RESOLVED to: (1) approve grant funding, to the value of £16.6m to Sea Change Sussex, subject to planning permission being granted, to fund the delivery of the North Bexhill Access Road; (2) approve grant funding to the value of £1.7m to Sea Change Sussex, subject to approval of the business case by the South East Local Enterprise Partnership’s Accountability Board, to fund the delivery of site infrastructure at the Sovereign Harbour, North Queensway and North Bexhill employment sites; and (3) delegate authority to the Director of Communities, Economy and Transport to approve the terms of any agreements and to take all other necessary actions in respect of recommendations (1) and (2) above. Reasons 27.3 The North Bexhill Access Road is one of the Local Growth Deal schemes to come forward in East Sussex and its delivery will help unlock employment space and create jobs in the A21/A259 Bexhill/Hastings Growth Corridor. Equally the improvement of site infrastructure at Sovereign Harbour, North Queensway and North Bexhill as a Local Growth Scheme will help unlock employment space and create jobs in the A21/A259 and the A22/A27 Eastbourne/South Wealden growth corridors. 27.4 Sea Change Sussex is a key delivery partner for the County Council in achieving its ambitions for driving economic growth in the county.
Word for word from the decision East Sussex published for this meeting.Source: democracy.eastsussex.gov.uk
Report to: Lead Cabinet Member for Strategic Management and Economic Development
Date: 5 February 2016
By: Director of Communities, Economy and Transport
Title: Funding Agreements with Sea Change Sussex – North Bexhill Access Road and Site Infrastructure Investment
Purpose: To seek approval, subject to the necessary planning permission/business case approvals being in place, for the County Council to enter into legal agreements to transfer the Local Growth Fund monies approved by the South East Local Enterprise Partnership to Sea Change Sussex to deliver the North Bexhill Access Road and a Site Infrastructure Investment Package
RECOMMENDATIONS: The Lead Member is recommended to: (1) Approve grant funding, to the value of £16.6m to Sea Change Sussex, subject to planning permission being granted, to fund the delivery of the North Bexhill Access Road; (2) Approve grant funding to the value of £1.7m to Sea Change Sussex, subject to approval of the business case by the South East Local Enterprise Partnership’s Accountability Board, to fund the delivery of site infrastructure at the Sovereign Harbour, North Queensway and North Bexhill employment sites; and (3) Delegate authority to the Director of Communities, Economy and Transport to approve the terms of any agreements and to take all other necessary actions in respect of recommendation 1 above. 1 Background Information 1.1 In March 2014, the South East Local Enterprise Partnership (SE LEP), which comprises businesses, local authorities and education leaders across East Sussex, Essex, Kent, Medway, Southend and Thurrock, submitted their proposals to Government for a Growth Deal to drive economic expansion in the area over the next 6 years up to 2021. Within this was a specific growth plan for East Sussex focussed around its three growth corridors – Newhaven, A22/A27 Eastbourne/South Wealden and the A21/A259 Bexhill/Hastings Growth Corridor. 1.2 The SE LEP’s initial Growth Deal was agreed in July 2014 with a further Growth Deal agreed in February 2015. Within East Sussex, over £71m has been secured to date towards infrastructure projects, with a particular focus on transport schemes that will bring forward new jobs and homes across the county. 1.3 The East Sussex element of the Growth Deal identifies the North Bexhill Access Road as integral to the growth plans in the A21/A259 Bexhill/Hastings Growth Corridor and a site infrastructure investment package as important to delivering jobs and employment space in the A21/A259 and A22/A27 Eastbourne/South Wealden growth corridors. The Growth Deal initially allocates £7.6m of funding for the North Bexhill Access Road and £1.7m towards the site infrastructure package. North Bexhill Access Road
1.4The North Bexhill Access Road, as shown in Appendix 1, comprises a 2.4km single carriageway road link between the A269 and the Bexhill Hastings Link Road (BHLR) with a roundabout at each end and two further roundabouts along the road’s alignment. The road will unlock planned employment growth in North Bexhill identified under Policy BX3 of the 2006 Rother Local Plan with capacity for circa 38,000sqm of employment generating floorspace. The Access Road also provides the road infrastructure to unlock the proposed urban extension in North East Bexhill with potential to directly unlock land for up to approximately 780 new homes. 1.5 Sea Change Sussex, as the promoter of the scheme, submitted a planning application to Rother District Council for the road in October 2014; the District Council will be considering the planning application on 11 February 2016. Following assessment by the SE LEP’s Independent Technical Evaluator (ITE) to ensure the scheme represented good value for money, the business case for the project was approved by the South East LEP’s Accountabilty Board on 13 November 2015. Main construction of the road is expected in March 2016 and is programmed for completion by the end of 2017.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Public and PressIt was RESOLVED to exclude the public and press from the meeting for the remaining agenda items on the grounds that i...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.