Cabinet, Wednesday 16 September 2026 at 7.00pm

Water Play Strategy Update

Decided Executive 1 paper

AI summaryElmbridge Cabinet asked to delegate authority to award three Splashpad contracts within a £2.2 million budget, with works starting in January 2027 and completion by April 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedDeputy Chief Executive and Strategic Director to award
Money£2.2 million allocatedAlready approved at February Cabinet 2026
What happens nextContracts awarded October 2026Anticipated 6 October 2026, works January 2027
Who it affectsThree recreation groundsHersham, Leg O' Mutton Cobham, Molesey Hurst

What was decided

Cabinet is recommended to delegate authority to the Deputy Chief Executive and Strategic Director to award the contracts for the three Splashpad projects. Report P1, P3

The delegation applies within the existing approved budget, with the projects procured in separate Lots. Report P1, P2, P6

Why

A robust and compliant procurement process is under way, with works split into separate Lots and exempt from Section 24 requirements because procurement started before 3 July 2026. Report P2

Delegation allows timely award of contracts following tender evaluation, avoiding delay to a programme that must complete before 1 April 2027. Report P9, P11

What happens next

Tender moderation is scheduled for 15 September 2026, with contract award anticipated on 6 October 2026. Report P11

Subject to any planning approval needed, works are expected to start in January 2027, completing before 1 April 2027. Report P9, P11

The money

  • £2.2 million Total budget allocated across the three Splashpad projects, covering design, construction, utilities, planning, site preparation, landscaping and infrastructure. Report P10

Options considered

  • Recommended: Delegate authority to award contracts to the Deputy Chief Executive and Strategic Director. Procurement is compliant and underway; delegation avoids delay ahead of the April 2027 completion target. Report P1, P2, P3, P9

Implications

  • Legal: Projects are exempt from Section 24 requirements because procurement commenced before 3 July 2026, though further Section 24 approval may be needed if the sum awarded to a contractor exceeds the allocated budget. Report P2, P13
  • Financial: Budget was approved at February Cabinet 2026; principal risk is potential budget overrun. Report P12, P14
  • Risk: Risks include budget overruns, delays to Shadow Authority approval if required, contract award and delivery delays, and planning permission requirements affecting the programme. Report P14
  • Other: Consultation undertaken with CMB and the Portfolio Holder for Leisure, Culture and Commercial Strategy. Report P15

Who and where

  • Children under six and families across Elmbridge using the three recreation grounds Report P5, P9
  • Users of Hersham Recreation Ground (renewed Splashpad) and users of Molesey Hurst Recreation Ground and Leg O' Mutton Field, Cobham (new Splashpads) Report P5, P6
  • Prospective contractors submitting tenders for the separate Lots Report P2, P6, P11

Timeline

  • September 2023: Water Play Strategy adopted by Cabinet, agreeing a long-term programme including the initial three Splashpads. Report P5
  • February 2026: Budget of £2.2 million approved by Cabinet. Report P10, P12
  • Before 3 July 2026: Procurement process commenced, making the projects exempt from Section 24 requirements. Report P2
  • 2 September 2026: Tender submissions due. Report P11
  • 15 September 2026: Tender moderation scheduled. Report P11
  • 16 September 2026: Cabinet meeting considering delegation of contract award authority. Report P1, P3
  • 6 October 2026: Contract award anticipated. Report P11
  • January 2027: Works expected to commence, subject to any planning approval required. Report P11
  • Before 1 April 2027: Programme to be completed. Report P9

Plain English for the jargon

  • Splashpad: A recreational water play area with ground-level jets and features, designed here primarily for children under six.
  • Section 24: A statutory approval requirement referenced in the report that can apply to local authority contracts above certain thresholds; the report states the projects are exempt because procurement began before 3 July 2026.
  • Lot: A separately tendered package of works within a procurement exercise; the report states the three projects are being procured as separate Lots.
  • CMB: The Council's Corporate Management Board, which has been consulted on the project.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16/26

Resolved

View the decision text for item 16/26
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to Cabinet

Executive summary

Approval is sought to delegate authority to the Deputy Chief Executive and Strategic Director to approve the award of contracts and associated expenditure within the existing approved budget for the Council's three Splashpad projects at Hersham Recreation Ground, Leg O' Mutton Field Cobham, and Molesey Hurst Recreation Ground.

A robust and compliant procurement process is being undertaken, with the works divided into separate Lots. As the procurement process commenced prior to 3 July 2026, the projects are exempt from the requirements of Section 24.

Recommendation

(a) approves the delegation of authority to the Deputy Chief Executive and Strategic Director to award the contracts for the Council's three Splashpad projects.

Report:

Background

1. Following the adoption of the Water Play Strategy in September 2023, Cabinet agreed a long-term programme for sustainable water play across the Borough, with the initial phase delivering three Splashpad projects by March 2027. The strategy seeks to provide an equitable distribution of facilities, prioritise play opportunities for children under six, locate new Splashpads alongside income-generating amenities where possible, ensure suitable parking provision, and promote environmentally and financially sustainable solutions. This includes a preference for recirculating water systems where utility infrastructure allows, while carefully balancing capital investment and ongoing operational costs to ensure long-term sustainability.

2. The Council is progressing the delivery of three Splashpad projects across Elmbridge, comprising the renewal of the existing Splashpad at Hersham Recreation Ground and the installation of new Splashpads at Molesey Hurst Recreation Ground and Leg O' Mutton Field, Cobham. Each project will be procured separately and may be awarded to one or more suppliers, with the

OFFICIAL OFFICIAL

aim of enhancing local recreational facilities and providing high-quality, inclusive play spaces for the community.

3. The key objectives agreed by Cabinet are to deliver environmentally sustainable Splashpad facilities, primarily for children under six, with a preference for recirculating water systems where utilities allow and the use of solar panels where feasible. The programme is to be completed before 1 April 2027.

4. A total budget of £2.2 million has been allocated for the three Splashpad projects. This funding will cover all aspects of project delivery, including design and construction, utilities, planning and statutory approvals, site preparation, landscaping, and all associated infrastructure required to deliver fully operational Splashpad facilities.

5. The procurement process is underway, with tender submissions due on 2 September 2026, moderation scheduled for 15 September 2026, and contract award anticipated on 6 October 2026. Subject to potential planning approval, works are expected to commence in January 2027.

Financial implications N/A – budget has been approved during February Cabinet 2026

Legal implications Section 24 approval may be required if total sum awarded to contractor exceeds the allocated budget.

Risk implications The principal risks to the project are potential budget overruns, delays in obtaining Shadow Authority approval if required, delays to contract award and delivery, and any planning permission requirements that could impact the programme.

Principal consultees CMB has been consulted as well as Cllr Simon Waugh, the Portfolio Holder for Leisure, Culture and Commercial Strategy

Contact details Steven Ndangi Green Spaces Development Officer (Splashpads) [email protected]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Water Play Strategy UpdateReport 115 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
MR
Councillor Mike RollingsLeader, present
SW
Councillor Simon WaughDeputy Leader, present
AB
Councillor Alex BatchelorCommittee Member, present
GC
Councillor Gill CoatesCommittee Member, present
KH
Councillor Kirsty HewensCommittee Member, present
CJ
Councillor Caroline JamesCommittee Member, present
JL
Councillor Jez LanghamCommittee Member, present
AT
Councillor Ashley TillingCommittee Member, present
DB
Daniel BainbridgeOfficer, in attendance
AC
Andrew CooperOfficer, in attendance
DC
Dawn CreweOfficer, in attendance
TH
Tracey HulseSecretary, in attendance

All 14 on the meeting page

On this subject at Elmbridge

Search all
  1. Water Play Strategy UpdateThis decision
  2. Sustainable Water Play Strategy 2023 - 2029Decided

More from Elmbridge Cabinet

All decisions
MeetingDecisionOutcome
27 Oct 2026 Old Post Office EsherView the decision text for item 22/26 Decided Open
16 Sep 2026 Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 Decided Open
16 Sep 2026 Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 Decided Open
16 Sep 2026 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 Decided Open