Item121
Resolved
RESOLVED That the application be approved subject to conditions:- The development hereby permitted must be begun not later than the expiration of three years beginning with the date of this permission. The development hereby permitted shall be completed in accordance with the following approved plans; Plan No. J1721 (08) 07 Received by the LPA on 11/12/18. Plan No. J1721 (08) 22 Received by the LPA on 11/12/18. Plan No. J1721 (08) 23 Received by the LPA on 11/12/18. Plan No. J1721 (08) 24 Received by the LPA on 11/12/18. Plan No. J1721 (08) 25 Received by the LPA on 11/12/18. Before any works above the damp proof course a surface water strategy shall be submitted to and approved in writing by the Local Planning Authority. No building shall be occupied until the works have been carried out in accordance with the surface water strategy so approved. Before any works above the damp proof course a foul water strategy shall be submitted to and approved in writing by the Local Planning Authority. No building shall be occupied until the works have been carried out in accordance with the foul water strategy so approved. Before any works above the damp proof course a schedule of external materials, including samples where requested, to be used in the construction of ... view the full minutes text for item 121.
Word for word from the decision East Lindsey published for this meeting.
Source: democracy.e-lindsey.gov.uk