It was RESOLVED to: (1) approve the Outline Business Case contained in appendix 1 of the report; and (2) approve the development two options (Option 1, Separate Contractor Contract & Separate Designer Contract and Option 2, Integrated Contractor & Designer Contract) to determine the new service delivery model for future highway services in the Detailed Business Case, which will be reported to Cabinet for approval later in the year. Reason 38.3 To approve the Outline Business Case and agree the proposal to develop two options in the Detailed Business Case to determine the new highways service delivery model. The Detailed Business Case will be presented to Cabinet for approval later in the year prior to procurement of the new contract
Word for word from the decision East Sussex published for this meeting.Source: democracy.eastsussex.gov.uk
Purpose: To present the outcomes and recommendations from the Outline Business Case for the Highway Services Re-procurement Project for approval by Cabinet
RECOMMENDATIONS: Cabinet is recommended to: (1) Approve the Outline Business Case contained in appendix 1 of the report; and (2) Approve the development two options (Option 1, Separate Contractor Contract & Separate Designer Contract and Option 2, Integrated Contractor & Designer Contract) to determine the new service delivery model for future highway services in the Detailed Business Case, which will be reported to Cabinet for approval later in the year.
1. Financial Appraisal 1.1 The project costs were estimated to be £533,000 profiled over the three years 2020/21 to 2023/24. These costs are in addition to ESCC staff costs which already form part of existing highways budgets.
1.2As the first stage of the project has evolved, opportunities to work as part of an academic study delivered by an independent consultant Proving Services Ltd based at Cranfield University have reduced the need for traditional external consultancy support. In addition, greater use of analysis of the service from the previous highways re-procurement project has also reduced the need for traditional consultancy support. The estimated project costs have subsequently reduced to £328,000 profiled over the years 2020/21 to 2023/24 as follows:
1.3Whilst the majority of the identifiable savings from the Highways Service were achieved from the last tender exercise in 2016, the opportunity for further savings will be examined in detail in the Detailed Business Case (DBC) phase.
2. Background 2.1 This report presents an overview of the main work and outcomes from the Outline Business Case (OBC) for the re-procurement of the new Highway Infrastructure Services (HIS) contract. The OBC has been developed using the Council’s Strategic Commissioning approach and the HM Treasury Five Case Model.
3.1The Process – Strategic Commissioning Approach 3.1.1 The OBC sets out the methodology, findings, conclusions and recommendations from Stage 1, Development of an Outline Business Case, of the re-procurement project. The OBC comprises two documents, Appendix 1, the OBC including an Executive Summary and Appendix 2 containing the technical appendices (6 in total) referred to in the OBC. The OBC has been prepared using the County Council’s Strategic Commissioning approach as illustrated on pages 13 and 14 of Appendix 1 and summarises work from the analysis phase of the strategic commissioning model. A summary of the key findings from this work is included on page 30 of Appendix 1.
3.2The Process - HM Treasury Five Case Model Methodology 3.2.1 The Five Case model is a HM Treasury recommended methodology for writing robust business cases, it is recognised as a best practice approach. The approach also provides a clear audit trail for the purposes of public accountability and was used in the Council’s previous re-procurement project which led to the successful appointment of the current Service Provider.
3.2.2 In applying the Five Case model through the project stages (Figure 002, page 15 Appendix 1), each of the five ‘cases’ will be developed as the project progresses. In preparing this OBC, much of the information in it provides a foundation for stage two when the DBC is developed.
3.3Drivers for Change 3.3.1 The OBC also considers the key drivers for making changes (pages 25 & 30 of Appendix 1) including; the need to replace existing arrangements; continue to deliver our statutory obligations as the Highway Authority and; the need to continue to make the best use of our limited resources.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Monitoring Report - Q1 2026/27It was RESOLVED to: 1) note the latest monitoring position for the Council; and 2) approve proposed amendments to per...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.