Licensing and Planning Policy Committee noted this item on Thursday 24 January 2019. Below is the council's own wording, with the papers it was decided on.
It was resolved: That the Committee: (1) noted the good progress being made in preparing the new Local Plan; (2) noted the government’s Housing Delivery Test and the implications that would follow; and (3) agreed to advise the Planning Committee that planning applications should be determined with the knowledge that there is not a demonstrable five year housing land supply.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
Licensing and Planning Policy Committee 24 January 2019
Progress on the Local Plan
Head of Service/Contact: Ruth Ormella, Head of Planning Urgent Decision?(yes/no) No If yes, reason urgent decision required: N/A Annexes/Appendices (attached): None stated Other available papers (not attached): Epsom & Ewell Local Plan Programme July 2018
Report summary Progress against the new Local Plan’s project milestones continues to be maintained. The focus is currently upon completing a robust and proportionate evidence base that will support the new Local Plan through the forthcoming submission and examination stages. In parallel, the Borough Council continues to engage with its partners to identify including stakeholder engagement on future community infrastructure improvements.
The revised National Planning Policy Framework introduces a Housing Delivery Test that assesses the performance of local planning authorities in meeting the government’s objective to significantly boost housing delivery. The first assessment under this new regime took place at the end of 2018. This report provides an overview of the Delivery Test, the Borough’s performance and the implications for our plan and decision making.
Recommendation (s)
The Committee
(1) notes the good progress being made in preparing the new Local Plan;
(2) notes the government’s Housing Delivery Test and the implications that will follow; and
(3) advises the Planning Committee that planning applications should be determined with the knowledge that there is not a demonstrable five year housing land supply. Licensing and Planning Policy Committee 24 January 2019 1 Implications for the Council’s Key Priorities, Service Plans and Sustainable Community Strategy
1.1The delivery and implementation of the Epsom & Ewell Local Plan contributes towards all of the Council’s Key Priorities. The new Epsom & Ewell Local Plan is critical as it will set out how sustainable growth, particularly in relation to new housing, will be delivered during the plan period.
2 Progress on our Local Plan
2.1At the November 2018 Licensing & Planning Policy Committee, Members agreed to receive a regular report that provides an update on the progress being made on the preparation of the new Local Plan against the milestones identified by the Local Plan Programme (July 2018). This is the second Local Plan Progress report to the Licensing & Planning Policy Committee.
2.2The Borough Council continues to make good progress against the timetable and milestones set out in the Local Plan Programme. The current focus is on preparing a robust evidence base to ensure the new Local Plan meets the tests of soundness by being “justified”1. Work on the evidence base is already advanced. During November 2018 the Committee approved the Longmead and Nonsuch Industrial Estates Capacity Study, and the current agenda includes a report on the Borough- wide Urban Capacity. In the build-up to public consultation on the Pre- Submission Draft of the new Local Plan, the evidence base will be expanded to include the following studies –
Revised Strategic Housing Market Assessment
Strategic (Development) Viability Assessment
Green Infrastructure/ Open Space Study (Update)
Employment Land Assessment (update)
Borough-wide Food Retail Impact Assessment
Strategic Flood Risk Assessment Level 22
Self-Build and Custom Housing Need Study
2.3The above studies will be reported to the Committee as appropriate and will help inform the development of the emerging policy and new Local Plan.
1 This is set out under NPPF Paragraph 35. 2 As required – the requirement for this additional work will only be triggered should any of the site
allocation options be subject to flood risk. Licensing and Planning Policy Committee 24 January 2019 3 Progress on the Infrastructure Delivery Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Licensing and Planning Policy Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
Authority Monitoring Report 2025-2026The Committee resolved (8 for, 1 against) to: 1) Note the content of the Authority Monitoring Report for the 2025/26 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.