timber boarded fencing.

2.3Whilst there is pedestrian access to this dwelling from Victoria Road, it is also shared with its neighbours in this block of 6 terraces. (68-78 Victoria Road), all ancillary buildings (garages) and rear garden areas to all these six properties are accessed via Keddington Road.

3.0DESCRIPTION OF THE PROPOSAL

3.1The planning application seeks permission for the demolition of the existing dividing boundary wall and to erect a single storey extension and to carry out alterations to existing dwelling to provide an enlarged kitchen and living area.

4.0CONSULTATION 4.1 Set out below are the consultation responses that have been received on this application. These responses may be summarised and full copies are available for inspection separately. Some of the comments made may not constitute material planning considerations.

Publicity

4.2The application has been advertised by means of a site notice displayed on metal post to the front of the site and neighbours have been notified in writing.

CONSULTEES

4.3LOUTH TOWN COUNCIL – Supports this application but has concerns regarding the impact on the neighbour of the use of the party wall.

4.4LCC as HIGHWAY AUTHORITY and LEAD LOCAL FLOOD AUTHORITY - Does not wish to restrict the grant of permission.

NEIGHBOURS

4.5None received.

5.0RELEVANT SITE HISTORY

5.1N/105/00555/11 – Planning permission – Construction of a vehicular access and provision of parking on the site of an existing boundary wall which is to be removed, in accordance with an amended site location plan received by the Local Planning authority on 11 May 2011. Refused – 25 May 2011.

6.0PLANNING POLICY

6.1Section 38(6) of the Planning and Compulsory Purchase Act 2004 requires that planning applications are determined in accordance with the Development Plan unless material considerations indicate otherwise. The Development Plan comprises the East Lindsey Local Plan Alteration 1999 (Saved Policies). The Governments National Planning Policy Framework (NPPF) is a material consideration. Paragraph 215 of the NPPF makes it clear that due weight should be given to relevant policies in existing plans according to their degree of consistency with the framework (the closer the policies in the plan to the policies in the Framework, the greater the weight that may be given).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
09-N-105-00226-17Report 5 pages DownloadRead as text
PDF
N/105/00226/17:Report 1 pages Download

At this meeting

Whole meeting

More from East Lindsey Planning Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Tree Preservation Order: 137, Eastgate, Louth (105.36)That 137 Eastgate, Louth (105.36) Tree Preservation Order be confirmed (made permanent). Decided Open
2 Sep 2026 Tree Preservation Order: Land adjacent 116C Horncastle Road, Roughton Moor (215.31)That land adjacent to 116C Horncastle Road, Roughton Moor (215.31) Tree Preservation Order be confirmed (made permane... Decided Open
2 Sep 2026 00489/26/fulThat the application be approved. Approved Open
2 Jul 2026 03860/25/fulThat this Council resolve to grant planning permission with the application being referred to the Secretary of State ... Decided Open
20 May 2026 Election of ChairmanThat Councillor Stephen Eyre be elected Chairman of the Planning Committee for the Council year 2026/27. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies