East Sussex County Council
Cabinet, Tuesday 27 June 2023 at 10.00am

Highway Maintenance Investment

Approved Executive 4 papers

Cabinet approved this item on Tuesday 27 June 2023. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

RESOLVED to: 1) Note what has been achieved with the £5.8m additional investment approved In November 2021. 2) a) Note the impact of the 2022/23 winter on road condition and, in accordance with our highways asset management plan agree the following to bring investment in 2023/24 to £28.2m. Agree additional one off £5.6m spend on highways maintenance comprising £2.5m patching work and £3.1m drainage work, to be funded from the Priority Outcomes and Transformation Reserve, which includes the balance on the 2022/23 Services Grant set aside for one-off investment; b) Agree to increase the capital programme for 2023/24 by £5.1m to maintain steady state and; c) Agree, subject to the County Council agreeing to increase the Capital Programme, that a further £5m be spent on highway maintenance to provide early improvements and resilience. d) Agree to lobby the Government, directly and with other partners, to provide funding for highways sufficient to ensure East Sussex roads are adequate for the needs of residents and businesses. Reasons 3.3 The additional £5.8m one-off investment in highway maintenance was successfully delivered in 2022/23 with the exception of some of the road markings and sign replacement works that have been delayed to the current financial year due to supply chain and weather issues. The additional £2.5m in patching paid dividends and was clearly noticeable in the autumn of 2022. 3.4 However, the exceptional winter of 2022/23 has partly mitigated the effect of the additional patching programmes and increased the backlog of patching works (to deal with non-intervention level potholes) to £2.5m. Therefore, further one-off investment of £2.5m will continue to tackle the backlog of patching and prevent intervention level potholes forming. This will provide additional early resilience to a weakened network during the current year in preparation for the coming winter months. 3.5 The very wet winter has generated the highest number of carriageway potholes since the contract with Costain began in 2016 with the relationship between wet winters and pothole numbers clearly evident. Alongside this there has been a visible deterioration in carriageway condition with some areas experiencing sudden surface failure. 3.6 The experience of the 2022/23 winter, and the impact it has had on the network, has shown that road condition will continue to deteriorate at an accelerating rate if similar winters are experienced in the future and funding continues at current levels. 3.7 The investment modelling undertaken considers how to address this and the levels of funding required. The modelling is based on using up to date maintenance costs to account for higher costs since 2021/22; the last condition information available from the September 2022 road condition surveys; estimating the impact on condition on the network following the 2022/23 winter; and using some engineering assumptions about the make-up (construction materials) of the roads. 3.8 Based on the outputs from the modelling additional investment is needed to achieve our current road condition targets know as steady ... view the full minutes text for item 3.
Word for word from the decision East Sussex published for this meeting. Source: democracy.eastsussex.gov.uk

Follow this further

Built from East Sussex's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet Date of meeting: 27 June 2023 By: Director of Communities, Economy and Transport Title: Highway Maintenance Investment. Purpose: To provide an update on the one-off £5.8m investment in Highway maintenance approved by Cabinet in November 2021; and following the latest assessment of road conditions to advise on the impact of the 2022/23 winter on road condition and recommend additional investment.

RECOMMENDATIONS: Cabinet is recommended to: (1) Note what has been achieved with the £5.8m additional investment approved In November 2021. a) note the impact of the 2022/23 winter on road condition and, in accordance with our highways asset management plan agree the following to bring investment in 2023/24 to £28.2m Agree additional one off £5.6m spend on highways maintenance comprising £2.5m patching work and £3.1m drainage work, to be funded from the Priority Outcomes and Transformation Reserve, which includes the balance on the 2022/23 Services Grant set aside for one-off investment; b) Agree to increase the capital programme for 2023/24 by £5.1m to maintain steady state and; c) Agree, subject to the County Council agreeing to increase the Capital Programme, that a further £5m be spent on highway maintenance to provide early improvements and resilience. d) Agree to lobby the Government, directly and with other partners, to provide funding for highways sufficient to ensure East Sussex roads are adequate for the needs of residents and businesses.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cabinet 27 June 2023: Highway Maintenance Investment: Appendix 1Appendix 2.3 MB Download
PDF
Cabinet 27 June 2023: Highway Maintenance Investment: Appendix 2Appendix 2.3 MB Download
PDF
Highway Maintenance InvestmentReport 486 KB DownloadRead as text
PDF
View item 3. as HTML 63 KBReport 63 KB Copy on its way

At this meeting

Whole meeting

On this subject at East Sussex

Search all
  1. Highway Maintenance InvestmentThis decision
  2. Highway Maintenance Incentive Funding 2025/26Noted
  3. Highway Maintenance - Consideration of CharacterAgreed

More from East Sussex Cabinet

All decisions
MeetingDecisionOutcome
29 Sep 2026 Council Monitoring Report - Q1 2026/27It was RESOLVED to: 1) note the latest monitoring position for the Council; and 2) approve proposed amendments to per... Noted Open
29 Sep 2026 Reconciling Policy, Performance and Resources (RPPR): Update on planning for 2027/28It was RESOLVED to: 1) agree the revised priority and delivery outcomes to form the basis of business planning for 20... Agreed Open
29 Sep 2026 Climate Resilience and Environment PolicyIt was RESOLVED to: 1) note the draft Climate Resilience and Environment Policy at Appendix 1 of the report and the r... Noted Open
29 Sep 2026 Scrutiny Review of Personal Travel Budgets and Independent Travel Training in School Transport - Report of the People Scrutiny CommitteeIt was RESOLVED to: 1) note and welcome the report of the People Scrutiny Committee; and 2) recommend the County Coun... Agreed Open
29 Sep 2026 Scrutiny Review of Street Works - Report of the Place Scrutiny CommitteeIt was RESOLVED to: 1) note and welcome the report of the Place Scrutiny Committee; and 2) recommend the County Counc... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies