It was RESOLVED to: 1) agree the final draft of the corporate Climate Emergency Plan as set out in appendix 1; and 2) agree the draft summary version of the Climate Emergency Plan as set out in appendix 2. Reason 38.3 In October 2019 the County Council set a target of achieving carbon neutrality from its activities as soon as possible and in any event by 2050. In June 2020 Cabinet approved a corporate climate emergency action plan for 2020-22. In 2021-22 Cabinet agreed an additional £9.9m to address corporate climate change up to March 2025. The report covers an updated corporate Climate Emergency Plan covering 2023-25. The final draft of the Climate Emergency Plan is set out in Appendix 1 of the report and a summary version is set out in Appendix 2 of the report.
Word for word from the decision East Sussex published for this meeting.Source: democracy.eastsussex.gov.uk
Date of meeting: 24 January 2023 By: Director of Communities, Economy and Transport and the Chief Operating Officer.
Title: Final draft corporate Climate Emergency Plan for 2023-25 Purpose: To seek approval of the corporate Climate Emergency Plan that will go to Full Council on 7 February 2023
RECOMMENDATIONS Cabinet is recommended to:
1) agree the final draft of the corporate Climate Emergency Plan (appendix 1); and 2) agree the draft summary version of the Climate Emergency Plan (appendix 2).
1 Background 1.1 In October 2019 the County Council set a target of achieving carbon neutrality from its activities as soon as possible and in any event by 2050. In June 2020 Cabinet approved a corporate climate emergency action plan for 2020-22. In 2021-22 Cabinet agreed an additional £9.9m to address corporate climate change up to March 2025. This report covers an updated corporate Climate Emergency Plan covering 2023-25. The final draft of the Climate Emergency Plan is set out in Appendix 1 and a summary version is set out in Appendix 2.
2 Supporting information 2.1 A clear understanding of the carbon emissions generated by our activities is a key foundation for working towards net zero. The carbon emissions of an organisation are usually divided into the following 3 categories: Scope 1 – emissions from the use of gas and oil in Council buildings and petrol and diesel in Council-owned vehicles. These are about 2% of total Council emissions. Scope 2 – emissions from the electricity purchased by the Council. These are also about 2% of total Council emissions. Scope 3 – emissions that result from all other activities of the Council, including business travel, water usage, waste, procurement and staff commuting. These are about 96% of total Council emissions, with the vast majority from procurement of the goods, works and services that the Council needs to pay for in order to deliver its statutory services. This is similar to other local authorities.
2.2The Council has good quality data for scope 1 and 2 emissions, as these are under the direct control of the Council. The quality of scope 3 emission data is much more variable, in particular for the goods, works and services that are purchased by the Council in order to deliver its functions. Further work is required to quantify most scope 3 emissions before they can begin to be integrated reliably into the Council’s carbon footprint and modelled for future emission reductions. Most local authorities are in a similar position.
2.3Following the declaration of a climate emergency in 2019 the Council developed a corporate climate emergency plan for 2020-22, which set out the baseline carbon emissions and the actions to be delivered during 2020-22. A Scrutiny review of progress in becoming a carbon neutral council was carried out in 2019-20, which included a set of recommendations that were accepted by the Council in 2020. Since then, six monthly reports have been taken to the Place Scrutiny Committee
1 on progress in delivering against the recommendations and an annual progress report on the climate emergency plan was presented to full Council in October 2021 and in October 2022.
2.4The Council’s scope 1 and 2 carbon emissions have been reduced by over 66% over the last decade, due to the decarbonisation of the national electricity grid, through a reduction in the Council’s estate and as a result of investment made by the Council in carbon reduction measures.
2.5The draft Climate Emergency Plan for 2023-25 in appendix 1 sets out: 1) The Council’s current carbon footprint; 2) Some principles for the Council to follow in its approach to net zero; 3) The Council’s science-based 5 year carbon budgets; 4) The modelling work that has been used to steer some of actions in the Plan; 5) How the additional investment of £9.9m made available by Cabinet for climate change will be spent up to March 2025; 6) The governance, monitoring and reporting systems in place to cover the Plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Monitoring Report - Q1 2026/27It was RESOLVED to: 1) note the latest monitoring position for the Council; and 2) approve proposed amendments to per...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.