Transport and Environment, Monday 14 March 2022 at 10.00am

Alexandra Park shared pedestrian and cycle route, Hastings

Approved Committee 7 papers

Transport and Environment approved this item on Monday 14 March 2022. Below is the council's own wording, with the papers it was decided on.

Item52

Resolved

RESOLVED to: (1) Advise the petitioners that the separate requests ‘to remove the proposed section of the shared pedestrian and cycling route from the lower section of Alexandra Park’ and for ‘East Sussex County Council to Support the Cycleway and Walking & Cycling 'Greenway' link through Alexandra Park’ have been considered; and (2) As the proposed shared pedestrian and cycle route running through Alexandra Park meets the wider County Council objectives as set out in section 1 of the report, and that the proposed route has historically been subject to public and stakeholder consultation, further design review, road safety audits and an Equality Impact Assessment, the proposal will progress to implementation as part of the Capital Programme for Transport Improvements 2022/23. REASONS 52.5 The 2014 Hastings Cycling Strategy and latterly the East Sussex Local Cycling and Walking Infrastructure Plan, approved in September 2020, identifies the route through Alexandra Park as a priority for delivery and an integral part of a network of cycle routes for the town, linking to the proposed route between Silverhill and Queensway in western Hastings and future eastern routes to the Hastings town centre and seafront as well as Conquest hospital. 52.6 Following Lead Member approval in June 2018 to progress the scheme to detailed design and construction, there has been significant and careful consideration given to ensuring any potential risks to pedestrians and cyclists using the proposed cycle route through both the Upper and Lower sections of Alexandra Park are mitigated and incorporated into the design of the scheme. This process has included independent road safety audits at preliminary and detailed design stages to consider the overall safety of the scheme, and identify any recommended changes, as well as assessing the equalities impacts of the scheme on those groups with protected characteristics. Throughout this process, Hastings Borough Council have remained supportive of the scheme and have agreed to monitor the operation of the route through the park, educate users and where necessary undertake enforcement. Officers agreed to explore a Service Level Agreement with Hastings Borough Council regarding resources for enforcement. 52.7 Despite looking at alternative on road routes, which have been discounted for technical feasibility reasons, the recommended route through the lower section of Alexandra Park remains the most practicable solution for providing for cyclists in ... view the full minutes text for item 52.
Word for word from the decision East Sussex published for this meeting. Source: democracy.eastsussex.gov.uk

Follow this further

Built from East Sussex's papers

What the report saysPro

Report to Transport and Environment

Report to: Lead Member for Transport and Environment

Date of meeting: 14 March 2022

By: Director of Communities, Economy and Transport

Title: Alexandra Park shared pedestrian and cycle route, Hastings

Purpose: To consider the petitions calling on East Sussex County Council to address cycling measures in Alexandra Park, Hastings.

RECOMMENDATIONS: The Lead Member is recommended to advise the petitioners that: (1) The separate requests ‘to remove the proposed section of the shared pedestrian and cycling route from the lower section of Alexandra Park’ and for ‘East Sussex County Council to Support the Cycleway and Walking & Cycling 'Greenway' link through Alexandra Park’ have been considered; and (2) As the proposed shared pedestrian and cycle route running through Alexandra Park meets the wider County Council objectives as set out in section 1 of the report, and that the proposed route has historically been subject to public and stakeholder consultation, further design review, road safety audits and an Equality Impact Assessment, the proposal will progress to implementation as part of the Capital Programme for Transport Improvements 2022/23.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Alexandra Park shared pedestrian and cycle route, HastingsReport 322 KB DownloadRead as text
PDF
Appendix 1Appendix 1 1.6 MB Download
PDF
Appendix 2Appendix 2 30 KB Download
PDF
Appendix 3Appendix 3 222 KB Download
PDF
Appendix 4Appendix 4 18 MB Download
PDF
Appendix 5Appendix 5 2.5 MB Download
PDF
View item 52. as HTML 40 KBReport 40 KB Copy on its way

At this meeting

Whole meeting

On this subject at East Sussex

Search all
  1. Alexandra Park shared pedestrian and cycle route, HastingsThis decision
  2. Alexandra Park shared pedestrian and cycle route, HastingsNoted
  3. Alexandra Park and St Helen's Road cycle route reviewNoted
  4. Alexandra Park, Hastings - proposed designated shared pedestrian and cycle route - consultation resultsDeferred

More from East Sussex Transport and Environment

All decisions
MeetingDecisionOutcome
20 Jul 2026 Petition: Installation of a pedestrian crossing and traffic calming measures in A271 Amberstone, HailshamRESOLVED to advise petitioners that: (1) a potential scheme to install a new pedestrian crossing and traffic calming ... Approved Open
20 Jul 2026 East Sussex Local Flood Risk Management Strategy 2027 - 2037RESOLVED to approve that the Council commences public consultation on the draft East Sussex Local Flood Risk Manageme... Approved Open
20 Jul 2026 Policy for Enforcement and Prosecutions of Highway and Street Works ActivitiesRESOLVED to agree the policy in principle and delegate authority to Director of Communities, Economy and Transport to... Agreed Open
16 Mar 2026 Programme of Transport Improvements 2026/27RESOLVED to: (1 ) agree the draft programme of transport improvements for 2026/27 set out in Appendix 2 of the report... Agreed Open
16 Mar 2026 East Sussex and Brighton and Hove Record Office Collections PoliciesRESOLVED to: (1 ) approve the East Sussex and Brighton and Hove Record Office Collections Development Policy, as set ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies