Apologies for Absence
To receive any apologies for absence.
The EMCCA Board approved a £470.96m transport investment programme for 2026/27 to 2028/29, £15.35m for seven regional projects, a three-year Corporate Plan, and agreed to prepare a Spatial Development Strategy for the region. Members also approved taking on the East Midlands Freeport Accountable Body role from 1 April 2026.
What the committee will consider, in order, with every paper attached to its item. East Midlands Outcomes Framework and EMCCA Corporate Plan 2026-29 is the main business.
To receive any apologies for absence.
To receive any declarations of interest.
Members of the public may ask questions if they have given notice and provided the text of the question to Governance Services ( [email protected] ) no later than 5pm on Monday 2 nd March 2026 and include the name and address of the questioner and the name of the Member to whom the questioner would like the question put. The total time set aside for such questions and answers will be limited to 30...
To approve as a correct record the minutes of the EMCCA Board meeting held on 26 January 2026
Decision: RESOLVED to unanimously agree: That the minutes of the meeting of the EMCCA Board held on 26 January 2026 be approved as a correct record. Decision page
To receive a Mayoral update on key activity since the previous meeting of the EMCCA Board.
To seek the Board’s approval and adoption of the East Midlands Outcomes Framework and EMCCA Corporate Plan 2026-29
Decision: EMCCA Board: a) Approved and adopted the East Midlands Outcomes Framework as the strategic basis for defining, monitoring and reporting progress against the region’s long-term ambitions set out in the East Midlands Growth Plan and Inclusive Growth Framework. b) Approved the EMCCA Corporate Plan 2026-29 as the organisation’s medium-term delivery plan, as the successor to the 2025-26 plan previously agreed by the Board. Decision page
To seek approval to commence preparation of a Spatial Development Strategy (SDS) for the EMCCA area and update the Board on the emerging functions of EMCCA as a Strategic Planning Authority (SPA).
Decision: EMCCA Board: a) Noted the statutory requirement for the Combined Authority to prepare a Spatial Development Strategy (SDS). b) Approved the preparation of a Spatial Development Strategy (SDS) for the East Midlands Combined County Authority (EMCCA) area and noted the indicative timetable to adopt an SDS by 2028. c) Approved the following approach: i. Regular updates to be considered through the Housing and Land Committee and periodic consideration at the Overview and Scrutiny Committee to inform... Decision page
To seek East Midlands Combined County Authority (EMCCA) approval for a range of local transport allocations to take effect from the beginning of the 2026/27 financial year. The report outlines the funding opportunity, explains the collaborative processes applied to the development of this proposal and details the allocations being requested so that the Board can make a decision on the awards.
Decision: EMCCA Board: a) Approved the Transport Investment Programme allocations and distribution of £470.96m for the period 2026/27 to 2028/29 from the region’s Transport for City Regions award. b) Agreed that the allocations approved as a result of this report be used to create the Transport for City Regions Delivery Plan and that sign off of the submission of this plan to the Department for Transport be delegated to the Executive Director of Place. Decision page
To seek Board approval for the transfer of Accountable Body Status of the East Midlands Freeport (EMF) to EMCCA. This means that EMCCA will be the single point of contact with the Ministry for Housing Communities and Local Government on all Lead Authority/Accountable Body issues relating to EMF
Decision: EMCCA Board: a) Approved the transfer of Accountable Body Status for the East Midlands Freeport (EMF) from Leicestershire County Council to the East Midlands Combined County Authority (EMCCA). b) Approved that EMCCA see ‘founding membership’ of EMF to permit the appointment of a Director to the Board (subject to approval by the EMF Board). c) Approved the appointment of the: Executive Director of Place to the EMF Board as EMCCA’s nominated director, EMCCA Chief Executive as Member... Decision page
To provide the Board with an overview of the Quarter 3 (Q3) forecast position on both revenue and capital for the 2025/26 financial year and provide an update on any significant variances to budget.
Decision: EMCCA Board: a) Noted the Quarter 3 forecast position of the Combined County Authority for the 2025/26 financial year: A forecast spend on revenue of £0.5m below budget. A capital reprofiling of £55m. b) Approved the movement in revenue reserves, which had been reflected in the Q3 forecast and further detailed in Section 5 of the report: £3.3m movement to Transport reserves from the forecast Bus Service Improvement Plan (BSIP) grant. £4m reprofiled to Transport reserves relating to... Decision page
To seek Board approval of the EMCCA Pay Policy Statement 2026, which sets out the Authority’s approach to pay and remuneration for the forthcoming financial year in accordance with statutory requirements.
Decision: EMCCA Board: a) Approved the EMCCA , as required under sections 38-43 of the Localism Act 2011. b) Noted that, following approval, the will be published on the EMCCA website no later than 31 March 2026, in line with statutory requirements. Decision page
To inform the Board of the MDNs, ODNs and decisions taken under urgency provision since the last meeting of the Combined County Authority Board.
Decision: EMCCA Board: a) Noted the decisions taken via urgency provision, Officer Decision Notice and Mayoral Decision Notice. b) Noted the amendments to the Constitution to enter into a local scheme of delegation for the sealing and signing of documentation and to clarify wording in the constitution. Decision page
To receive recommendations from EMCCA’s Investment Committee, Housing and Land Committee and Audit and Governance Committee.
Decision: EMCCA Board: a) Considered and approved the recommendation of the Investment Committee to approve the inclusion of seven projects with an indicative investment value of £15.35m set out in Appendix A of the report onto the EMCCA Investment Pipeline, subject to compliance with the EMCCA Constitution and Single Assurance Framework. b) Considered and approved the following recommendations of the Housing and Land Committee: i) That the EMCCA Board a. formally adopt the East Midlands Retrofit... Decision page
Item 6 is where most of this meeting's papers sit: 3 papers, about 4.1 MB.
To seek the Board’s approval and adoption of the East Midlands Outcomes Framework and EMCCA Corporate Plan 2026-29
This committee has dealt with the subject before.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 19 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 26 January 2026. 3 of its items lead into this meeting; 7 items are new. Point at any item to follow a thread. Procedural items are left out.
The Budget 2026-27 and Medium Term Financial Plan (MTFP) to 2031, The Mayoral Budget 2026-27 and Medium Term Financial Plan (MTFP) to 2031, Local Government Pension Scheme Employer Discretions Policy, Procurement Strategy and 3 more do not return this time.
See the 26 January meetingEvery East Midlands Combined County Authority Board meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
East Midlands Combined County Authority, East Midlands Combined County Authority Board
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the East Midlands Combined County Authority Board, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.