Procurement of Supply of Gas and Electricity to East Sussex County Council Assets

Approved Committee 2 papers

Resources and Climate Change approved this item on Monday 15 July 2024. Below is the council's own wording, with the papers it was decided on.

Item17

Resolved

RESOLVED to: 1) Approve East Sussex County Council continuing to purchase electricity and gas via the Crown Commercial Services Energy Framework following an energy market review; 2) Delegate authority to the Chief Operating Officer to take all actions considered appropriate to give effect to the above decision including, but not limited to, agreeing the contract for purchase of electricity and gas; and 3) Delegate authority to the Chief Operating Officer to undertake a further review within 24 months to ensure the Council is securing value for money. REASONS 17.3 The Council needs to provide value for money and a secure supply of gas and electricity for its assets and properties, including schools. On its own, the Council does not have the appropriate demand and leverage to gain an optimum price and value for this supply independently. It will benefit from continuing to purchase with Crown Commercial Services, who undertake aggregated buying of approximately £51 billion of public sector energy to achieve this. 17.4 Due to the nature of the energy markets, to obtain best value, the Council procures energy in advance via an energy strategy. The supply of gas and electricity are subject to wider geo-political factors as seen with the energy crisis in 2022.
Word for word from the decision East Sussex published for this meeting. Source: democracy.eastsussex.gov.uk

Follow this further

Built from East Sussex's papers

What the report saysPro

Report to Resources and Climate Change

Recommendations

The Lead Member for Resources and Climate Change is recommended to:

1) Approve East Sussex County Council (ESCC) continuing to purchase electricity and gas via the Crown Commercial Services Energy Framework following an energy market review; 2) Delegate authority to the Chief Operating Officer to take all actions considered appropriate to give effect to the above recommendation including, but not limited to, agreeing the contract for purchase of electricity and gas; and 3) Delegate authority to the Chief Operating Officer to undertake a further review within 24 months to ensure the Council is securing value for money.

1 Background 1.1 East Sussex County Council’s current arrangements for the supply of gas and electricity are procured through the Crown Commercial Services Energy Supply Frameworks as outlined in the Lead Member’s decision of 20 September 2019 (Agenda for Lead Member for Resources and Climate Change on Friday, 20th September, 2019, 11.00 am | East Sussex County Council). 1.2 The Council currently procures gas and electricity for the following assets:  Corporate Buildings (including Social Care Buildings and Libraries):  Schools.  Street Lighting.  Academies. Academies and Schools pay their sites energy invoicing direct to the supplier. Table 1 - shows the energy consumption (in megawatt hours) used in 2023/2024 for the different areas shown above.

Department Gas MWh Electricity MWh Corporate 6,233 4,505 Schools 11,644 9,216 Street - 6,088 Lighting Academies 13,659 6,398 Total 31,536 26,207 1.3 The annual cost for the supply of gas and electricity across all the assets above will change according to demand and wholesale market cost. 1.4 The Council’s Property team are working with site managers regarding best practice on how to reduce energy usage and this is an important role to aid the reduction of energy consumption. The Council also has an established programme of capital investment including heat decarbonisation projects, LED lighting and solar PV panel installation programme. The Business Services Department Portfolio Plan had a target for 23 energy efficiency projects in 2023/2024 to reduce energy consumption; however, this was surpassed by achieving 25 projects in that period.

1.5Due to the nature of the market and to obtain best value, the Council procures energy in advance. The contract for the gas and electricity supply is pivotal to ensure all services are maintained in a way to support the requirements of East Sussex County Council in monitoring consumption, carbon reporting and spend of energy. This is because East Sussex County Council’s Climate Emergency Plan 2023-25 recognises the impact of energy usage on the environment. 1.6 The energy industry has made progress in developing a greater mix of energy produced via renewable sources, such as wind, solar, hydro and wave for example. Consequentially, the carbon intensity of energy supplied by the national grid has reduced since East Sussex County Council’s current arrangements for the supply of gas and electricity were procured in 2019. 1.7 East Sussex County Council’s corporate estate electricity and street lighting currently procures REGO’s (Renewable Energy Guarantees of Origin) and the ongoing purchase will be subject to a separate review.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of Supply of Gas and Electricity to East Sussex County Council AssetsReport 151 KB DownloadRead as text
PDF
View item 17. as HTML 44 KBReport 44 KB Copy on its way

At this meeting

Whole meeting

On this subject at East Sussex

Search all
  1. Procurement of Supply of Gas and Electricity to East Sussex County Council AssetsThis decision
  2. Procurement of supply of gas and electricityAgreed

More from East Sussex Resources and Climate Change

All decisions
MeetingDecisionOutcome
15 Sep 2026 Hollington Community Centre - Options for Next StepsRESOLVED to: 1) approve that the Council commences the Community Right to Bid process with a view to granting a lease... Approved Open
15 Sep 2026 Exclusion of Public and PressIt was RESOLVED to exclude the public and press from the meeting for the remaining agenda items on the grounds that i... Decided Open
11 Aug 2026 Robertsbridge Youth Centre - Options for Next StepsRESOLVED to: 1) approve the Council transferring the Charitable Trust, along with all assets held by the Trust, to Sa... Approved Open
11 Aug 2026 Exclusion of Public and PressRESOLVED to exclude the public and press from the meeting for the remaining agenda items on the grounds that if the p... Decided Open
21 Apr 2026 Orbis Shared Service Review - Consultation OutcomeRESOLVED to: 1) Note the feedback and conclusions from the Orbis staff consultations; 2) Agree to proceed with a sove... Noted Open