Resolved
View the decision text for item 71/E
AI summaryEast Surrey Shadow Authority Executive consented to Surrey County Council awarding the PCSA for Reigate Priory Junior School's relocation, within a £31m project budget. Stage two Design and Build consent will return in a future report. [P5][P7][P47]
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
View the decision text for item 71/E
This report has been prepared in line with the Section 24 General Consent preclusion amendment (Minute 6/E) made by the East Surrey Shadow Authority (ESSA) at the 08 June 2026 Executive meeting.
Specific consent is requested for approval to award the capital build contract for the relocation of Reigate Priory Junior School, in line with the decision already taken by Surrey County Council (SCC), Cabinet, 27 January 2026 (Minute 7/26 ‘Provision of primary school places in the pupil place planning area of Reigate’). The request includes the immediate award of the first stage, Pre-Construction Services Agreement (PCSA), following conclusion of the competitive tender exercise and subsequent delegated authority to enter into the main Design and Build (D&B) contract, as per the programme linked to the Department for Education (DfE) Priority Schools Build Programme 2 (PSBP2) grant funding.
In addition to the necessary governance, this report provides key data and evidence underpinning the SCC decision making to date as Education Authority, including detailed breakdown information used to substantiate the original data provided. For transparency, this information has been further supplemented with latest cost and budget positions to demonstrate the urgency and rationale for the recommendations (to approve the capital build contract), to secure a safe, purpose-built and energy efficient education asset for Reigate Priory Junior School and East Surrey Council.
It is recommended that the East Surrey Shadow Authority Executive resolves to:
1. Consent to Surrey County Council awarding the Pre-Construction Services Agreement (PCSA) to the successful bidder, as identified in section 9.1.7 of the Norse stage one tender report (Annex 1);
OFFICIAL OFFICIAL
2. That a further report seeking consent to award the stage two Design & Build contract, and finalise the transaction for that award, be brought to a future meeting of the Shadow Executive;
3. Delegate authority to approve PCSA contract price variations required for the project +/-10% to Surrey County Council’s Executive Director of Resources (s151 Officer) in consultation with Surrey County Council’s Director of Land & Property and Cabinet Member for Property, Waste and Infrastructure;
4. Delegate authority to Surrey County Council’s Director or Assistant Director(s) of Land & Property to authorise Surrey County Council to enter into all licences and agreements required to facilitate the capital works associated with the PCSA; and
5. Note that the Leader will write to the Leader of Surrey County Council to request that the Shadow Executive is provided with further analysis of a ‘hybrid’ configuration of school provision across the existing site, including a combination of redevelopment of part of the site and reuse of some of the existing building.
1. Approval of the recommendations enables the future East Surrey Council to guarantee the sufficiency of suitable primary places in the education place planning area of Reigate and allows for the future reconsideration of school organisational options for the area as a whole, without the added complexity of navigating a relocation project at the same time as enacting a series of other school organisation and building changes. This follows the Surrey County Council Cabinet Report and subsequent decision of 27 January 2026 to relocate Reigate Priory Junior School to Woodhatch Place.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Dovers Green RIBA Stage 1 /EAppendix 2 | 3.2 MB | Download |
PDF |
Holmesdale RIBA Stage 1 /EAppendix 3 | 3.7 MB | Download |
PDF |
RPJS at Priory Park RIBA Stage 1 /EAppendix 4 | 3.6 MB | Download |
PDF |
RPJS at Woodhatch RIBA Stage 1 /EAppendix 5 | 6.3 MB | Download |
PDF |
Reigate Priory Junior School Relocation: Building ContractReport | 362 KB | DownloadRead as text |
Follow East Surrey Shadow Authority Executive at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2026 | Implementation Programme UpdateView the decision text for item 6. | Decided | Open |
| 9 Nov 2026 | 2026/27 Quarter 1 Budget Monitoring Report of Existing East Surrey CouncilsView the decision text for item 7. | Decided | Open |
| 9 Nov 2026 | Strategic PartnershipsView the decision text for item 8. | Decided | Open |
| 9 Nov 2026 | Equality Diversity and Inclusion ApproachView the decision text for item 9. | Decided | Open |
| 9 Nov 2026 | Performance Management ApproachView the decision text for item 10. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.