AI summaryCabinet recommended County Council approval of the 2026/27 Treasury Management Strategy Statement and Annual Investment Strategy, Prudential and Treasury Indicators 2026/27 to 2028/29, and Minimum Revenue Provision policy for 2025/26 and 2026/27. The plan includes a £2.7m Treasury Management budget increase. [D] [P8]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFour strategy and policy documents recommended for approval [D]
Money£2.7m budget increase [P8]Proposed for 2026/27 Treasury Management budget [P8]
What happens nextCounty Council consideration required [D]Four recommendations await County Council approval [D]
Who it affectsCouncil borrowing and investments [P8]Liquidity, revenue budget and debt maturities [P8]
What was decided
Cabinet resolved to recommend County Council approval of the Treasury Management Strategy Statement and Annual Investment Strategy for 2026/27.
Cabinet resolved to recommend approval of the Prudential and Treasury Indicators for 2026/27 to 2028/29.
Cabinet resolved to recommend approval of the Minimum Revenue Provision Policy Statement for 2025/26 and 2026/27 at Appendix 1, Section 3.
Why
The Council must prepare a treasury management policy and strategy and set Prudential Indicators for the next three years. These indicators help ensure capital investment plans are affordable, prudent and sustainable. Report P7
The strategy supports the Medium Term Financial Plan and Council Plan. It seeks suitable investment income, reviews the capital programme, uses cash balances to reduce borrowing costs and manages the borrowing portfolio. Report P8
Cash balances are expected to fall because of the deficit and borrowing need, so the Council will keep prioritising security and liquidity rather than increase investment risk. The strategy also reflects Exceptional Financial Support through a capitalisation direction. Report P8
What happens next
The County Council is asked to consider the four approval recommendations.
During 2026/27, officers will review the interest rate forecast, cash flow needs, revenue deficit and Capital Programme. Treasury activity will also be covered by a mid year review, an annual report at the close of the year and quarterly updates. Report P8, P9
If any strategy limits are felt to represent unacceptable risk, appropriate and immediate action will be taken. Report P11
The money
£2.7m Proposed increase to the 2026/27 Treasury Management budget. Report P8
£121m Total borrowing need between 2026/27 and 2028/29. Report P8
£70m Capitalisation direction borrowing in 2026/27. Report P8
£51m Capital programme borrowing between 2026/27 and 2028/29. Report P8
£50m Proposed internal borrowing level from 2026/27 onwards. Report P8
£75m Previously identified appropriate internal borrowing level in the longer term, around £75m. Report P8
3.59% Forecast investment performance for 2026/27, compared with 5.26% in 2024/25 and 4.63% in the first six months of 2025/26. Report P8
3.25% MUFG forecast Base Rate reduction by December 2026, from a peak of 5.25% during 2024/25. Report P8
Options considered
Chosen: Recommend approval of the Treasury Management Strategy Statement 2026/27. The Council must prepare a policy and strategy for managing investments and borrowing. Report P7
Chosen: Recommend approval of the Annual Investment Strategy 2026/27. Returns are expected to be moderate, while falling balances require continued management of security and liquidity. Report P8
Chosen: Recommend approval of the Prudential and Treasury Indicators 2026/27 to 2028/29. The Council must set indicators for the next three years so capital investment plans remain affordable, prudent and sustainable. Report P7
Chosen: Recommend approval of the Minimum Revenue Provision Policy Statement 2025/26 and 2026/27. The update clarifies interest rates used for annuity calculations and policy on capitalisation direction provision. Approval for both years supports prudent provision as early as possible. Report P8
Implications
Financial: The total borrowing need over 2026/27 to 2028/29 is £121m: £51m for capital programme borrowing and £70m for capitalisation direction in 2026/27. Report P8
Financial: The previously identified appropriate internal borrowing level was around £75m. It is proposed to reduce this to £50m from 2026/27, and external borrowing will be required during 2026/27. Report P8
Financial: The Treasury Management budget is proposed to rise by £2.7m in 2026/27. Further increases are modelled for future years. Report P8
Financial: Reviewing the Capital Programme is intended to reduce investment in core council funded programmes that would otherwise increase the borrowing requirement. Report P8
Legal: The Local Government Act 2003 and supporting regulations require the Council to set indicators for the next three years so capital plans are affordable, prudent and sustainable. An in year MRP policy change would require a revised statement for Council approval. Report P7, P8
Risk: The Council will not alter its investment risk appetite to increase income while balances are reducing. Security and liquidity remain the priority. Report P8
Risk: The financial position and strategy limits will be kept under constant review. Immediate action will be taken if the limits are felt to create unacceptable risk. Report P11
Other: Officers will continue seeking Environmental, Social and Governance investments that meet Council security requirements. Market options meeting both security requirements and the shortened investment horizon are currently limited. Report P8
Who and where
East Sussex County Council
Council services Report P8
Core council funded programmes Report P8
Capital programme Report P8
Borrowing portfolio Report P8
Investment portfolio Report P8
Revenue budget Report P8
Local members Report P14
Timeline
11 February 2025: Full Council formally approved the Treasury Management Strategy 2025/26, including the Minimum Revenue Provision Policy Statement for 2025/26. Report P8
16 December 2025: Cabinet received the Treasury Management Stewardship Report 2024/25 and Mid-Year report 2025/26. Report P9
27 January 2026: Cabinet resolved to recommend County Council approval of the four documents. Report P2
2026/27: The strategy provides for external borrowing, £70m capitalisation direction borrowing and a £2.7m Treasury Management budget increase. Report P8
by December 2026: MUFG forecast a 3.25% Base Rate. Report P8
between 2026/27 and 2028/29: The estimated total borrowing need is £121m. Report P8
2026/27 to 2028/29: The Prudential and Treasury Indicators cover a three year approval period. Report P7
by 2028/29: If reserves continue to fall, the Council may need to borrow for day to day activity as well as the capital programme. Report P8
Plain English for the jargon
Treasury Management Strategy Statement: The Council’s policy and strategy for managing investments and borrowing. [P7]
Annual Investment Strategy: The part of the strategy that sets the Council’s investment approach and limits. [P7] [P8]
Prudential and Treasury Indicators: Three year measures used to ensure capital investment plans are affordable, prudent and sustainable. [P7]
Minimum Revenue Provision: An annual revenue charge to repay an element of accumulated General Fund capital spend financed by borrowing. [P8]
Capitalisation direction: A form of Exceptional Financial Support allowing certain revenue expenditure to be treated as capital expenditure and funded by borrowing or capital receipts. [P8]
Internal borrowing: Use of the Council’s own reserves to initially fund its borrowing requirement. [P8]
Liability benchmark: An indicator showing new external borrowing may be needed and possible day to day borrowing by 2028/29. [P8]
Treasury Management Tool: A point in time model of borrowing costs offset by investment returns, reviewed regularly for reasonableness. [P8]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item55
Resolved
It was RESOLVED to recommend to the County Council to: 1) Approve the Treasury Management Strategy Statement for 2026/27; 2) Approve the Annual Investment Strategy for 2026/27; 3) Approve the Prudential and Treasury Indicators 2026/27 to 2028/29; 4) Approve the Minimum Revenue Provision (MRP) Policy Statement for 2025/26 and 2026/27 at Appendix 1 of the report (Section 3). Reason 55.3 The report fulfils the requirement to submit an annual/half yearly report in the form prescribed in the Treasury Management Code of Practice.The policy sets out the acceptable limits on ratings, investment periods, amounts to be invested and the borrowing strategy. The financial position is kept under constant review and if at any time it is felt that any of these limits represent an unacceptable risk appropriate and immediate action will be taken accordingly.
Word for word from the decision East Sussex published for this meeting.Source: democracy.eastsussex.gov.uk
Title of report: Treasury Management Strategy Statement 2026/27
Purpose of This report proposes the Treasury Management Strategy Statement report: for 2026/27, including the Minimum Revenue Provision Policy Statement for 2025/26 and 2026/27, and Annual Investment Strategy. The Council is also required to set Prudential Indicators as set out in the Prudential Code which are included in this strategy for approval.
RECOMMENDATIONS Cabinet is recommended to recommend Council to:
1) approve the Treasury Management Strategy Statement for 2026/27; 2) approve the Annual Investment Strategy for 2026/27; 3) approve the Prudential and Treasury Indicators 2026/27 to 2028/29; 4) approve the Minimum Revenue Provision (MRP) Policy Statement for 2025/26 and 2026/27 at Appendix 1 (Section 3). ________________________________________________________________________ 1. Background 1.1 A requirement under the Chartered Institute for Public Finance and Accountancy (CIPFA) Code of Practice for Treasury Management in the Public Services is to prepare a Treasury Management Policy and Strategy setting out the Council’s policies for managing investments and borrowing. 1.2 The Local Government Act 2003 and supporting regulations requires the Council to ‘have regard to’ the Prudential Code and to set Prudential Indicators for the next three years to ensure that the Council’s capital investment plans are affordable, prudent and sustainable. 1.3 The Treasury Management Strategy Statement (TMSS) for 2026/27 is presented in Appendix 1 to this report. The strategy includes the Treasury Management Policy Statement, the Annual Investment Strategy, Prudential and Treasury Indicators for the next three years and the annual Minimum Revenue Provision (MRP) Policy Statement. 1.4 The 2026/27 TMSS has been prepared within the context of the financial challenge being faced by the County Council over the Medium Term Financial Plan (MTFP). A summary of the outlook for Local Government finances is outlined in Annex F of Appendix 1 of this report. The treasury management strategy for the year seeks to compliment the MTFP and Council Plan by:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Monitoring Report - Q1 2026/27It was RESOLVED to: 1) note the latest monitoring position for the Council; and 2) approve proposed amendments to per...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.