Transport and Digital Connectivity Committee, Thursday 15 January 2026 at 11.00am

Transport Investment Programme Delivery Update

Agreed Committee 1 paper

AI summaryEMCCA Transport and Digital Connectivity Committee noted the 2025/26 Transport Investment Programme is on track, with £151m forecast spend against a £184m allocation. Officers will explore options to maximise in year delivery through change control processes.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCommittee noted successful 2025/26 delivery and asked officers to maximise in year spend
Money£151m forecast / £184m allocationForecast year end spend against total 2025/26 allocation
What happens nextNot stated
Who it affectsEast Midlands transport networkFour Constituent Authorities and EMCCA region wide users

What was decided

The Committee unanimously noted the successful progress of delivery of the 2025/26 Transport Investment Programme. Report 2.1, 2.3

Officers will consider options to maximise the opportunity for in year delivery and present actions through change control governance processes. Report 3.4

Why

Delivery across the region remains robust, with strong in year spend and delivery forecasts following the first significant new investment since EMCCA's formation. Report 2.1, 2.2, 3.1

New funding, including £22m of additional Highways Maintenance Block and £66m from the Transport for City Regions programme, has enabled a much larger programme than 2024/25. Report 2.2, 3.1

Some allocations are constrained by external factors, such as DfT's hard spending deadline for legacy BSIP funding by March 2026 and delays in MRN approvals, so not all funds can be spent this year. Report P33, 2.3

What happens next

Officers will work collaboratively to identify further opportunities for early delivery without compromising the long term ambition, reporting through change control governance. Report 3.4

Construction of the A614/A6097 major road network scheme in Nottinghamshire is due to begin in summer 2026, with deferred funding to be carried into 2026/27. Report P28, P33

Onsite construction for the Merrill Way/A514/Boulton Lane junction improvements in Derby is set to start in January 2026, and ground investigation work for the Chesterfield Staveley Regeneration Route continues into 2026/27. Report P24, P26

The money

  • Over £183.7 million Total funding secured for 2025/26 across grants Report P5, 3.1
  • £22 million Additional Highways Maintenance Block funding in 2025/26 Report 2.2
  • £66 million Transport for City Regions (TCR) grant to EMCCA Report 2.2, 3.1
  • £151m Forecast year end spend for 2025/26 Report 2.3, P42
  • £184m Combined 2025/26 transport allocation Report 2.3, P42
  • £55m Approximate increase in regional delivery versus 2024/25 Report 2.3
  • £19.523m BSIP revenue applied to bus transition programme Report P9
  • £13m EMCCA retained funding for regional commissioning schemes Report P22
  • £3m EMCCA contribution to Merrill Way/A514/Boulton Lane junction improvements (Derby) Report P23
  • £2.5m EMCCA contribution to Chesterfield Staveley Regeneration Route ground investigation (Derbyshire) Report P25
  • £7.5m EMCCA contribution to A614/A6097 major road network scheme (Nottinghamshire) Report P27
  • more than £24m DfT Major Route Network funding secured for A614/6097 scheme via a strong business case Report P21
  • £38.8m Actual spend reported by Constituent Authorities by start of December 2025 Report P30
  • £112m Forecast spend for Q3 and Q4 2025/26 Report P30
  • well over £110m Combined Highways Maintenance Block and TCR capital highways programme for 2025/26 Report P33

Implications

  • Financial: Forecast spend of £151m against a £184m allocation reflects proactive programme management and permitted deferral of funding into 2026/27 in line with grant conditions and Department for Transport guidance. Report P42
  • Financial: Deferred funding remains ringfenced for transport purposes and will be incorporated into future year programmes through established governance and budget setting processes. Report P43
  • Financial: No additional financial risks or pressures arise from this report beyond those already managed within approved transport capital and revenue budgets. Report P44
  • Legal: The Committee is able to agree the priorities and guidelines for EMCCA's strategy for transport investment in accordance with its Terms of Reference, with no other legal implications identified. Report 6.2
  • Other: There are no direct impacts on other EMCCA directorates at programme level, with legislative compliance, procurement and communication managed at individual scheme level by the lead sponsor. Report P46

Who and where

  • Derby City Council as a Constituent Authority and BSIP Lead Authority Report P8, 3.1
  • Derbyshire County Council as a Constituent Authority Report P8, 3.1
  • Nottingham City Council as a Constituent Authority Report P8, 3.1
  • Nottinghamshire County Council as a Constituent Authority Report P8, 3.1
  • East Midlands Combined County Authority (EMCCA) Report 3.1, 4.1
  • Bus users across the East Midlands, through BSIP funded improvements
  • Residents who walk, wheel or cycle, through Active Travel England funded schemes Report 4.4
  • Residents without off street parking who may use LEVI funded EV chargepoints Report 4.5

Timeline

  • 10/03/2025: EMCCA Board approved the 2025/26 Transport Investment Programme Report P47, 4.1
  • August 2025: Monthly delivery liaison meetings with Constituent Councils began Report P10
  • 18/9/2025: DfT confirmed Full Business Case approval for the A614/A6097 scheme Report P28
  • November 2025: Derbyshire Council Cabinet approval for retaining walls and landslips urgent repair programme Report P33
  • Start of December 2025: Constituent Authorities reported around £38.8m of actual spend year to date Report P30
  • January 2026: Onsite construction of Merrill Way/A514/Boulton Lane junction improvements scheduled to start Report P24
  • Early 2026: Replacement of Victorian railings on Duffield Road, Derby, planned Report P14
  • March 2026: Retaining walls programme scheduled to complete; BSIP legacy funding hard spending deadline Report P33
  • Spring/summer 2026: Landslips ground works in Derbyshire planned to start Report P33
  • Summer 2026: A614/A6097 major road network scheme construction due to commence Report P28, P33
  • 2026/27: Deferred 2025/26 funding to be incorporated into future year programmes Report P43, 2.3
  • 2027 to 2032: National five year TCR settlement period Report 4.1

Plain English for the jargon

  • EMCCA: East Midlands Combined County Authority, the regional combined authority covering Derby, Derbyshire, Nottingham and Nottinghamshire.
  • TCR: Transport for City Regions, a national capital grant programme for Mayoral Combined Authorities, formerly known as CRSTS.
  • HMB: Highways Maintenance Block, baseline government funding for local road maintenance.
  • ITB: Integrated Transport Block, baseline government funding for small scale transport improvements.
  • BSIP: Bus Service Improvement Plan, a government grant programme to improve bus reliability, affordability and accessibility.
  • ATF5: Active Travel Fund 5, a capital grant administered by Active Travel England for walking and cycling infrastructure.
  • CATF: Consolidated Active Travel Fund, combining the former capital and revenue active travel streams for 2025/26.
  • LEVI: Local Electric Vehicle Infrastructure Fund, funded by the Office for Zero Emission Vehicles to expand on street EV charging.
  • SAF: Single Assurance Framework, EMCCA's governance framework for programme oversight and assurance.
  • MRN: Major Route Network, a DfT designation of strategically important local authority roads.
  • LLM Programme: Large Local Major Programme, a DfT funding stream for large local transport schemes.
  • FBC: Full Business Case, the detailed final stage of a transport scheme business case.
  • DfT: Department for Transport.
  • ATE: Active Travel England, the government body administering active travel funding.
  • OZEV: Office for Zero Emission Vehicles, the government unit funding EV infrastructure programmes.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

RESOLVED to unanimously agree: a) That the successful progress of the delivery of the Transport Investment Programme for 2025/26 be noted. b) That officers would consider options to maximise the opportunity for in-year delivery and present actions through the change control governance processes to administer these.
Word for word from the decision East Midlands Combined County Authority published for this meeting. Source: democracy.eastmidlands-cca.gov.uk

Follow this further

Built from East Midlands Combined County Authority's papers

What the report saysPro

Report to Transport and Digital Connectivity Committee

Executive summary

2.1This report provides an overview of programme delivery and financial performance across EMCCA’s transport investment portfolio for 2025/26. Delivery across the region remains robust, with schemes progressing well and demonstrating strong in-year spend and delivery forecasts. Authorities have strategically prioritised delivery of activities with more immediate impacts, in line with EMCCA guidance, to maximise impact and showcase the Combined Authority’s ability to deliver at pace.

2.2This year marks the first significant new investment for the Constituent Authorities, including an additional £22 million in Highways Maintenance Block (HMB) funding and £66 million from the Transport for City Regions (TCR) programme. This investment follows years of national underinvestment in transport across the East Midlands and a reliance on single-year settlements, which created well-documented financial uncertainties and made long-term planning challenging for local authorities.

Alongside this new funding, the year has also seen the introduction of new governance arrangements to support programme monitoring and delivery in line with regulatory and Single Assurance Framework (SAF) requirements. Constituent Authorities have worked hard to remodel internal systems, processes, and governance to meet these standards, transitioning from direct reporting to the funding body to coordinated oversight through EMCCA. This shift has required considerable effort and adaptability, with partners navigating new assurance processes and adopting more collaborative ways of working.

2.3For 2025/26, the total forecast year-end spend is £151m from a combined allocation of £184m, representing an increase in regional delivery of approximately £55m compared with 2024/25. The remaining allocation can be deferred into 2026/27, in line with proactive programme management principles and funding guidance, further opportunities to maximise the level of delivery in-year will be considered.

3. Proposal/update

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transport Investment Programme Delivery UpdateReport 203 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 18 attended
MB
Councillor Mick BartonChair, present
AM
Councillor Anthony McKeownVice-Chair, present
MC
Mayor Claire WardConstituent Member, present
HD
Councillor Hardyal DhindsaConstituent Member, apologies
CS
Councillor Carmel SwanConstituent Member, present
CW
Councillor Carol WoodConstituent Member, present
DM
Councillor David MellenConstituent Member, present
CH
Councillor Charlotte HillConstituent Member, present
LW
Councillor Linda WoodingsConstituent Member, present
BB
Councillor Bert BinghamConstituent Member, present
SF
Councillor Steve FlitterNon-Constituent Member, present
NB
Councillor Nigel BarkerNon-Constituent Member, present

All 18 on the meeting page

On this subject at East Midlands Combined County Authority

Search all
  1. Transport Investment Programme Delivery UpdateThis decision
  2. Transport Investment Programme AllocationsApproved
  3. Transport Investment Programme - Draft AllocationsAgreed
  4. Transport Investment Programme 2026/27 - 2028/29Approved
  5. Transport Investment ProgrammeAgreed
  6. Transport Investment ProgrammeAgreed

More from East Midlands Combined County Authority Transport and Digital Connectivity Committee

All decisions
MeetingDecisionOutcome
2 Apr 2026 Minutes of the Previous MeetingRESOLVED to unanimously agree: That the minutes of the meeting of the Transport & Digital Connectivity Committee held... Agreed Open
2 Apr 2026 Transport Investment Programme - Draft AllocationsRESOLVED to unanimously agree that: a) In considering the options presented for allocating further funding from the M... Agreed Open
2 Apr 2026 Transport & Digital Connectivity Committee Work ProgrammeRESOLVED to unanimously agree that: a) The draft work programme as presented be approved, subject to the additions no... Agreed Open
19 Feb 2026 Minutes of Previous MeetingRESOLVED to unanimously agree: That the minutes of the meeting of the Transport and Digital Connectivity Committee he... Agreed Open
19 Feb 2026 Transition of Bus Operations FunctionsRESOLVED to unanimously agree: a) To note and welcome the substantial completion of the transition of bus operations ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies