Resolved
Agreed to receive the internal audit progress report for 2017/18.
Audit and Scrutiny Committee agreed this item on Tuesday 19 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed to receive the internal audit progress report for 2017/18.
2.1The Committee’s Terms of Reference include a responsibility to monitor recommendations from the external and internal auditors.
2.2The Committee endorsed the Internal Audit Plan for 2017/18 in April 2017. Throughout its work programme 2017/18 the Committee has received progress reports from the Internal Auditors against this plan.
2.3The Committee last received an Internal Audit Progress Report for 2017/18 on 19 April 2018. At this time there were five outstanding reviews - Cyber Security, IT General Controls, Private Sector Leasing, Data Protection/GDPR and the supplementary work on commercial property acquisitions. Audit, Crime & Disorder and Scrutiny Committee 19 June 2018 2.4 As reported to the Committee in April 2018, two audits have been deferred until 2018/19 (Housing Needs and Temporary Accommodation Initiatives). These deferrals were requested by management due to resource implications arising from the Homelessness Reduction Act 2017. Both audits have been added to the 2018/19 internal audit plan.
2.5The Commercial Property Acquisitions audit was extended to include supplementary assurance regarding the governance around the two properties purchased through the Council’s wholly owned company, Epsom & Ewell Property Investment Company Ltd (EEPIC). The initial Commercial Property Acquisitions audit, reported to this Committee in November 2017, provided assurance regarding the purchase of the Council’s two commercial properties.
2.6The Committee will wish to note that RSM has undertaken a follow up of the actions agreed to address previous years’ internal audit findings; adequate progress has been reported. Details have been included in the Annual Internal Audit Report elsewhere on this Agenda (Item 6).
3 Proposals
3.1A summary of progress against the Internal Audit Plan 2017/18 is shown below. Since 19 April 2018 three further audits have been finalised – Private Sector Leasing, Data Protection/GDPR and Commercial Property Acquisitions supplementary report (Part 2) One audit report from the Audit Plan for 2017/18 remains outstanding relating to Cyber Security and IT General Controls. The Debrief meeting has been held. This will be reported to the next Committee in November as part of the 2018/19 monitoring.
3.2It is proposed that the Committee receives the last Internal Audit Progress Report for 2017/18 attached at Annex 1.
Assignment Reported Opinion H M L
Business Process Review - 19 April 18 Reasonable 3 Homelessness Assurance
Booking System and Income 23 November 17 Reasonable 3 Collected Assurance
Emergency Planning and Civil 23 November 17 Reasonable 3 4 Contingencies Assurance
Delivery of the Local Plan 8 February 18 Reasonable 1 1 Assurance Audit, Crime & Disorder and Scrutiny Committee 19 June 2018
Assignment Reported Opinion H M L
Property Management 23 November 17 Reasonable 5 Assurance
Cyber Security & IT General 22 November 18 De brief Controls
Commercial Property Acquisitions 23 November 17 Substantial - - - Assurance
Commercial Property Acquisitions 19 June 18 Substantial Supplementary report Assurance
Housing Needs Deferred to 2018/19
Transport Contract Management 8 February 18 Substantial 3 Assurance
Private Sector Leasing 19 June 18 Substantial 1 Assurance
Temporary Accommodation Deferred to Initiatives 2018/19
Planning Income 19 April 18 Substantial 3 Assurance
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Monitoring Report Annex 1Appendix | 2 MB | Download |
PDF |
Internal Audit Monitoring ReportReport | 84 KB | DownloadRead as text |
Follow Audit and Scrutiny Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Use of Urgent Decisions Annual ReportA Member raised the issue of reasons given for taking an urgent decision which he said were conflicting and were appl... | Agreed | Open |
| 19 Mar 2026 | Work Programme - March 2026A Member sought an update and clarification on Community and Wellbeing Committee deferred decision. Following call-in... | Deferred | Open |
| 5 Feb 2026 | Work Programme - February 2026Decision 158 (UD158) and the process in which that was taken. It was an exempt officer decision. That decision could ... | Agreed | Open |
| 25 Jul 2024 | Use of Delegated Powers Annual ReportDecision 118 and 119. A Member of the Committee asked why decision 118 took two months to be authorised and then was ... | Noted | Open |
| 18 Jul 2023 | External Auditor's Annual Report - 2021/22Resolved (5 for, 1 abstained, and the Chair not voting) to: (1) Receive the Auditor’s Annual Report; (2) Note the man... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.