Resolved
RESOLVED That the briefing paper be noted.
Planning Committee noted this item on Thursday 5 December 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the briefing paper be noted.
PLANNING COMMITTEE
BRIEFING PAPER – PLANNING ENFORCEMENT
5th December 2019
1.0INTRODUCTION
1.1This briefing paper is the first in a series that will be reported to the Committee in order to keep Members informed of the work of the Planning Enforcement Service.
1.2The Service has, over the past four years gone through a period of difficulty and also change. At one point, with staff leaving there was only the Principal Enforcement Officer and one other member of staff in the team, which led to a backlog of cases, reaching such a point that in the end the Council had to employ a consultant to help with the work load.
1.3Earlier in the year, it was felt that the Planning Enforcement Service needed to be relooked at, staffing levels were nearly back to full capacity with only one post still vacant and it was the right time for a process and procedure review, this also coincided with a minor restructure in the Development Management Service.
2.0THE SERVICE
2.1Set out below is a table showing the total number of complaints received each year since 2016/2017. For 2019/2020, the number of cases has been extrapolated up to March 2020.
Enforcement Complaints
995 879 829 702
2016/2017 2017/2018 2018/2019 2019/2020
2.2The chart below shows the number of Enforcement Notices served for the period January 2019 to June 2019 for all shire district councils. East Lindsey is number 1, followed by Epping Forest and Maidstone. No of Enforcement Notices served to June 2019 - Shire Districts EAST LINDSEY 49 EPPING FOREST 40 MAIDSTONE 35 GEDLING 34 MENDIP 33 WYCOMBE 28 MID DEVON 25 KING'S LYNN AND WEST NORFOLK 25 BASILDON 24 NEWARK AND SHERWOOD 20 0 10 20 30 40 50 60
2.3Whilst this result is really positive, given the difficulties the team have had and the number of cases each year the service is dealing with. However, it was felt that the decision about when and when not to take action should be speeded up. In order to do this a number of changes were made.
2.4When a complaint was made, the process was, that officers would go out on site, conclude that there was or was not a breach of planning control and then write to those persons that were responsible to inform them that they had breached the planning regulations. They requested that a planning application be submitted to regularise the breach or that the breach was to be removed/remediated. If no application was submitted the officer would then go out again and check if action had happened on site. It was only after this second site visit to establish whether the breach had been removed/remedied that the expediency test was carried out and the decision made to take action or not.
2.5It was felt that this was a time-consuming process and left those making complaints and those who had breached the regulations with a period of time when it was not clear what the Council`s actions would be. Also the Principle Officer of the team, who also had their own caseload of work was spending time making the expediency decision as well as managing the team.
2.6Clients of the Planning Enforcement Service who did submit a planning application also had to deal with a different service (Development Management) in the Council for the determination of their application and this could be someone who did not know about their case and they had no “relationship” with in terms of customer service.
2.7Therefore a review of the processes was carried out and the following has been changed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning Enforcement:Report | 3 pages | DownloadRead as text |
Follow Planning Committee at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Tree Preservation Order: 137, Eastgate, Louth (105.36)That 137 Eastgate, Louth (105.36) Tree Preservation Order be confirmed (made permanent). | Decided | Open |
| 2 Sep 2026 | Tree Preservation Order: Land adjacent 116C Horncastle Road, Roughton Moor (215.31)That land adjacent to 116C Horncastle Road, Roughton Moor (215.31) Tree Preservation Order be confirmed (made permane... | Decided | Open |
| 2 Sep 2026 | 00489/26/fulThat the application be approved. | Approved | Open |
| 2 Jul 2026 | 03860/25/fulThat this Council resolve to grant planning permission with the application being referred to the Secretary of State ... | Decided | Open |
| 20 May 2026 | Election of ChairmanThat Councillor Stephen Eyre be elected Chairman of the Planning Committee for the Council year 2026/27. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.