East Lindsey District Council
Planning Committee, Thursday 6 September 2018 at 10.00am

N/060/01259/18

Approved Planning 2 papers

Planning Committee approved this item on Thursday 6 September 2018. Below is the council's own wording, with the papers it was decided on.

Item52

Resolved

RESOLVED That the application be approved subject to the following conditions:- The development hereby permitted must be begun not later than the expiration of three years beginning with the date of this permission. The development hereby permitted shall be completed in accordance with the following approved plans; LDC2111-PL-01 Received by the LPA on 26/06/2018. LDC2111-PL-02 Received by the LPA on 26/06/2018. LDC2111-PL-03 Received by the LPA on 26/06/2018. LDC2111-PL-04 Received by the LPA on 26/06/2018. RTK-046-01 Received by the LPA on 26/06/2018. No development shall commence until a surface water strategy has been submitted to and approved in writing by the Local Planning Authority. No ... view the full minutes text for item 52.
Word for word from the decision East Lindsey published for this meeting. Source: democracy.e-lindsey.gov.uk

Follow this further

Built from East Lindsey's papers

What the report saysPro

Report to Planning Committee, 9 pages

Consultation

4.1Set out below are the consultation responses that have been received on this application. These responses may be summarised and full copies are available for inspection separately. Some of the comments made may not constitute material planning considerations.

Publicity

4.2The application has been advertised by means of a site notice and neighbour notification letters. Consultees

4.3ASTERBY AND GOULCEBY PARISH COUNCIL - Object - grounds include a) already three dwellings approved [immediately to the south] and proposal would harm village character; b) SP3 of LP calls for ‘great weight to be placed on conserving landscape and beauty of AONB’; c) retaining gaps in development key to maintaining village character; d) proposal site not in ‘appropriate location’ as applicant asserts; e) Goulceby is not a ‘sustainable location’ with few facilities and no safe access to village centre; f) cumulatively with recent permission this scheme would add too many dwellings to the village which has had sufficient development; g) proposal contrary to basic NPPF principles; h) traffic impacts; i) dwellings would be exceptionally large and would not be affordable to local people.

4.4LCC as LEAD LOCAL HIGHWAYS AND FLOOD AUTHORITY - No objection but conditions requested in event of approval.

4.5LINCOLNSHIRE WOLDS COUNTRYSIDE SERVICE - No objection - ‘We have no concerns on the proposal as it sits within a block of existing housing and consolidates the nucleated settlement pattern of the village. There is no detriment to the surrounding landscape’.

4.6ELDC ENVIRONMENTAL HEALTH (DRAINAGE OFFICER) - Percolation tests requested for any soakaways and full surface water drainage plan to be submitted and approved by Local Planning Authority.

4.7ELDC ENVIRONMENTAL HEALTH (NOISE/ODOUR & CONTAMINATED LAND) - 'No comments'.

4.8HISTORIC ENVIRONMENT OFFICER - None received.

Neighbours

4.9Four letters of objection have been received from residents with an identified Goulceby address, one letter of objection from an address in the village of Scothern and one letter of objection which did not carry an identified address. In addition one resident wrote arguing that the case should be determined by the Planning Committee.

4.10Some objectors have written at considerable length (one letter covers 13 pages plus photographs) and all points raised have been carefully considered. All correspondence can be found in full on the planning file.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
17.N.060.01259.18Report 9 pages DownloadRead as text
PDF
N/060/01259/18:Report 1 pages Download

At this meeting

Whole meeting

More from East Lindsey Planning Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Tree Preservation Order: 137, Eastgate, Louth (105.36)That 137 Eastgate, Louth (105.36) Tree Preservation Order be confirmed (made permanent). Decided Open
2 Sep 2026 Tree Preservation Order: Land adjacent 116C Horncastle Road, Roughton Moor (215.31)That land adjacent to 116C Horncastle Road, Roughton Moor (215.31) Tree Preservation Order be confirmed (made permane... Decided Open
2 Sep 2026 00489/26/fulThat the application be approved. Approved Open
2 Jul 2026 03860/25/fulThat this Council resolve to grant planning permission with the application being referred to the Secretary of State ... Decided Open
20 May 2026 Election of ChairmanThat Councillor Stephen Eyre be elected Chairman of the Planning Committee for the Council year 2026/27. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies