DECISION 57.2 RESOLVED to: (1) agree the programme of local transport improvements for 2016/17 set out in appendix 1 of the report with the proviso that no construction works would take place on implementing the Eastbourne Seafront cycle route before a decision has been taken by the DCLG on the Eastbourne Borough Council bye-law that covers the use of the Promenade; (2) agree the allocation of County Council capital funding, development contributions and Local Growth Fund monies towards specific improvements identified in the 2016/17 programme; (3) thank the officers for their work in preparing the programme. Reasons 57.3 The capital programme represents a balanced programme of improvements which will help deliver not only the objectives of the County Council’s Local Transport Plan but also contribute to achieving broader corporate objectives.
Word for word from the decision East Sussex published for this meeting.Source: democracy.eastsussex.gov.uk
Report to Lead Cabinet Member for Transport and Environment
Date 14 March 2016
Report By Director of Communities, Economy and Transport
Title of Report Capital Programme for Local Transport Improvements 2016/17
Purpose of Report To seek approval for the proposed allocation of funds to a specific programme of local transport improvements
RECOMMENDATIONS: The Lead Member is recommended to: (1) Agree the programme of local transport improvements for 2016/17 set out in Appendix 1 to this report; and (2) Agree the allocation of County Council capital funding, development contributions and Local Growth Fund monies towards specific improvements identified in the 2016/17 programme.
1. Background Information
1.1The Capital Programme for Local Transport Improvements sets out a proposed programme of schemes to be developed and delivered in various locations across the county in 2016/17. The programme is funded from a number of sources including a capital allocation from East Sussex County Council, development contributions and funding secured from the Government’s Local Growth Fund through both the South East and Coast to Capital Local Economic Partnerships. A copy of the draft programme is included in Appendix 1.
2. Supporting Information
2.1In May 2011 County Council approved the Local Transport Plan (LTP) 2011 – 2026 which identified the Council’s strategy for transport investment. The strategic approach adopted in the LTP is to invest in infrastructure which delivers sustainable economic growth. This will be achieved by developing schemes which tackle congestion, improve safety for all road users and where practical and appropriate, promote sustainable travel on foot, by bike and by public transport.
2.2The LTP will be complemented by a series of Implementation Plans setting out delivery proposals in line with the priorities set out in the plan of supporting sustainable economic growth and improving safety, health and security for 5 year time periods over its lifetime. The first of the Implementation Plans covered the period 2011/12 to 2015/16; the second Implementation Plan covers the period 2016/17 to 2020/21 and will be considered as a later agenda item in this Lead Member meeting. The content of the Capital Programme for Local Transport Improvements is consistent with the emerging second LTP Implementation Plan.
2.3The programme for 2016/17 has been reviewed to take account of the priorities set out in the Council Plan, LTP and its associated Implementation Plan, as well as ensuring the continuation of schemes commenced in the previous financial year and the availability of external contributions.
2.4A number of priority investment areas are identified in both the LTP and the Implementation Plan. These are Bexhill, Hastings, Eastbourne, Hailsham and South Wealden, Newhaven and Uckfield. The schemes included in the draft programme show a significant investment of County Council funding in local transport improvements in these priority investment areas.
2.5As part of the LTP Implementation Plan, and with a single budget for Local Transport and Road Safety schemes, a more robust, evidence based prioritisation process has been developed to assess requests received for all types of schemes. This new prioritisation framework was approved by the Lead Member for Transport and Environment in September 2011. One of the key elements of this process involves assessing the extent to which scheme requests would meet the objectives of the LTP.
2.6The amount of County Council funding in the current approved Capital Programme for Integrated Transport in 2016-17 amounts to £2.4m. This allocation was approved by County Council on 9 February 2016.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.