RESOLVED to (1) note the results of the consultation; (2) agree that the proposals for traffic calming along Ghyll Road as set out in the report should be taken forward to construction as part of the 2018/19 Capita Programme for Local Transport Improvements; and (3) agree to explore the feasibility of providing additional traffic calming features in Sheepsetting Lane with a view to include these measures in the scheme. Reasons 22.3 There have been requests from local residents over a number of years for the extension of the existing Tilsmore traffic management scheme into Ghyll Road as traffic speed surveys have shown that drivers are not complying with the current 30 mph speed limit. Whilst the scheme initially sought to address the speed problem in Ghyll Road in the vicinity of Ghyll Bridge, through the design process, the safety audit identified a number of concerns about the high approach speeds to the first of the proposed traffic calming features. This has resulted in exploring a number of alternative scheme options that has made it been necessary to extend the scheme over the whole length of Ghyll Road. 22.4 The results of the public consultation showed significant support for the proposed traffic calming scheme. The detailed design work should include the additional traffic calming measures in Sheepsetting Lane between Cross in Hand Primary School and the A267 as an extension to the existing traffic management scheme if they are considered technically viable and acceptable to the residents of Sheepsetting Lane.
Word for word from the decision East Sussex published for this meeting.Source: democracy.eastsussex.gov.uk
Report to: Lead Cabinet Member for Transport and Environment Date of meeting: 16 October 2017 By: Director of Communities, Economy and Transport Title: Ghyll Road Traffic Calming Proposals, Heathfield Purpose: To consider the results of the consultation on traffic calming proposals along Ghyll Road, Heathfield
RECOMMENDATIONS: The Lead Member is recommended to: (1) Note the results of the public consultation; and (2) Agree that the proposals for traffic calming along Ghyll Road as set out in this report should be taken forward to construction as part of the 2018/19 Capital Programme for Local Transport Improvements; and (3) Agree to explore the feasibility of providing additional traffic calming features in Sheepsetting Lane with a view to include these measures in the scheme.
1. Background 1.1 In 2008 East Sussex County Council introduced a traffic management scheme along Sheepsetting Lane, Tilsmore Road and Mill Road, Heathfield to encourage slower vehicle speeds and to improve road safety. At the time, Ghyll Road was also identified for a potential future traffic management scheme to address concerns about vehicle speeds in the vicinity of Ghyll Bridge but the scheme was not progressed. Recent traffic speed surveys in Ghyll Road show that drivers are not complying with the 30 mph speed limit. In the vicinity of the bridge near Old Ghyll Road junction average speeds have been recorded at 30 mph and 34 mph for northbound and southbound traffic respectively whilst the 85th percentile speeds have been recorded at 35 mph and 40 mph for northbound and southbound traffic respectively. 1.2 The section of Ghyll Road between Leeves Way and Swaines Way has previously been assessed and identified as a potential site for traffic calming measures. It was ranked third on the priority list of sites warranting further assessment in 2010/11. At the time there was only sufficient funding available to progress the further assessment of the first two sites on the list and, as a consequence, a scheme for Ghyll Road was not developed. 1.3 In May 2011 a petition from residents was received requesting the introduction of speed reducing features and parking improvements in Ghyll Road. This was considered at the Lead Member decision making meeting in July 2011 at which a recommendation was approved for the County Council to consider this request as part of their scheme prioritisation process to see if a project can be included in a future year’s Capital Programme for Local Transport Improvements. A scheme to address the speed problem in Ghyll Road in the vicinity of Ghyll Bridge was initially included in the 2013/14 Capital Programme for Local Transport Improvements to develop to a preliminary design. However, through the design process for this scheme, the safety audit identified a number of concerns about the high approach speeds to the first of the proposed traffic calming features. It has therefore been necessary to explore a number of alternative scheme options to overcome these concerns that has resulted in the expansion of the scheme to cover the whole of Ghyll Road. In developing this design, we have engaged with the community through a local residents’ working group. 1.4 A comprehensive traffic calming scheme has now been developed which extends the length of Ghyll Road between the existing priority working build-out north of Tilsmore Road and the junction of Ghyll Road and the B2203 (Theobalds Green) to the south. The scheme extent is detailed in Appendix 1. 1.5 The features that have been proposed comprise a series of speed cushions (17 sets in total) along the length of Ghyll Road and two raised tables; at the junction with Geers Wood and at the existing toucan crossing to the north of Treetops Way junction.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.