It was RESOLVED to: (1) note the estimated costs and options for replacing Exceat Bridge; (2) agree to continue with the proposals for an offline two-lane replacement bridge (‘Option A’); (3) agree to re-direct £11.128m grant funding from the Newhaven and Peacehaven bus priority schemes set out in the Council’s Bus Service Improvement Plan (BSIP) to the Exceat Bridge Replacement Project; (4) approve the amendments to the 2025/26 BSIP funding allocation, reflecting the reallocation of £4m of funding to the Newhaven bus priority scheme; and (5) delegate authority to the Director of Communities, Economy and Transport to take all actions necessary to achieve the completion of the offline two-lane replacement bridge (‘Option A’), including but not limited to awarding any required construction contracts for the Bridge. Reasons 85.3 The Council’s preference has always been to complete the original proposal for an offline two-lane replacement bridge (Option A). However, this is only viable if additional external funding is identified. The diversion of BSIP funding from the Peacehaven and Newhaven bus priority schemes provides an opportunity to continue with Option A, subject to confirmation of the Orders by the Secretary of State and / or successful negotiations with the landowners. 85.4 Delegation of authority to the Director of Communities, Economy and Transport to take all actions necessary to achieve the completion of the ‘option A’ two-lane replacement bridge, including but not limited to awarding any required construction contracts for the Bridge will ensure the effective delivery of the project.
Word for word from the decision East Sussex published for this meeting.Source: democracy.eastsussex.gov.uk
Cabinet is recommended to: (1) Note the estimated costs and options for replacing Exceat Bridge; (2) Agree to continue with the proposals for an offline two-lane replacement bridge (‘Option A’); (3) Agree to re-direct £11.128m grant funding from the Newhaven and Peacehaven bus priority schemes set out in the Council’s Bus Service Improvement Plan (BSIP) to the Exceat Bridge Replacement Project; (4) Approve the amendments to the 2025/26 BSIP funding allocation, reflecting the reallocation of £4m of funding to the Newhaven bus priority scheme; and (5) Delegate authority to the Director of Communities, Economy and Transport to take all actions necessary to achieve the completion of the offline two-lane replacement bridge (‘Option A’), including but not limited to awarding any required construction contracts for the Bridge.
1. Background Affordability of bridge and design options
1.1Exceat Bridge spans the Cuckmere River on the A259 and is part of the Major Road Network. It is a key corridor between Eastbourne and Brighton, with an average annual daily traffic count of 11,500 vehicles and has morning and evening peaks of nearly 1000 vehicles per hour. The bridge creates a pinch point between Seaford and Eastbourne and was considered as a Levelling Up Fund bid given its strategic importance as a transport corridor and its poor condition. In 2021, ESCC was awarded £7,957,517 of Levelling Up Funding (LUF) towards the then estimated total cost of £10,590,517 for the replacement of Exceat Bridge with a new two-lane bridge on a better alignment and with improvements for pedestrians.
1.2Since then the project has suffered significant delays and costs have increased by over £10m. Given the Council’s current financial constraints, it is not currently possible to meet these additional costs from the Council’s capital programme. Further information about the reasons for the increase to project costs were detailed in a report presented to Cabinet on 4 March 2025 (sections 1.2-1.6)
1.3At the meeting on 4 March 2025, Cabinet were asked to consider the affordability of the project and the potential options for progressing the project. The options set out in that report are as follows:
Option A: Continue with plans for an offline, two-lane bridge with planning approval, noting the considerable price increase from the original estimated costs. Option B: Replace the existing bridge with a single-lane bridge in the same location using secured LUF funding, subject to approval from the Government. It is anticipated that this could be done under permitted development rights, although this is subject to confirmation from the South Downs National Park Authority (SDNPA).
Option C: Refurbish the existing bridge at ESCC cost, estimated at £2.5m. This option would require repayment of LUF funding. £4.543m has been received and £3.085m of this has already been spent.
1.4Although the two-lane bridge (‘Option A’) remained the preferred option, the paper asked Cabinet to consider an alternative, on-line, single-lane bridge that would be within budget (‘Option B’). The single-lane bridge would be very similar to the existing bridge, have fewer benefits for users and would require a 22 week road closure to construct; however, it could be delivered within the financial envelope available at that time.
Additional funding
1.5East Sussex County Council has been working with bus operators, including Brighton and Hove Bus and Coach Company Limited (B&H Buses) and other stakeholders to deliver the East Sussex Bus Service Improvement Plan (BSIP). £41.4m of funding was secured from the Department for Transport for East Sussex’s BSIP 1 in the autumn of 2022 for a variety of projects, including bus priority schemes along the A259 transport corridor.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Monitoring Report - Q1 2026/27It was RESOLVED to: 1) note the latest monitoring position for the Council; and 2) approve proposed amendments to per...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.