Resolved
The Orbis Joint Committee: i . note the forecast zero budget variance at year end on both the joint operating budget and investment fund; and ii. note that Orbis forecast to achieve £1.2m efficiencies by year end.
Orbis Joint Committee noted this item on Monday 18 July 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
The Orbis Joint Committee: i . note the forecast zero budget variance at year end on both the joint operating budget and investment fund; and ii. note that Orbis forecast to achieve £1.2m efficiencies by year end.
The Orbis Joint Committee is asked to:
1. note the forecast zero budget variance at year end on both the joint operating budget and investment fund; and
2. note that Orbis forecast to achieve £1.2m efficiencies by year end.
The Orbis Joint Committee is responsible for ensuring sound financial management of the partnership, overseeing delivering the business plan and monitoring the investment.
DETAILS:
3. The Joint Operating Budget is £53.1m. This includes £1.2m of efficiency savings. The 2016/17 budget for investment to achieve a successful partnership is £3.3m, which includes £0.5m carried forward from 2015/16.
4. As at 31 May 2016, forecast spending across the services is in line with both the Joint Operating Budget and the Orbis Investment Budget., There are, however, some risks which are being closely monitored and may lead to year end variances. Orbis Joint Operating Budget
5. Services are planning to spend to their budgets this year but there are some risks to achieving this.
6. In addition to the savings to be delivered this year, Orbis is expected to deliver further savings of £3.1m in 2017/18 as part of the Business Plan. Since the major budget is staffing, services in the partnership are planning restructures and may deliver some of the savings this year as these changes take place and vacancies are held. This may lead to an underspend in 2016/17.
7. The Business Operations savings are £0.6m, reorganisations have taken place to deliver these but there are still income risks and possible delayed savings from implementing the new e-invoicing system. The service is planning to surmount the income pressure by reviewing the services it offers and the costs of delivering them. The e-invoicing system has been implemented and should realise full year savings from 2017/18.
Table 1: 2016/17 Joint Operating Budget Joint Operating Budget YTD YTD YTD Full Year Full Year Full Year Budget Actual Variance Budget Forecast Variance £000s £000s £000s £000s £000s £000s Business Operations 855 629 -226 5,130 5,130 0 Finance 1,571 1,745 174 9,426 9,426 0 Human Resources 853 429 -424 5,120 5,120 0 Information & Technology 2,884 2,768 -115 17,303 17,303 0 Management 393 136 -257 2,359 2,359 0 Procurement 583 549 -34 3,496 3,496 0 Property 1,712 1,585 -127 10,272 10,272 0 Orbis Net Expenditure 8,851 7,842 -1,009 53,105 53,105 0
Subjective Analysis YTD YTD YTD Full Year Full Year Full Year Budget Actual Variance Budget Forecast Variance £000s £000s £000s £000s £000s £000s
Income -1,704 -2,519 -816 -10,222 -10,222 0
Staffing 9,416 8,885 -531 56,497 56,497 0 Non-staffing 1,138 1,475 337 6,830 6,830 0 Total Expenditure 10,555 10,361 -194 63,327 63,327 0
Orbis Net Expenditure 8,851 7,842 -1,009 53,105 53,105 0
Revenue Contribution YTD YTD YTD Full Year Full Year Full Year Budget Actual Variance Budget Forecast Variance £000s £000s £000s £000s £000s £000s ESCC Contribution to Orbis 2,653 2,350 -302 15,916 15,916 0 SCC Contribution to Orbis 6,198 5,491 -707 37,189 37,189 0 8,851 5,491 -707 37,189 37,189 0 Efficiencies
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
May Budget MonitoringReport | 5 pages | DownloadRead as text |
Follow Orbis Joint Committee at East Sussex and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jan 2021 | Orbis Budget Monitoring reportThe Orbis Joint Committee noted the report . Actions/further information to be provided: Budget preparations for all ... | Noted | Open |
| 16 Oct 2020 | Orbis Performance MonitoringRESOLVED to (1) note the Orbis service performance information presented; (2) advise that service performance informa... | Noted | Open |
| 16 Oct 2020 | Service Spotlight - Business OperationsRESOLVED (1) to thank the staff for their flexibility and commitment during the pandemic; and (2) to note the report. | Noted | Open |
| 28 May 2020 | Orbis Performance MonitoringRESOLVED to note the report | Noted | Open |
| 28 May 2020 | IT & Digital Service SpotlightRESOLVED to thank the staff, in particular in relation to the Covid-19 response, and noted the report. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.