Site 6, Eastbourne - Disposal of Long Leasehold Interest

Approved Committee 3 papers

Resources and Climate Change approved this item on Tuesday 14 January 2025. Below is the council's own wording, with the papers it was decided on.

Item60

Resolved

RESOLVED to: 1) Declare Site 6, Eastbourne shown in Appendix 1 of the report (“the Site”) to be surplus to the requirements of the Council; 2) Approve the disposal of the Site in accordance with s123 of the Local Government Act 1972; 3) Approve that East Sussex County Council enters into a Memorandum of Understanding with Eastbourne Borough Council (EBC) whilst the ownership of the Site is held jointly and to delegate authority to the Chief Operating Officer to agree the terms of it; 4) Delegate authority to the Chief Operating Officer to agree the terms of the sale, jointly with Eastbourne Borough Council, to achieve best value for the Site in accordance with s123 of the Local Government Act 1972, including proceeding with the next best offer(s) in the event of the transaction(s) not completing within the expected timelines; and 5) Delegate authority to the Chief Operating Officer to take all actions necessary to give effect to the recommendations in the report. REASONS 60.3 East Sussex County Council (ESCC) has no ongoing operational use for the Site. It is therefore surplus to the Council’s requirements. The disposal of the Site will reduce revenue liabilities relating to the management and holding costs of this surplus asset, as well as providing the Council with a capital receipt. 60.4 A Memorandum of Understanding is to be agreed between both Councils, settling out the joint management strategy whilst the Site remains in joint ownership. Delegation of approval of the terms of this Memorandum of Understanding to the Chief Operating Officer will ensure that the Site can be efficiently managed. 60.5 Delegation to the Chief Operating Officer authority to agree the terms of the sale, jointly with EBC, to achieve the best consideration for the Site in accordance with s.123 of the Local Government Act 1972, including authority to proceed with the next best offer(s) in the event of the transaction(s) not completing within the expected timelines and to take all actions necessary to give effect to the recommendations in the report will facilitate the effective disposal of the Site.
Word for word from the decision East Sussex published for this meeting. Source: democracy.eastsussex.gov.uk

Follow this further

Built from East Sussex's papers

What the report saysPro

Report to Resources and Climate Change

Report to: Lead Member for Resources and Climate Change

Date of meeting: 14 January 2025

By: Chief Operating Officer

Title: Site 6, Eastbourne – Disposal of Long Leasehold Interest

Purpose: To declare Site 6, Eastbourne to be surplus to the operational requirements of the Council and to agree to dispose of the asset in accordance with s123 of the Local Government Act 1972

RECOMMENDATIONS The Lead Member for Resources and Climate Change is recommended to: 1) Declare Site 6, Eastbourne shown in Appendix 1 (“the Site”) to be surplus to the requirements of the Council;

2) Approve the disposal of the Site in accordance with s123 of the Local Government Act 1972;

3) Approve that East Sussex County Council enters into a Memorandum of Understanding with Eastbourne Borough Council (EBC) whilst the ownership of the Site is held jointly and to delegate authority to the Chief Operating Officer to agree the terms of it;

4) Delegate authority to the Chief Operating Officer to agree the terms of the sale, jointly with Eastbourne Borough Council, to achieve best value for the Site in accordance with s123 of the Local Government Act 1972, including proceeding with the next best offer(s) in the event of the transaction(s) not completing within the expected timelines; and

5) Delegate authority to the Chief Operating Officer to take all actions necessary to give effect to the recommendations in this report.

1 Background 1.1 The Site comprises a former boat yard, with a community centre to the south-western side of the Site which leads to Sovereign Harbour Retail Park. It is adjacent to an office building known as Pacific House, which is to the western boundary of the site. The extent of the Site is shown in Appendix 1.

1.2Eastbourne Borough Council’s (EBC) Core Strategy Local Plan and the Employment Land Local Plan identifies the Site as being allocated as employment land, capable of delivering offices, research and development space, and/or light industrial units. A total allocation of 20,000 sqm is identified as being deliverable across Sovereign Harbour, with the bulk of this to be shared between ‘Site 6’ and a neighbouring site, ‘Site 7’ - Eastbourne Core Strategy - Lewes and Eastbourne Councils.

1.3East Sussex County Council (ESCC) owns the long leasehold interest in Site 6, along with EBC as tenants in common. The ownership split is ESCC 48.485% and EBC 51.515%. The long leasehold interest is for a term of 999 years from April 2014. The 999-year lease restricts the permitted development of ‘Site 6’ to a use within Use Class B1 (a) (b) or (c) of the Town and Country Planning (Use Classes) Order 1987 as at the date the lease is granted. This therefore follows the site allocation in the Local Plan, being offices, research and development space, and/or light industrial units.

1.4A draft Memorandum of Understanding has been drawn up to document the roles and expectations of both Councils whilst the ownership of the Site is held jointly. It also sets out the approach for joint decision-making and the escalation process for a dispute. This is outlined within an exempt item later in the agenda.

2 Supporting information

2.1Five options for the Site have been considered. These options are:

1) Retain for a Council service; 2) Dispose of the long leasehold interest via a Community Asset Transfer or market sale; 3) Sell the ESCC proportion to EBC; 4) Rent to an ESCC or EBC partner; 5) Rent to an external tenant.

2.2Option 1 (Retain for a Council service): ESCC and EBC Directorates have confirmed that there is no operational service need for the Site by either party.

2.3Option 2 (Dispose of the Long Leasehold): as the Site is formed of open land, it is not considered suitable for a community asset transfer. The Site is likely to be considered as a development site with potential for employment use (subject to relevant consents being obtained), which supports economic development goals. Disposal through a market sale is therefore considered a viable option.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 554 KB Download
PDF
Site 6, Eastbourne: Disposal of Long Leasehold InterestReport 223 KB DownloadRead as text
PDF
View item 60. as HTML 39 KBReport 39 KB Copy on its way

At this meeting

Whole meeting

On this subject at East Sussex

Search all
  1. Site 6, Eastbourne - Disposal of Long Leasehold InterestThis decision
  2. Variation of Conditions 5 & 6 of planning permission EB/677/CM to extend the operational hours of the site. Eastbourne Household Waste Recycling Site, St Philip's Avenue, Eastbourne, BN22 8NB - EB/812/CMRefused

More from East Sussex Resources and Climate Change

All decisions
MeetingDecisionOutcome
15 Sep 2026 Hollington Community Centre - Options for Next StepsRESOLVED to: 1) approve that the Council commences the Community Right to Bid process with a view to granting a lease... Approved Open
15 Sep 2026 Exclusion of Public and PressIt was RESOLVED to exclude the public and press from the meeting for the remaining agenda items on the grounds that i... Decided Open
11 Aug 2026 Robertsbridge Youth Centre - Options for Next StepsRESOLVED to: 1) approve the Council transferring the Charitable Trust, along with all assets held by the Trust, to Sa... Approved Open
11 Aug 2026 Exclusion of Public and PressRESOLVED to exclude the public and press from the meeting for the remaining agenda items on the grounds that if the p... Decided Open
21 Apr 2026 Orbis Shared Service Review - Consultation OutcomeRESOLVED to: 1) Note the feedback and conclusions from the Orbis staff consultations; 2) Agree to proceed with a sove... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies