Resolved
RESOLVED That the report be noted.
Planning Policy Committee noted this item on Thursday 22 July 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the report be noted.
This report relates to the 5 year housing supply calculation that the Council, as Local Planning Authority, must produce on an annual basis. It also covers the National Housing Delivery Test and includes the most recent result.
That this report be noted by members.
This report is intended to provide an update to Members on the current 5 Year Housing Supply and National Housing Delivery Test result.
OTHER OPTIONS CONSIDERED
n/a – there is a national requirement to produce these figures. 1.0 Introduction
1.1The National Planning Policy Framework in paragraph 73 requires Local planning authorities to: “identify and update annually a supply of specific deliverable sites sufficient to provide a minimum of five years’ worth of housing against their housing requirement set out in adopted strategic policies.”
1.2The Council maintains a position statement of all planning permissions granted for housing, which is used to produce the housing supply figures. The figures are produced once a year and looks at how much housing the Council has provided, and what pipeline sites are likely to come forwards in the next 5 year period.
1.3The Housing Delivery Test is a new national indicator. It was introduced in November 2018 and was first published in February 2019. The production of this indicator is managed by central government. The output of this is a percentage that shows whether the Council is delivering sufficient housing.
1.4The HDT is produced annually in November of each year. It is based on the preceding three years to that November. The test uses the housing need over that 3 year period and the number of houses actually delivered. These are placed into a formulae, which produces the percentage.
1.5If the percentage is 95% or above, the test result is considered to be a ‘pass’ and no further action is required. Between 85% and 95%, an action plan is required.
1.6If a Council drops below 85%, then the 20% buffer must be applied to the 5 year housing supply calculation. As can be seen from the figure1 below, as of 2020, Councils dropping below 75% will have to apply the presumption in favour of sustainable development found in paragraph 11 of the National Planning Policy Framework. Figure 1: source: https://lichfields.uk/media/4468/housing-delivery-test_september-2018pdf.pdf
1.7Further information regarding the National Housing Delivery Test can be found using the following link: https://www.gov.uk/government/publications/housing-delivery-test- 2019-measurement
2.05 Year Housing Supply
2.1The full 5-year supply calculation can be found in appendix a). The calculation is worked out with two different buffers. The buffers give leeway to allow for the fact that some of the sites identified might not actually be developed for various reasons.
2.2The first is a 5% buffer, the second is a 20% buffer. If the Council consistently under delivers on the housing it needs to over a 3 year period, the bigger buffer of 20% must be applied. The Council is currently performing at an acceptable level in terms of delivery. Therefore the 5% buffer is the appropriate one to use. The 20% buffer calculation is included just for reference.
2.3It can be seen from the calculation in appendix a) that the Council currently has a 6.06 years supply with the 5% buffer. This provides a robust margin above the 5 year minimum. The most recent annual figures are shown in the table below. Period 5 Year Supply (5% buffer) 2018-19 5.42 years 2019-20 5.92 years 2020-21 6.06 years
3.0National Housing Delivery Test
3.1The National Housing Delivery Test (HDT) has the following result for East Lindsey:
Period Need Delivery Result 2016-2019 1189 1298 109% 2017-2020 1148 1494 130% Figure 2: https://www.gov.uk/government/publications/housing-delivery-test-2020-measurement
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
5 year supply 210722Appendix A | 4 pages | Download |
PDF |
Housing Supply:Report | 6 pages | DownloadRead as text |
Follow Planning Policy Committee at East Lindsey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 May 2026 | Election of Vice ChairmanThat Councillor Terry Aldridge be elected Vice-Chairman of the Planning Policy Committee for the Council year 2026/27. | Decided | Open |
| 14 May 2026 | Conservation Area AppraisalsRESOLVED That the Committee noted and endorsed the conservation area appraisals and South East Lincolnshire Tradition... | Noted | Open |
| 21 May 2025 | Election of Vice-ChairmanThat Councillor Terry Aldridge be elected Vice-Chairman of the Planning Policy Committee for the Council year 2025/26. | Decided | Open |
| 17 Oct 2024 | ActionsIt was agreed that the Actions would be deferred to the next Committee Meeting. | Agreed | Open |
| 22 May 2024 | Election of Vice-ChairmanThat Councillor Terry Aldridge be elected Vice-Chairman of the Planning Policy Committee for the Council year 2024/25. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.