Community and Wellbeing Committee approved this item on Tuesday 23 January 2018. Below is the council's own wording, with the papers it was decided on.
Following consideration, the Committee: (1) Submitted the Capital Programme for 2018/19 as identified in section 4 and 5 of the report to the Council for approval on 20 February 2018. (2) Confirmed that it supported all of the schemes included in the provisional programme for 2019-21 as identified in section 6 of the report. And noted that:- a) Schemes subject to external funding from Disabled Facilities Grant would only proceed when funding had been received . b) schemes for 2019-21 were provisional pending an annual review of funds available for capital investment.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
2.1The Capital Strategy was last agreed by the Council on 14 February 2017 at which time the capital programme was approved for 2017/18. Schemes for 2018-2020 were provisional pending the annual budget review and an annual assessment of funds for capital investment.
2.2The Financial Policy Panel (‘the Panel’) provided the Capital Member Group (CMG) with a remit for the preparation of a capital programme for 2018/19. Under this remit, CMG assessed all capital bids and recommended a programme to the Panel for approval on 5 December 2017.
2.3The programme presented to the Panel assumed funding from capital receipts and government grants. The Panel were advised that the proposed level of investment of £3.2 million over three years 2018/19 to 2020/21, of which £1.475 million was to be funded from capital receipts, would reduce the available capital receipts balance to £1.6 million at the end of this period. The agreed minimum threshold of capital receipts is £1 million. In order to slow the depletion of capital reserves, FPP supported a proposal that any surplus revenue funds, arising principally from dividend income received from Epsom & Ewell Property Investment Company (EEPIC), should be allocated to fund the capital programme. COMMUNITY & WELLBEING COMMITTEE 23 JANUARY 2018
2.4In total, MTFS projections show that £540k revenue funds are available to fund the capital programme in 2018/19, subject to the risk identified in paragraphs 11.4 and 11.5 of this report. It has been recommended to the respective policy committees that the entirety of the Strategy & Resources capital programme and part of Environment’s capital programme be funded from revenue, altogether totalling £540k.
2.5The use of £540k of revenue funds for these schemes would ease the use of capital receipts and maintain the reserves at £2.16 million at the end of this period.
2.6The Panel’s guidance relevant to this policy committee’s recommendations was as follows:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Community and Wellbeing Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
Homelessness Expenditure UpdateThe Committee unanimously resolved to: (1) Note the priority actions points which have been taken to manage homelessn...
Options for the Future of the MuseumThe Committee resolved (6 for, 1 abstaining) to: (1) Option 2: Invest in improvement of the Museum (should option 2 b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.