Vehicle parking improvements to the Waste Depot, Fairfield Industrial Estate, Louth
ApprovedExecutive1 paper
AI summaryEast Lindsey Executive Board approves £500,000 of capital funding to expand vehicle parking at Louth waste depot ahead of food waste collections starting October 2026.
What happens nextProcurement of worksAssets Team to procure via competitive quotes
Who it affectsWaste depot staff and operationsLouth depot, Fairfield Industrial Estate
What was decided
The Executive Board approved adding £500,000 to the 2026/27 Capital Programme to fund vehicle parking improvements at the Louth waste depot. Report P4
The Board approved reallocating £185,000 of DEFRA revenue funding to capital expenditure, making a total capital investment of £500,000. Report P29
The Board noted the remaining £58,250 revenue grant will be used to support wider depot enhancement initiatives. Report P4, P29
Why
Food waste collections starting in October 2026 will require an additional ten HGVs, 30 staff and their vehicles to be based at the depot, and current parking is insufficient. Report 2.1, P5
The depot, built in 2008, has had only minor surfacing works since and serves around 80 staff daily, with health and safety standards needing to be maintained. Report 1.1, 1.2, P5
Failure to increase parking capacity could harm operational efficiency and create health and safety risks from vehicle movements on the site. Report P30
What happens next
The Assets Team will procure the parking improvement works in line with the Council's Contract Procedure Rules, with the final cost set by a competitive quotation process. Report 2.3, 2.4, P36
Food waste collections are scheduled to begin in October 2026, which the improvements are timed to support. Report 2.1
The money
£500,000 Addition to 2026/27 Capital Programme for vehicle parking improvements at Louth waste depot Report P4, 2.3
£558,250 Total DEFRA grant award to support depot infrastructure improvements Report P2, P29
£315,000 Capital element of DEFRA funding award Report P29
£243,250 Revenue element of DEFRA funding award Report P29
£185,000 Revenue funding reallocated from DEFRA to capital expenditure Report P29
£58,250 Remaining DEFRA revenue grant to support wider depot enhancement initiatives Report P4, P29
Options considered
Rejected: Do nothing. Would fail to address additional capacity requirements or the need to maintain a safe operational depot Report P7
Implications
Financial: The DEFRA grant allows flexibility between revenue and capital, so £185,000 of revenue funding can be reallocated to capital, leaving £58,250 for other service enhancements. Report P29
Risk: Without increased parking, operational efficiency and health and safety could be affected by vehicle movements and parking arrangements at the depot. Report P30
Staffing: Current infrastructure does not adequately meet current or future workforce capacity needs, particularly for vehicle parking. Report P24
Other: The proposals support the Council's environmental priorities by enabling food waste collections and improve the working environment for operational staff. Report P20, P22
Legal: No constitutional or legal implications identified. Report P26
Who and where
Around 80 staff currently attending the Louth waste depot daily Report 1.2
An additional 30 staff due to be based at the depot for food waste collections Report 2.1
Waste, Markets and Neighbourhoods vehicle operators using the concrete parking area Report 1.1
Residents in East Lindsey receiving the new food waste collection service Report 2.1, P20
October 2026: Introduction of food waste collections requiring additional fleet and staff at the depot Report 2.1
2026/27: £500,000 capital allocation to be used for vehicle parking improvements Report P4
Plain English for the jargon
DEFRA: Department for Environment, Food and Rural Affairs
HGV: Heavy Goods Vehicle
Capital Programme: The council's planned spending on long-term assets and infrastructure
Revenue funding: Day-to-day running costs, as opposed to capital investment in assets
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
That the addition of £500,000 to the 2026/27 Capital Programme to fund the improvements to vehicle parking provision at the waste depot, on Fairfield Industrial Estate, Louth be approved. 2. That reallocating £185,000 of the revenue funding from DEFRA to capital expenditure be approved. 3. That, as per the intentions of the grant award from DEFRA, the remaining £58,250 revenue grant will be used to support wider depot enhancement initiatives be noted.
Word for word from the decision East Lindsey published for this meeting.Source: democracy.e-lindsey.gov.uk
This report sets out the need for improvements to the waste depot located on Fairfield Industrial estate, Louth. The works are required to accommodate the increase in fleet vehicles, staff, and staff vehicles associated with the introduction of food waste collections, whilst ensuring the continued safe operation of the depot.
An appeal to Defra regarding this additional operational requirement resulted in an award of £558,250 to support depot infrastructure improvements.
The Executive Board is being asked to support the recommendations to amend the Capital Programme, reallocating the £558,250 funding awarded by Defra to the Council.
Recommendation 1. That the Executive Board approves the addition of £500,000 to the 2026/27 Capital Programme to fund the improvements to vehicle parking provision at the waste depot, on Fairfield Industrial Estate, Louth. 2. That the Executive Board approves reallocating £185,000 of the revenue funding from DEFRA to capital expenditure. 3. That the Executive Board notes that, as per the intentions of the grant award from DEFRA, the remaining £58,250 revenue grant will be used to support wider depot enhancement initiatives.
Reasons for recommendations
The existing depot requires improvement to its vehicle parking provision to accommodate the additional fleet vehicles required for food waste collections, the increased number of staff vehicles, and to ensure health and safety standards are maintained within this operational environment.
Other Options Considered
Do nothing. This option is not recommended as it would fail to address the additional capacity requirements, or the need to maintain a safe operational depot.
Background
1.1The waste depot at Louth was constructed in 2008 adjacent to the County Council’s Waste Transfer Station and Household Waste Recycling Centre on Fairfield Industrial Estate, Louth. The site comprises a portacabin used for office and welfare accommodation, a second portacabin used as a meeting room and relocated from the previous depot building at Manby Park, a gravel staff car park, and a concrete parking area for Waste, Markets and Neighbourhoods vehicles.
1.2Only minor surfacing improvements have been undertaken since the site was constructed and further works to vehicle parking are now required to maintain a safe and effective operational depot. Approximately 80 staff currently attend the site each day, with many arriving for shifts commencing at 5.30am.
2. Report
2.1The introduction of food waste collections in October 2026 will require an additional ten HGVs to be based at Louth depot, together with a corresponding increase of 30 staff and their associated vehicles. Current parking arrangements are insufficient to accommodate this increase. 2.2 An appeal to Defra regarding this additional operational requirement was successful and resulted in an award of £558,250 to support depot infrastructure improvements. This funding has been received and allocated to reserves.
2.3The Assets Team will procure the works required to deliver the parking improvements. Initial soft market testing has indicated an estimated project cost in the region of £500,000. It is therefore recommended that £500,000 is added to the Capital programme, funded from the Defra award currently held within the Council’s reserves.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2026/27 Quarter 1 Finance Update1) That the General Fund forecast revenue outturn position for 2026/27 being an underspend of £56k as detailed in Tab...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.