RESOLVED That prior approval be granted subject to the following conditions:- 1. The development must be begun not later than the expiration of five years beginning with the date of this approval. 2. The development hereby permitted shall be completed in accordance with the following approved plans; Plan No. 306296-01-101-MD001 1.A Received by the LPA on 20/01/2020. Plan No. 306296-00-004-MD001 1.A Received by the LPA on 20/01/2020. Plan No. 306296-01-100-MD001 1.A Received by the LPA on 20/01/2020. Plan No. 306296-01-150-MD001 1.A Received by the LPA on 20/01/2020 3. The mast and associated equipment shall be dismantled and removed from the site within three months from the date of it no longer being operational.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
PROPOSAL: Determination of whether or not prior approval is required for the siting and appearance of the proposed smart metering pole to the maximum height of 8 metres and associated antennas, 2no. bollards and equipment enclosure. LOCATION: LAYBY OFF, RAITHBY TOP, RAITHBY CUM MALTBY
1.0REASONS FOR COMMITTEE CONSIDERATION
1.1The application is referred to Planning Committee because it is felt that the number of representations received and the interest of the Ward Councillor requires a Committee consideration.
2.0THE SITE AND SURROUNDINGS
2.1The site is in open countryside to the north west of the main body of the village of Raithby cum Maltby on land that rises from the village towards Raithby Top and the A153 where there are four houses. The site and surrounding area are within landscape character type area G1- 'Binbrook to Tetford Wolds Farmland' as identified in the Council's Landscape Character Assessment. The key characteristics of this area are described as including, open elevated plateau with rolling hills and valleys, views to big skies, very tranquil, distinctive and intact rural landscape and an area with a high level of landscape and nature conservation protection given its location within the Lincolnshire Wolds Area of Outstanding Natural Beauty (AONB). The Landscape Character Assessment considers the area to have an overall landscape character sensitivity of moderate to high.
2.2The site of the Smart Metering pole and its associated equipment is between a field boundary hedge and the rear of a roughly gravelled lay- by. Agricultural land directly adjoins the site to its north and is also on the opposite side of the road to the south of the site. A two-storey residential barn conversion is sited to the NE of the site. The proposed pole is approximately 24m from the end of is garden. Other residential properties are further away from the site being located on the eastern site of the A153. A mature deciduous Ash tree of approximately 14m in height and a much small tree stand close to the site in the field boundary hedge to its North East. Telegraph poles approximately 8m high run along the opposite side of the road to the smart metering pole site.
2.3The site is in flood zone 1 - low risk.
3.0DESCRIPTION OF THE PROPOSAL
3.1The application seeks determination of whether or not prior approval is required for the siting and appearance of the proposed Smart Metering pole which would have a maximum height of 8 metres with associated antenna mounted on the top which would take the overall height of the structure to approximately 9.9m and a diameter of about 0.2m at its widest part as it is of a tapered design. In addition, two bollards, a 0.6m x 0.1m and 0.9m a high equipment enclosure and smart metering equipment enclosure, power supply cabinet about 30cm x 15cm and 1m high are proposed. The submission states that the mast is required to provide coverage to the settlement of Raithby cum Maltby. The mast is not proposed to be coloured, but the applicants advise that it could be coloured if it was felt appropriate.
3.2The application is accompanied by a supporting letter, a statement in support of the application incorporating a design and access statement, a Department of Energy and Climate Change Document about the Smart Metering System and a document declaring conformity with Public RF exposure guidelines (formerly known as an ICNIRP Declaration).
3.3The main points of the supporting letter and statement are summarised below:
Benefits of the Smart Metering Network
The application is to help enable Government Proposals to roll out smart electricity and gas meters to homes and small businesses between 2014 and 2020.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.