What was decided
The Board noted delivery of Phases 1 and 2, including 21 grant approvals, contracting progress, forecast outputs and lessons learnt. Report 3.2
The Board noted confirmation of a further £57.2m for Phase 3 from MHCLG, including a requirement to contract circa £27.58m by March 2027, and supported continued officer engagement on eligible schemes. Report 2.1, 3.4
The Board delegated authority: to the Executive Director for Place to add schemes to the pipeline; to the Chief Executive in consultation with the Section 73 Officer to approve business cases and funding agreements up to £3M and minor amendments; and to the Mayor in consultation with the four Constituent Council Leaders for any approvals exceeding £3M. Report 3.7, 3.8
Why
The Phase 3 allocation is materially larger than earlier phases and requires contracting of around £27.58m by March 2027, with future year funding conditional on satisfactory progress. Report 3.4, P16
Officers propose focusing on fewer, larger and partnership-led schemes of around £7m to £10m to reduce fragmentation, while still maintaining geographic spread across the region. Report 3.5, P18
The new delegations are intended to streamline approvals and contracting within the tight timetable while keeping oversight through the Housing and Land Committee and Key Decision rules for amounts above £1m. Report 3.7, 3.8
What happens next
Officers will continue engagement with local authorities, registered providers and private developers to progress eligible schemes through due diligence and contracting. Report 2.4, 3.5
The Memorandum of Understanding with MHCLG for Phase 3 will be finalised, setting out the spend profile, milestones and conditions. Report 6.1, P26
Performance updates on the fund, including all decisions taken under the new delegations, will be reported to the Housing and Land Committee. Report 3.8
The money
- £57.2m Phase 3 Brownfield Housing Fund allocation from MHCLG, confirmed March 2026 Report 2.1, P10, 6.1
- £16.8m Phase 1 allocation received in March 2024 Report 3.1
- £19.7m Phase 2 allocation awarded in November 2025 Report P9
- £93.7m Total MHCLG capital allocations across Phases 1 to 3 Report 6.1
- £27.58m Phase 3 amount to be contracted by March 2027 Report 2.1, 3.4, P26
- £1,223,000 RDEL revenue funding to support 2026/27 delivery capacity Report P11, P28
- £30,577,030 Approved grant allocation across 24 schemes in Phases 1 and 2 Report 3.2
- £6.11m Phase 3 year 2 funding Report 3.4
- £6.11m Phase 3 year 3 funding Report 3.4
- £17.4m Phase 3 year 4 funding Report 3.4
Options considered
- Rejected: Continue a broad market approach across many schemes. Exposes the Phase 3 programme to avoidable delivery risks given the scale, pace and conditionality of the allocation Report P16
- Chosen: Focus on fewer, larger partnership-led schemes of around £7m to £10m, while maintaining geographic spread. Reduces fragmentation, improves portfolio manageability, and increases leverage and governance oversight Report 3.5, P18
- Chosen: Delegate approvals of up to £3M to the Chief Executive, with the Mayor and four Constituent Council Leaders approving larger amounts. Provides a proportionate and efficient governance route to meet tight contracting deadlines Report 3.7, 3.8
Implications
- Financial: Future year Phase 3 funding is conditional on satisfactory progress; MHCLG may withhold, reduce or withdraw funding where delivery is insufficient. Report 6.2
- Legal: All allocations must comply with the Single Assurance Framework, MHCLG Memorandum of Understanding, the EMCCA constitution and the Subsidy Control Act 2022, with each scheme requiring appraisal, due diligence, subsidy control compliance, milestones and security arrangements. Report 6.3, P33
- Risk: Decisions above £1m remain Key Decisions subject to 28-day notice and call in; Appendix B is exempt under Schedule 12A of the Local Government Act 1972 due to commercial sensitivity. Report 3.8, 2.3, P35
- Staffing: Capacity to support the fund will be increased beyond its current state, supported by £1.223m of revenue funding for 2026/27. Report P11, P28
Who and where
- Local authorities across the EMCCA region, expected to bring forward a deliverable pipeline of brownfield schemes Report 2.4, 3.5
- Registered providers and private developers with eligible brownfield schemes Report 2.4, 3.5
- Future residents of the 1,765 homes expected from Phases 1 and 2, of which around 705 are planned as affordable Report 2.2, P13
- Homes England, as a partner in aligning with wider strategic pipelines Report 3.6
Timeline
- March 2024: Phase 1 allocation of £16.8m received from MHCLG Report 3.1
- November 2025: Phase 2 allocation of £19.7m awarded Report P9
- March 2026: Phase 3 allocation of £57.2m confirmed Report P10
- 2026/27: £27.58m of Phase 3 to be contracted and £1.223m revenue funding to be deployed Report 3.4, P11, P26
- March 2027: Deadline to contract circa £27.58m of Phase 3 funding Report 2.1
Plain English for the jargon
- EMCCA: East Midlands Combined County Authority
- MHCLG: Ministry of Housing, Communities and Local Government, the government department providing the Brownfield Housing Fund
- RDEL: Resource Departmental Expenditure Limit, the revenue funding stream from MHCLG to support programme delivery
- SAF: Single Assurance Framework, the rules EMCCA must follow when allocating funds
- Key Decision: A decision above £1m that requires 28 days' notice and is subject to call-in by the Overview and Scrutiny Committee