Community and Wellbeing Committee approved this item on Tuesday 19 January 2021. Below is the council's own wording, with the papers it was decided on.
Following consideration, the Committee unanimously resolved: (1) to submit the capital programme for 2021/22 as identified in section 4 of the report to the Council for approval on 16 February 2021; (2) to confirm that it supported all of the schemes included in the provisional programme for 2022-24 as identified in section 4 of this report; (3) to note that:- (a) schemes subject to external funding from Disabled Facilities Grants only proceed when funding has been received; (b) schemes for 2022-24 are provisional pending an annual review of funds available for capital investment.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
1.1To seek the Committee’s approval to submit the proposed capital programme for 2021/22 to Council in February 2021 and confirm that it supports the schemes included in the provisional programme for 2022-24. Community and Wellbeing Committee 19 January 2021 2 Background
2.1The Capital Strategy was last agreed by the Council on 13 February 2020 at which time the capital programme was approved for 2020/21. Schemes for 2021-2023 were provisional pending the annual budget review and an annual assessment of funds for capital investment.
2.2Strategy and Resources provided the Capital Member Group (CMG) with a remit for the preparation of a capital programme for 2021/22. Under this remit, CMG assessed all capital bids and recommended a programme to Financial Policy Panel (‘the Panel’) for approval on 1 December 2020.
2.3The programme presented to the Panel assumed funding from capital receipts, revenue funding, reserves and government grants. The Panel were advised that the proposed level of investment over three years 2021/22 to 2023/24 is £2.7m, of which £255k is to be funded from a planned contribution from revenue. Combined with funding from other sources including CIL, S106 and Disabled Facilities Grants, this will allow the forecast available capital receipts to remain at £2.57 million at the end of this period. The agreed minimum threshold of capital receipts is £1 million.
2.4The receipts forecast assumes a £300k revenue contribution to fund capital schemes in 2021/22, which is subject to the budget being approved at Council in February 2021. With £255k allocated to fund the proposed capital programme, the balance of the revenue contribution of £45k would be held in a reserve for funding future capital programmes.
2.5The Panel’s guidance relevant to this policy committee’s recommendations was as follows:-
2.5.1 Priority schemes identified by the Capital Member Group should be presented with project appraisals to the policy committees in January to establish whether there is support for the individual projects, with any projects not supported being removed from the draft programme.
2.5.2 Schemes identified in section 4 of this report, totalling £805k, £75k of Community Infrastructure Levy receipts, £110k of S106 receipts and £620k of external grant funding, should be included in the 2021/22 capital programme, subject to support for the project appraisal by this Committee and subject to external funding being received before expenditure is committed.
3 Proposals
3.1The Committee is asked:-
3.1.1 To approve the proposed capital programme for 2021/22; and
3.1.2 To agree to the provisional programme for 2022-24. Community and Wellbeing Committee 19 January 2021 3.2 The timing of the programme should be based on the ability to deliver with a realistic number of projects in any one year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Community and Wellbeing Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
Homelessness Expenditure UpdateThe Committee unanimously resolved to: (1) Note the priority actions points which have been taken to manage homelessn...
Options for the Future of the MuseumThe Committee resolved (6 for, 1 abstaining) to: (1) Option 2: Invest in improvement of the Museum (should option 2 b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.