Transport and Environment, Monday 15 January 2024 at 10.00am

Hastings and Bexhill Movement and Access Package

Noted Committee 4 papers

Transport and Environment noted this item on Monday 15 January 2024. Below is the council's own wording, with the papers it was decided on.

Item58

Resolved

RESOLVED to: (1) Note the South East Local Enterprise Partnership Accountability Board decision to proceed with a revised delivery package for the Hastings and Bexhill Movement and Access Package; (2) Approve the revised package moving forward to construction in 2024/25 to be included in the forthcoming Capital Programme for Local Transport Improvements 2024/25; and (3) Delegate authority to the Chief Finance Officer and Assistant Chief Executive, to negotiate and agree the financial package development costs with the South East Local Enterprise Partnership as covered in paragraphs 2.15 to 2.18 of the report. REASONS 58.3 Since the County Council secured £9m of Local Growth Fund monies from the South East Local Enterprise Partnership (SELEP) towards the development and delivery of the Hastings and Bexhill Movement and Access Package in 2018, significant progress has been made in progressing each of the schemes towards delivering cycling, walking, bus infrastructure, traffic management and public realm improvements, aimed at supporting economic growth across Hastings and Bexhill. 58.4 Due to sharp increases in costs across the construction sector because of high inflation, the war in Ukraine and delays due to the Covid-19 pandemic, the cost to deliver the remaining schemes now exceeds the £3.84m remaining funding. 58.5 Following a comprehensive cost estimate and business case review exercise undertaken by transport consultants, and in consultation with key stakeholders as set out in paragraphs 2.9 of the report, a revised scheme package was approved by the SELEP Accountability Board in September 2023 to deliver the following remaining schemes by March 2026: · Albert Road, Hastings · Station Approach, Hastings and · Bexhill Cycle Route A.
Word for word from the decision East Sussex published for this meeting. Source: democracy.eastsussex.gov.uk

Follow this further

Built from East Sussex's papers

What the report saysPro

Report to Transport and Environment

Report to: Lead Member for Transport and Environment

Date of meeting: 15 January 2024

By: Director of Communities, Economy, and Transport

Title: Hastings and Bexhill Movement and Access Package

Purpose: To note and approve the revised Hastings and Bexhill Movement and Access Package in line with the South East Local Enterprise Partnership Accountability Board decisions.

RECOMMENDATIONS: The Lead Member is recommended to: (1) Note the South East Local Enterprise Partnership Accountability Board decision to proceed with a revised delivery package for the Hastings and Bexhill Movement and Access Package; (2) Approve the revised package moving forward to construction in 2024/25 to be included in the forthcoming Capital Programme for Local Transport Improvements 2024/25; and (3) Delegate authority to the Chief Finance Officer and Assistant Chief Executive, to negotiate and agree the financial package development costs with the South East Local Enterprise Partnership as covered in paragraphs 2.15 to 2.18 of this report.

1 Background 1.1 In 2018, the County Council secured £9m of Local Growth Fund (LGF) monies from the South East Local Enterprise Partnership (SELEP) towards the development and delivery of the Hastings and Bexhill Movement and Access Package (HBMAP). The integrated package of schemes was developed to deliver cycling, walking and bus infrastructure, traffic management and public realm improvements, aimed at supporting economic growth across Hastings and Bexhill. 1.2 In 2022, following discussions with the County Council’s Highways Contractor, it became evident that the total amount of funding required to complete the design and delivery of all schemes within the package would be significantly higher than the remaining LGF monies available. This has primarily been driven by delays due to the Covid-19 pandemic, in addition to high inflationary cost increases across the construction sectors, including on elements such as materials and labour costs. 1.3 Programme delivery has therefore needed to be split into two phases with the first phase of schemes having already been delivered between 2018/19 and 2023/24. The 2023/24 Capital Programme of Local Transport Improvements, of which the HBMAP forms an element, was approved by the Lead Member for Transport and Environment at a decision-making meeting on 13 March 2023. The Lead Member was advised that the work on the HBMAP package would be paused while a full scheme review and programme assessment was undertaken to determine which of the remaining schemes within the HBMAP could be taken forward for final development and/or delivery. 1.4 The County Council has since undertaken a comprehensive review of the package in line with the amount of funding available, ensuring that remaining schemes are deliverable, still meet the original aims, value for money and benefits of the business case, and can be delivered within the remaining LGF funding allocation. 1.5 The necessary approvals were sought from the SELEP Accountability Board in September 2023 to reallocate project funding to three prioritised remaining schemes and extend construction delivery timescales to March 2026. 2 Supporting information

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 377 KB Download
PDF
Hastings and Bexhill Movement and Access PackageReport 347 KB DownloadRead as text
PDF
View as HTML (58./2) 19 KBAppendix 19 KB Copy on its way
PDF
View item 58. as HTML 53 KBReport 53 KB Copy on its way

At this meeting

Whole meeting

On this subject at East Sussex

Search all
  1. Hastings and Bexhill Movement and Access PackageThis decision
  2. Rent review of Pebsham Waste Transfer Station and Hastings Household Waste Recycling Site, Freshfields, Bexhill Road, St Leonards-on-SeaApproved
  3. To consider objections received in response to the statutory consultation and the public advertisement on the draft Traffic Regulation Order (TRO) to introduce Bus Lanes and No Waiting At Any Time as part of the A259 Bexhill Road Bus Priority Scheme (Phase 1) in St Leonards, HastingsDecided
  4. Installation of tanks to facilitate the transfer of leachate and other associated development. Former Hastings Household Waste Recycling Site, Freshfields, off Bexhill Road, Pebsham, Bexhill, TN40 2RZ - RR/784/CMApproved

More from East Sussex Transport and Environment

All decisions
MeetingDecisionOutcome
20 Jul 2026 Petition: Installation of a pedestrian crossing and traffic calming measures in A271 Amberstone, HailshamRESOLVED to advise petitioners that: (1) a potential scheme to install a new pedestrian crossing and traffic calming ... Approved Open
20 Jul 2026 East Sussex Local Flood Risk Management Strategy 2027 - 2037RESOLVED to approve that the Council commences public consultation on the draft East Sussex Local Flood Risk Manageme... Approved Open
20 Jul 2026 Policy for Enforcement and Prosecutions of Highway and Street Works ActivitiesRESOLVED to agree the policy in principle and delegate authority to Director of Communities, Economy and Transport to... Agreed Open
16 Mar 2026 Programme of Transport Improvements 2026/27RESOLVED to: (1 ) agree the draft programme of transport improvements for 2026/27 set out in Appendix 2 of the report... Agreed Open
16 Mar 2026 East Sussex and Brighton and Hove Record Office Collections PoliciesRESOLVED to: (1 ) approve the East Sussex and Brighton and Hove Record Office Collections Development Policy, as set ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies