Resources and Climate Change approved this item on Thursday 21 June 2018. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

DECISION 12.2 The Lead Member RESOLVED to (1) approve the granting of a full repairing and insuring lease to Ore Community Association on a peppercorn rent for a three year period, in order to operate a Community Library in the former Ore Library building; and (2) delegate authority to the Chief Operating Officer in consultation with the Director of Communities, Economy and Transport to agree the terms for the lease. Reasons 12.3 Granting a three year peppercorn lease to Ore Community Association (OCA) to operate a Community Library in the former Ore Library building would represent a potential loss of rental income to the County Council of £6,000-£9,000 over the three year period. Granting the lease instead of an immediate sale of the site would also defer a capital receipt of around £130,000. However, the option would remain for the County Council at the end of the lease period to sell the freehold or to consider an alternative use of the site, including a community asset transfer. 12.4 The OCA proposal would provide social value to the community in Ore and is judged by the evaluation panel to be viable. Granting a short-term peppercorn lease is in line with the Cabinet decision of 6 March 2018.
Word for word from the decision East Sussex published for this meeting. Source: democracy.eastsussex.gov.uk

Follow this further

Built from East Sussex's papers

What the report saysPro

Report to Resources and Climate Change

Report to: Lead Member for Resources

Date: 21 June 2018

By: Director of Communities, Economy and Transport

Title of report: Ore Community Library

Purpose of report: To seek Lead Member approval to grant a full repairing and insuring lease to Ore Community Association on a peppercorn rent for a three year period, in order to operate a Community Library in the former Ore Library building.

RECOMMENDATION: The Lead Member is recommended to:

(1) approve the granting of a full repairing and insuring lease to Ore Community Association on a peppercorn rent for a three year period, in order to operate a Community Library in the former Ore Library building; and

(2) delegate authority to the Chief Operating Officer in consultation with the Director of Communities, Economy and Transport to agree the terms for the lease.

1 Background Information

1.1At its meeting of 6 March 2018, Cabinet approved the revised Libraries Strategic Commissioning Strategy, following a 12 week period of public consultation. As part of the overall Strategy, Langney, Mayfield, Ore, Pevensey Bay, Polegate, Ringmer and Willingdon libraries and the Mobile Library closed on 5 May 2018.

1.2Cabinet agreed to give delegated authority to the Director of Communities, Economy and Transport, in consultation with the Assistant Chief Executive, to consider any viable community proposals to take over the running of the seven closed libraries or the Mobile Library, and to enter into appropriate agreements on behalf of ESCC.

2. Supporting information

2.1Ore Community Association (OCA) is an established charitable organisation which runs the Ore Centre, a large community centre in Hastings. Its proposal is to create a volunteer-led community library and community hub in the former Ore Library building in Old London Road, Ore, Hastings TN35 5BP. As with all of the community libraries, this would not be part of ESCC’s statutory library provision and would not be branded as an ESCC library. The aim is to incorporate the library into the Ore Centre, managing it under the same charitable incorporated organisation. The freehold of the former Ore Library building is owned by the County Council. A location plan is provided as Appendix 1.

2.2OCA have proposed a fully-repairing and insuring peppercorn lease arrangement for the building and a selection of stock, and the fixtures and fittings currently in the library for 3-5 years. OCA would like the County Council to consider a community asset transfer towards the end of this period.

2.3The panel set up to evaluate the Community Library proposals (comprising the Director of Communities, Economy and Transport and the Assistant Chief Executive) has reviewed the proposal and its supporting business case, and assessed it to be viable. A copy of the panel’s evaluation report is attached as Appendix 2.

2.4It is estimated that the site of the former Ore Library has a freehold value with planning permission for residential use of approximately £130,000. The annual commercial rental value of the building is estimated to be in the order of £2,000-£3,000. This would also require planning permission for change of use, and the types of commercial uses for which planning permission would be granted may be limited, given the largely residential surroundings.

3. Conclusions and reasons for recommendations

3.1Granting a three year peppercorn lease to OCA to operate a Community Library in the former Ore Library building would represent a potential loss of rental income to the County Council of £6,000-£9,000 over the three year period. Granting the lease instead of an immediate sale of the site would also defer a capital receipt of around £130,000. However, the option would remain for the County Council at the end of the lease period to sell the freehold or to consider an alternative use of the site, including a community asset transfer.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Lead Member for Resources 21 June 2018: Ore Community Library Appendix 2Appendix 258 KB Download
PDF
Ore Community Library [Item 4]Report 76 KB DownloadRead as text
PDF
Ore Library Location Plan: Appendix 1Appendix 475 KB Download

At this meeting

Whole meeting

On this subject at East Sussex

Search all
  1. Ore Community Library [Item 4]This decision
  2. Erection of detached, single storey, nursery building to south-west of main School. Parkside Community Primary School, Beechwood Lane, Heathfield, TN21 8QQ - WD/3381/CCApproved

More from East Sussex Resources and Climate Change

All decisions
MeetingDecisionOutcome
15 Sep 2026 Hollington Community Centre - Options for Next StepsRESOLVED to: 1) approve that the Council commences the Community Right to Bid process with a view to granting a lease... Approved Open
15 Sep 2026 Exclusion of Public and PressIt was RESOLVED to exclude the public and press from the meeting for the remaining agenda items on the grounds that i... Decided Open
11 Aug 2026 Robertsbridge Youth Centre - Options for Next StepsRESOLVED to: 1) approve the Council transferring the Charitable Trust, along with all assets held by the Trust, to Sa... Approved Open
11 Aug 2026 Exclusion of Public and PressRESOLVED to exclude the public and press from the meeting for the remaining agenda items on the grounds that if the p... Decided Open
21 Apr 2026 Orbis Shared Service Review - Consultation OutcomeRESOLVED to: 1) Note the feedback and conclusions from the Orbis staff consultations; 2) Agree to proceed with a sove... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies