Reigate Priory Junior School Relocation - Building Contract

Decided Executive 5 papers

AI summaryEast Surrey Shadow Authority Executive consented to Surrey County Council awarding the PCSA for Reigate Priory Junior School's relocation, within a £31m project budget. Stage two Design and Build consent will return in a future report. [P5][P7][P47]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedSurrey County Council may award it to the successful bidder. [P5]
Money£31m approved project budget [P47]Includes a £25m build contract budget and £10.7m DfE funding. [P47]
What happens nextStage two consent report [P7]Further report will seek consent for the stage two contract. [P7]
Who it affectsReigate Priory Junior School [P11]Relocation to Woodhatch Place as a five form entry school. [P41]

What was decided

The Executive consented to Surrey County Council awarding the PCSA to the successful bidder. [P5] Report P5

A further report will seek consent for the stage two Design and Build contract, while delegated authority covers PCSA price variations within 10% either side and the licences and agreements needed for the works. [P7][P8][P9] Report P7, P8, P9

The Leader will ask the Surrey County Council Leader for further analysis of a hybrid configuration combining redevelopment of part of the existing site with reuse of some existing building. [P10] Report P10

Why

The award secures the remaining £10.5m DfE PSBP2 grant and supports a long term, fit for purpose school building. [P12][P13] Report P12, P13

No comparable alternative supported by DfE meets the required timescale, and the Woodhatch Place relocation has full planning approval and avoids temporary accommodation. [P20][P24] Report P20, P24

Without approval, the £10.7m DfE funding is at risk, £2.3m of development costs would be charged to revenue and the existing site is unlikely to remain safe beyond 2029. [P27][P28][P29] Report P27, P28, P29

What happens next

Sign the PCSA during 23rd October to 30th October and start the contract on 2nd November 2026. [P99] Report P99

Complete Stage 2 contractor pricing from 11th January to 5th February 2027, then complete the procurement report and DfE review before finalising and issuing the Build Contract. [P99] Report P99

Bring a further report to a future Shadow Executive meeting for stage two consent, and request further analysis of a hybrid configuration at the existing site. [P7][P10] Report P7, P10

The money

  • £31m Approved project budget for the relocation. Report P47
  • £25m Build contract budget within the approved project budget. Report P47
  • £10.7m DfE PSBP2 funding contribution ringfenced to the project. Report P47
  • £10,514,321.82 Remaining capital grant funding used to offset the Schools Basic Need grant required. Report P68
  • £106,306.96 Historic Planning Infrastructure Contributions allocation reducing the Schools Basic Need requirement. Report P69
  • £20,204,371.22 Total Schools Basic Need grant funding requirement. Report P70
  • £2.3m Accumulated abortive development costs if the award is not approved. Report P29, P54
  • £4,540,000 Temporary classroom and toilet provision total. Report P33

Options considered

  • Chosen: Decision Option 1: award the PCSA with delegated approval for the stage two Design and Build contract. Identified as the recommendation. The successful bidder submitted the highest quality and most economically advantageous stage one tender of five bids. Report P17, P67
  • Rejected: Decision Option 2: do not approve the award. Without approval, the existing site is unlikely to sustain a safe learning environment beyond 2029, DfE funding is at risk and abortive costs arise. Report P27, P28, P29
  • Rejected: Decision Option 3: approve the PCSA only and require a subsequent report for the stage two contract Report P17

Implications

  • Financial: The £10.7m DfE contribution is ringfenced to this scheme and cannot be transferred to another scheme if delivery does not continue. [P47][P54] Report P47, P54
  • Financial: Without approval, £2.3m of abortive costs would be charged to revenue, while temporary classroom and toilet provision is estimated at £4,540,000 and is also unbudgeted. [P29][P30][P33] Report P29, P30, P33
  • Risk: The existing school site is unlikely to sustain a safe learning environment beyond 2029. [P27] Report P27
  • Risk: A later appointment or reprocurement could delay the project by at least one year, and the current tender offer expires on November 2026. [P54] Report P54
  • Legal: Surrey County Council has the power to enter the contract, but Shadow Executive consent is required under the Section 24 Direction. [P80][P81] Report P80, P81
  • Equalities: The new building is intended to improve access, the educational experience and wellbeing for pupils and staff. [P13][P35] Report P13, P35
  • Climate: The new building is operationally net zero and uses solar panels and air source heat pumps, while habitat enhancements deliver a 1% net gain in habitat units. [P89][P90] Report P89, P90
  • Staffing: The award has no direct workforce effect, but transition planning requires engagement with school staff and representatives. [P83][P85] Report P83, P85

Who and where

  • Pupils at Reigate Priory Junior School Report P13, P36
  • School staff Report P13, P83
  • Parents and families Report P59, P60
  • School governors Report P60
  • The local community Report P51, P60
  • Surrey County Council Report P79, P80
  • East Surrey Council Report P3, P77
  • The Education service Report P57, P83

Timeline

  • 27 January 2026: Surrey County Council Cabinet decided to relocate the school to Woodhatch Place as a five form entry junior school. [P41] Report P41
  • 13th October to 20th October 2026: East Surrey Shadow Authority review and approval to award the PCSA, including the statutory standstill period. [P99] Report P99
  • November 2026: The current tender offer expires. [P54] Report P54
  • 2nd November 2026: PCSA contract start date. [P99] Report P99
  • 11th January to 5th February 2027: Stage 2 contractor pricing period. [P99] Report P99
  • 5th April to 9th April 2027: Stage 2 procurement report. [P99] Report P99
  • 3rd May to 7th May 2027: Finalise and issue the Build Contract. [P99] Report P99
  • 30th August 2027 to 3rd May 2029: Construction of the new school and highway works, with construction float before completion. [P99] Report P99

Plain English for the jargon

  • PCSA: Pre Construction Services Agreement, covering work before the main building contract. [P2]
  • D&B: Design and Build contract for the main construction stage. [P2]
  • DfE: Department for Education. [P2]
  • PSBP2: Priority Schools Build Programme 2 funding programme. [P2]
  • SBN: Schools Basic Need grant. [P68]
  • PIC: Planning Infrastructure Contributions. [P69]
  • 5FE: Five form entry junior school model approved for the relocation. [P12][P41]
  • BNG: Biodiversity Net Gain. [P90]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item71/E

Resolved

View the decision text for item 71/E
Word for word from the decision Elmbridge published for this meeting. Source: mygov.elmbridge.gov.uk

Follow this further

Built from Elmbridge's papers

What the report saysPro

Report to East Surrey Shadow Authority Executive

Purpose of the report

This report has been prepared in line with the Section 24 General Consent preclusion amendment (Minute 6/E) made by the East Surrey Shadow Authority (ESSA) at the 08 June 2026 Executive meeting.

Specific consent is requested for approval to award the capital build contract for the relocation of Reigate Priory Junior School, in line with the decision already taken by Surrey County Council (SCC), Cabinet, 27 January 2026 (Minute 7/26 ‘Provision of primary school places in the pupil place planning area of Reigate’). The request includes the immediate award of the first stage, Pre-Construction Services Agreement (PCSA), following conclusion of the competitive tender exercise and subsequent delegated authority to enter into the main Design and Build (D&B) contract, as per the programme linked to the Department for Education (DfE) Priority Schools Build Programme 2 (PSBP2) grant funding.

In addition to the necessary governance, this report provides key data and evidence underpinning the SCC decision making to date as Education Authority, including detailed breakdown information used to substantiate the original data provided. For transparency, this information has been further supplemented with latest cost and budget positions to demonstrate the urgency and rationale for the recommendations (to approve the capital build contract), to secure a safe, purpose-built and energy efficient education asset for Reigate Priory Junior School and East Surrey Council.

Recommendations

It is recommended that the East Surrey Shadow Authority Executive resolves to:

1. Consent to Surrey County Council awarding the Pre-Construction Services Agreement (PCSA) to the successful bidder, as identified in section 9.1.7 of the Norse stage one tender report (Annex 1);

OFFICIAL OFFICIAL

2. That a further report seeking consent to award the stage two Design & Build contract, and finalise the transaction for that award, be brought to a future meeting of the Shadow Executive;

3. Delegate authority to approve PCSA contract price variations required for the project +/-10% to Surrey County Council’s Executive Director of Resources (s151 Officer) in consultation with Surrey County Council’s Director of Land & Property and Cabinet Member for Property, Waste and Infrastructure;

4. Delegate authority to Surrey County Council’s Director or Assistant Director(s) of Land & Property to authorise Surrey County Council to enter into all licences and agreements required to facilitate the capital works associated with the PCSA; and

5. Note that the Leader will write to the Leader of Surrey County Council to request that the Shadow Executive is provided with further analysis of a ‘hybrid’ configuration of school provision across the existing site, including a combination of redevelopment of part of the site and reuse of some of the existing building.

Reason for recommendations

1. Approval of the recommendations enables the future East Surrey Council to guarantee the sufficiency of suitable primary places in the education place planning area of Reigate and allows for the future reconsideration of school organisational options for the area as a whole, without the added complexity of navigating a relocation project at the same time as enacting a series of other school organisation and building changes. This follows the Surrey County Council Cabinet Report and subsequent decision of 27 January 2026 to relocate Reigate Priory Junior School to Woodhatch Place.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Dovers Green RIBA Stage 1 /EAppendix 2 3.2 MB Download
PDF
Holmesdale RIBA Stage 1 /EAppendix 3 3.7 MB Download
PDF
RPJS at Priory Park RIBA Stage 1 /EAppendix 4 3.6 MB Download
PDF
RPJS at Woodhatch RIBA Stage 1 /EAppendix 5 6.3 MB Download
PDF
Reigate Priory Junior School Relocation: Building ContractReport 362 KB DownloadRead as text

At this meeting

Whole meeting
71/EReigate Priory Junior School Relocation - Building ContractThis decision

Who was there

0 of 1 attended
TH
Tracey HulseCommittee Member, expected

More from Elmbridge East Surrey Shadow Authority Executive

All decisions
MeetingDecisionOutcome
9 Nov 2026 Implementation Programme UpdateView the decision text for item 6. Decided Open
9 Nov 2026 2026/27 Quarter 1 Budget Monitoring Report of Existing East Surrey CouncilsView the decision text for item 7. Decided Open
9 Nov 2026 Strategic PartnershipsView the decision text for item 8. Decided Open
9 Nov 2026 Equality Diversity and Inclusion ApproachView the decision text for item 9. Decided Open
9 Nov 2026 Performance Management ApproachView the decision text for item 10. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies