Planning Committee, Wednesday 13 February 2019 at 7.30pm

Five Year Housing Land Supply Statement

Agreed Planning 1 paper

Planning Committee agreed this item on Wednesday 13 February 2019. Below is the council's own wording, with the papers it was decided on.

Item56

Resolved

It was therefore agreed that the Head of Planning would advise the Planning Committee on the position of the housing land supply. Accordingly the Committee was informed that there was 1 year of housing land supply. However, it was acknowledged that in view of the potential for sites to come forward (as identified in the Urban Housing Capacity Study), there was potential to meet up to 50% of the required number of homes from developing in existing urban areas. It was noted that if the authority did not have a demonstrable 5 year housing land supply and applications were refused there was a risk of incurring a penalty of up to 20% increase on top of the housing target (579 homes annually). However it was further noted that officers were optimistic of achieving a 5 year land supply and in addition any penalty that was levied would decrease as the land supply increased. To assess the basis for the under delivery and identify actions to increase the land supply a Housing Delivery Action plan would be prepared in line with national planning guidance. It was highlighted that during the transition period when the Housing Delivery Action Plan was being developed an important way to minimise the risk of incurring any penalties was to be mindful of the possible levy when determining planning applications. Nevertheless it was also emphasized that when considering applications attention should always be on quality outcomes and sustainable development, and these aspects would be the focus of the pre-app stage. To that end it was agreed that the Planning Committee would receive regular updates on the status of the 5 year land supply.
Word for word from the decision Epsom and Ewell published for this meeting. Source: democracy.epsom-ewell.gov.uk

Follow this further

Built from Epsom and Ewell's papers

What the report saysPro

Report to Planning Committee

Planning Committee 13/02/2019 Update Report from the Licencing and Planning Policy Committee: Five Year Housing Land Supply Statement

Report by: Ruth Ormella, Head of Planning

At the Licencing and Planning Policy Committee of 24th January 2019 Item 6 included a report that accompanied the Urban Housing Capacity Study detailing the extent to which the urban areas could accommodate the annual housing requirement of 579 homes.

The third recommendation for Item 6 was as follows.

The Licencing and Planning Policy Committee advises the Planning Committee that planning applications should be determined with the knowledge that there is not a demonstrable 5 year housing land supply.

This recommendation was unanimously supported and the Head of Planning was instructed to formally advise the Planning Committee through an item on the next Planning Committee agenda of the 5 year housing supply position statement.

The report and evidence confirmed that there is approximately 1 year of housing land supply.

Implications

Planning applications are to be determined having regard for the update to date policies and all other material planning considerations. The NPPF sets out in Chapter 5 how authorities are to deliver a sufficient supply of homes.

Paragraph 11 of the NPPF raises the importance of a 5 year housing land supply in relation to decision making and sets out the meaning of the presumption in favour of sustainable development.

Members are encouraged to read Paragraph 11 in full and have particular reference to footnote 7, which makes clear that applications involving housing should be favourably determined where the local planning authority cannot demonstrate a five year supply of deliverable housing sites.

Deliverable housing sites are made up from the pipeline of planning permissions and sites which the Local Planning Authority are aware may come forward with planning applications. The Urban Housing Capacity Study identified the potential for sites to come forward from the existing urban areas, and that these could have the potential to meet up to 50% of the total number of homes required based on the housing delivery requirement of 579. A five year housing land supply position is a dynamic figure that adjusts as further sites secure permission and come forward counting towards the housing land supply. Planning Committee 13/02/2019 All planning applications for housing being considered by the Planning Committee will include a section which confirms the 5 year housing land position statement and other housing related matters so as to ensure Members are fully updated on the position when taking-decisions and applying the presumption in favour of sustainable development.

A Housing Delivery Action Plan is to be prepared in line with national planning guidance to assess the cause of under delivery and identify actions to increase delivery in future years. Members will be briefed as this work is undertaken.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Five Year Housing Land Supply StatementReport 51 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 18 attended
HR
Councillor Humphrey ReynoldsChairman, present
DR
Councillor David ReeveVice-Chair, present
MA
Councillor Michael Arthur MBE FCIOB FCMICommittee Member, present
JB
Councillor John BeckettCommittee Member, present
LD
Councillor Lucie DallenCommittee Member, apologies
JM
Councillor Jan MasonCommittee Member, present
TM
Councillor Tina MountainCommittee Member, apologies
PO
Councillor Peter O'DonovanCommittee Member, present
MO
Councillor Martin OlneyCommittee Member, present
VR
Councillor Vince RomagnuoloCommittee Member, present
CS
Councillor Clive SmitheramCommittee Member, present
MT
Councillor Mike TeasdaleCommittee Member, present

All 18 on the meeting page

More from Epsom and Ewell Planning Committee

All decisions
MeetingDecisionOutcome
5 Nov 2026 26/00879/FUL: The Lodge, Bourne Hall, Sprng Street, Ewell, Surrey, KT17 1UDFollowing consideration, Councillor Liz Frost proposed a motion that the Officer recommendation be agreed as set out ... Agreed Open
5 Nov 2026 26/00880/LBA: The Lodge, Bourne Hall, Spring Street, Ewell, Surrey, KT17 1UDFollowing consideration, Councillor Liz Frost proposed a motion that the Officer recommendation be agreed as set out ... Agreed Open
9 Jul 2026 26/00572/FUL Epsom Playhouse, Ashley Avenue, Epsom, Surrey, KT18 5ALFollowing consideration, Councillor Robert Leach proposed a motion that the Officer recommendation be agreed. The pro... Agreed Open
9 Jul 2026 25/01132/TPO Drummond Gardens, Christ Church Mount, Epsom KT19 8RPFollowing consideration, Councillor Neil Dallen proposed a motion that the Officer recommendation be agreed. The prop... Agreed Open
18 Jun 2026 25/01483/FUL Woodcote Stud, Wilmerhatch Lane, Epsom, KT18 7UEFollowing consideration, Councillor Dallen proposed a motion that the Officer recommendation be agreed. The proposal ... Agreed Open