Education and Inclusion, Special Educational Needs and Disability approved this item on Monday 22 January 2018. Below is the council's own wording, with the papers it was decided on.
RESOLVED to: approve Option 4, the Council working with Hailsham Community College to lower its age range with effect from September 2019 to establish an all-through school thereby creating an additional 420 primary places (two forms of entry) to serve north Hailsham. Reasons 32.3 Hailsham Community College has demonstrated a long term investment and commitment to improve provision and outcomes for children in Hailsham. The creation of an all-through school will provide the opportunity to expand provision to the primary phase, which will offer further diversity of provision, support the transition of learners from KS3 to KS4 and help improve outcomes at KS4.
Word for word from the decision East Sussex published for this meeting.Source: democracy.eastsussex.gov.uk
Report to Education and Inclusion, Special Educational Needs and Disability
Report to: Lead Member for Education and Inclusion, Special Educational Needs and Disability Date: 22 January 2018 By: Director of Children’s Services Title of report: Primary School Places in Hailsham Purpose of report: To seek Lead Member approval for the Council to work with Hailsham Community College to lower its age range with effect from September 2019 to establish an all-through school thereby creating an additional 420 primary places (two forms of entry) to serve Hailsham.
RECOMMENDATIONS: The Lead Member is recommended to approve Option 4, the Council working with Hailsham Community College to lower its age range with effect from September 2019 to establish an all- through school thereby creating an additional 420 primary places (two forms of entry) to serve north Hailsham.
1. Background 1.1 The birth rate in Hailsham has risen in recent years, linked to the significant levels of houses built in the town.
1.2Taking account of existing housing commitments, the Wealden Local Plan envisages that around 4,000 additional new dwellings will be built in and around Hailsham in the period to 2027/28. Births are therefore expected to continue to grow in the coming years. This is illustrated in the following graph.
Note: Live births to 2015/16, demographic projection of births from 2016/17
1.3The Council’s pupil forecasts show that recent house building in the area will begin to put pressure on primary school places from 2019/20.
1.4Given the impending pressure on primary school places in Hailsham, this report focusses on the need to provide an additional 420 primary places (two forms of entry, 2FE) in the town by 2019/20.
1.5Consideration also needs to be given to the medium to long term requirement for a further 2FE primary capacity from 2022/23 and the need for 4FE additional secondary capacity in the town from 2022/23. Options for delivery of these places will be developed working in partnership with local schools, the two Dioceses and other interested parties. 2. Supporting information 2.1 GP registration data indicates the current pupil admission number (PAN) of 270 is likely to be exceeded by around 60 Year Reception places (2FE) in 2019/20. The long term forecast is for Year Reception (Year R) intake shortfalls to eventually rise by 2027/28 to approximately 120 places (4FE). This is demonstrated in the graphs below.
2.2The requirement for additional Year R places can be mapped as follows (the figures are cumulative):
60 additional Year R places (2FE) from 2019/20 90 additional Year R places (3FE) from 2022/23 120 additional Year R places (4FE) from 2027/28 2.3 The Council has an option agreement on land east of Park Road for new primary school provision. The Council recently met with the landowner/ developer of the site; all parties are keen to progress the transfer of the school site to the Council at the earliest opportunity. It is hoped that agreement can be reached early in 2018, as securing the site is a crucial milestone if the new school places are to be delivered on time.
2.4The cost of building the new school would be met from the Schools Basic Need allocation in the Council’s approved capital programme. The cost of purchasing the school site east of Park Road is included within this capital programme.
2.5The Council’s initial strategy for providing places to meet the demand in 2019/20 in the north of the town was to support a free school application to establish a new school. Two free school applications were submitted to the Department for Education (DfE) in 2016 – by The Kemnal Academy Trust (TKAT) and the Tenax Schools Trust – for a new 2FE primary school on the site east of Park Road. Both proposals were rejected by the DfE in 2017 placing the Council in a challenging position in terms of delivering the additional places needed within the required timescale.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Education and Inclusion, Special Educational Needs and Disability at East Sussex and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.