Bid to European Regional Development Fund for low carbon business support programme

Approved Committee 1 paper

Economy approved this item on Tuesday 7 July 2015. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

DECISION 7.2 RESOLVED to approve the submission of a bid to the European Regional Development Fund (ERDF) for a low carbon business support programme, in support of the East Sussex Growth Strategy. Reasons 7.3 The proposed bid will help drive economic growth, and address specific needs and opportunities identified in the East Sussex Growth Strategy (2014-20) and the East Sussex Business Survey (2014). The County Council will make the best use of resources by enabling the County Council’s Energy team to implement energy efficiency projects that will cut the County Council’s energy costs.
Word for word from the decision East Sussex published for this meeting. Source: democracy.eastsussex.gov.uk

Follow this further

Built from East Sussex's papers

What the report saysPro

Report to Economy

Report to: Lead Cabinet Member for Economy

Date of meeting: 7 July 2015

By: Director of Communities, Economy and Transport

Title: Bid to European Regional Development Fund for low carbon business support programme

Purpose: To seek Lead Member approval to submit a bid with South East Local Enterprise Partnership partners for external funding from an EU fund.

RECOMMENDATION: The Lead Member is recommended to approve the submission of a bid to the European Regional Development Fund (ERDF) for low carbon business support programme, in support of the East Sussex Growth Strategy.

1 Background Information 1.1 Partners across the South East Local Enterprise Partnership (SELEP) area are working together to develop a bid to the European Regional Development Fund’s (ERDF) low carbon fund. There is clear evidence that nearly all businesses can improve their profitability by cutting their energy costs but that the majority of businesses in East Sussex have not accessed advice or finance on how to do so (see the East Sussex Business Survey, 2014). It is also apparent that the low carbon environmental goods and services sector (LCEGS) is a key growth sector for East Sussex (see the East Sussex Growth Strategy 2014-20). 1.2 There is a similar picture across the SELEP area. The need to address these points is reflected in the SELEP’s Local Implementation Plan, and the European Regional Development Fund includes a ring-fenced low carbon allocation to help fund the LEP’s low carbon plans. 2 Supporting Information 2.1 The partnership working collectively on the bid is led by Kent County Council and includes Essex County Council, Southend and Thurrock. In East Sussex, the proposal is to divide delivery between:

a) East Sussex County Council (ESCC) – to deliver support to businesses to cut their energy costs (ie. the demand side). The County Council has been delivering a similar and successful programme to local small and medium-sized enterprises (SMEs) for over a decade. This is currently funded by ESCC, via the SME Commission, but will end during 2015. ESCC will also use local suppliers to improve energy efficiency in some of its own buildings;

b) Brighton University – to deliver support to the LCEGS (ie. the supply side), because this will complement the existing five years Green Growth Platform programme that the University is delivering for this sector up to 2018.

2.2The draft partnership budget, key outputs and outcomes are listed in Appendix A. Of the total £18.3m partnership budget, an estimated £3.2m is proposed to be spent in East Sussex, subject to the take up from local SMEs of the services that the programme would offer. The costs to the County Council over 3 years would be:

1) Business Services Department Energy Team existing staff & Salix invest-to-save energy budget - £97,000 2) Environment Team Manager’s time - £36,875 3) Contribution from ESCC’s SME Commission budget - £20,000 4) Environment Team budget - £40,000

Therefore, the resources that the County Council is planning to commit to the programme would lever in significant additional spending within East Sussex. It should be noted that this budget, and the resulting outputs and outcomes, may change as further clarification is received from the Department for Communities and Local Government (DCLG) on eligible costs, funding thresholds etc.

2.3The deadline for the submission of final bids is 27 July. If the project is successful in securing ERDF funding then it’s anticipated that delivery would begin in November 2015, with practical completion in October 2018 and financial completion in January 2019.

2.4A risk register covering the proposed programme is included as Appendix B. In summary, none of the risks are considered significant enough to prevent the submission of the bid.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bid to European Regional Development Fund for low carbon business support programmeReport 211 KB DownloadRead as text

At this meeting

Whole meeting
5MinutesOn the agenda
7Bid to European Regional Development Fund for low carbon business support programmeThis decision

More from East Sussex Economy

All decisions
MeetingDecisionOutcome
24 Jul 2026 East Sussex Local Growth Assurance Framework (ESLGAF) Capital Programme reportRESOLVED to: 1) note the final spend in 2025/26 for the Local Growth Fund and Growing Places Fund programmes as set o... Noted Open
24 Jul 2026 WorkWell programme coordination in partnership with Surrey County Council and Surrey and Sussex Integrated Care BoardRESOLVED to: 1) approve East Sussex County Council’s role as the delivery coordinator for the WorkWell programme in E... Approved Open
17 Mar 2026 Adult Skills Fund: 2026/27 Grant allocation and delivery ArrangementsRESOLVED to: 1) Accept the additional Adult Skills Fund allocation; and 2) Delegate authority to the Director of Comm... Decided Open
22 Jan 2025 Department for Education Skills Bootcamps devolved fundingRESOLVED to: 1) Approve the County Council’s headline proposal for Skills Bootcamps funding to be submitted to the De... Approved Open
25 Nov 2024 Department for Work and Pensions (DWP) Supported Employment programme (Connect to Work)RESOLVED to: 1) Agree that the County Council accepts the request from the DWP to be the Accountable Body for the man... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies