RESOLVED to: (1) Note the comments of the local consultation and subsequent discussions with Rother District Council regarding the inter-relationship between the Town Hall Square proposals and the District Council’s Town Hall campus redevelopment proposals; and; (2) Approve that Option A – removal of the Town Hall Square gyratory and creation of a priority junction between London Road and Buckhurst Place - to be taken forward to detailed design and construction as part of the 2023/24 Capital Programme for Local Transport Improvements REASONS 54.3 The London Road corridor scheme forms part of the wider Hastings Bexhill Movement and Access Package and seeks to improve the pedestrian environment, including the public realm, and traffic management in this part of Bexhill. The scheme would be delivered using Local Growth Fund monies, as well as £300,000 Community Infrastructure Levy funding from Rother District Council. 54.4 Whilst the removal of the gyratory received a mixed response during the public consultation, it will deliver an attractive public realm that will provide a safe space for people to meet, encouraging people to come into the town more often and spend more time there.
Word for word from the decision East Sussex published for this meeting.Source: democracy.eastsussex.gov.uk
Report to: Lead Member for Transport and Environment
Date of meeting: 16 January 2023
By: Director of Communities, Economy and Transport
Title: London Road Corridor Improvements - Phase 2 - Buckhurst Place
Purpose: To consider the proposed way forward in relation to the Town Hall Square (Buckhurst Place) element of the Bexhill-on-Sea London Road Corridor scheme and seek approval to progress the scheme to detailed design and construction.
RECOMMENDATIONS: The Lead Member is recommended to: (1) Note the comments of the local consultation and subsequent discussions with Rother District Council regarding the inter-relationship between the Town Hall Square proposals and the District Council’s Town Hall campus redevelopment proposals; and; (2) Approve that Option A – removal of the Town Hall Square gyratory and creation of a priority junction between London Road and Buckhurst Place - to be taken forward to detailed design and construction as part of the 2023/24 Capital Programme for Local Transport Improvements
1. Background 1.1. The Hastings and Bexhill Movement and Access Package comprises a package of pedestrian, cycle and public transport improvement schemes across Bexhill, Hastings and St Leonards. One of the identified schemes within the package approved by the South East Local Enterprise Partnership (SELEP) is the London Road Traffic Management and Public Realm scheme in Bexhill with a focus on improving the pedestrian environment, including the public realm, and traffic management in the area. 1.2. The extent of the scheme is from its junction with the A259 and running south to and including its junction with Buckhurst Place including the one-way gyratory outside Bexhill Town Hall. The extent of the scheme also goes beyond London Road to include Buckhurst Place and part of Sackville Road to its junction with Western Road. The overall extent of the study area is illustrated in Appendix 1. 1.3. Funding for the works identified in the scheme would be funded by the Local Growth Fund monies secured from Government through the SELEP as well as from £300,000 of Community Infrastructure Levy secured from Rother District Council (RDC). The scheme will be added to the county’s highway asset register and the ongoing maintenance costs will be included in the County Council’s future highway maintenance programme. 1.4. The outcomes of the consultation on the overall scheme and recommended next steps were considered by the Lead Member for Transport and Environment at a decision making meeting on 21 February 2022, where the Lead Member resolved to: Agree that all elements of the scheme except the Phase 2 - Buckhurst Place/Town Hall Square options are taken forward to detailed design and construction as part of the Capital Programme for Local Transport Improvements; and Agree that a recommended way forward for Phase 2 - Buckhurst Place options is presented back to the Lead Member following further discussions with Rother District Council, Bexhill Town Council and other stakeholders. Since the February 2022 decision making meeting, further discussions have been held with Rother District Council on the interface of the Buckhurst Place options and their proposals for redeveloping the Town Hall campus In Bexhill.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.