Resolved
Agreed to note the status of the individual Key Priority Targets 2020/21 as at the end of January 2021, set out at Appendix 1. (2) Considered the latest update on all red and amber status targets set out at Appendix 2.
Audit and Scrutiny Committee agreed this item on Thursday 8 April 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed to note the status of the individual Key Priority Targets 2020/21 as at the end of January 2021, set out at Appendix 1. (2) Considered the latest update on all red and amber status targets set out at Appendix 2.
This report provides an update on progress made against the Key Priority Targets 2020/21 as at the end of January 2021.
Recommendation (s) The Committee is asked to:
(1) note the status of the individual Key Priority Targets 2020/21 as at the end of January 2021, set out at Appendix 1.
(2) consider the latest update on all red and amber status targets set out at Appendix 2.
1.1The Audit, Crime & Disorder and Scrutiny Committee has a responsibility under Paragraph 4 of the Overview and Scrutiny Procedure Rules of the Constitution for monitoring progress on the Council’s Corporate Plan.
1.2In line with this responsibility, the Committee is asked to consider progress made against the Key Priority Targets (KPTs) 2020/21 as at the end of January 2021. Audit, Crime and Disorder and Scrutiny Committee 8 April 2021 2 Background
2.1The Committee was presented with the KPTs 2020/21 at its meeting on 19 November 2020. It was informed that in light of the on-going impact of COVID-19 on the Council and its services, the targets contained within the Service Delivery Plan (SDP) 2020/21 had been revised to reflect what could be delivered. These revised targets were subsequently agreed through the Leadership Team and reported to the Member Recovery cell. The KPTs 2020/21 are based on the revised SDP priorities. They reflect the top three priorities within each service area and the overall top five priorities agreed corporately.
2.2It was highlighted in the report to the Committee on 19 November that the need to respond to the on-going pandemic might impact on the delivery of priorities going forward. Particular areas that might be impacted were highlighted as the Communications Review, potential for Grounds Maintenance Shared Service and the Climate Change Action Plan.
2.3Throughout this reporting period the Council has continued to provide COVID-19 support to residents, businesses and staff. It has responded to the changing Government restrictions, the Government introduced a further lockdown at the beginning of January 2021 due to increased cases of coronavirus, and has responded to new Government schemes requiring local implementation. However 69% of the targets are currently recorded as green or achieved, which is significant given that we remain in the third national lockdown which has impacted on the delivery of new services, functions and staff resources.
2.4The overview attached at Appendix 1 sets out the RAG status of the individual KPTs 2020/21 as at the end of January 2021. This is the first progress report brought to the Committee for 2020/21. The overall percentage of targets achieved or assigned green, amber or red status is set out in Table 1 below. ‘Achieved’ includes those targets achieved, but not in accordance with the target date.
Table 1
Status Number %
Achieved 12 24
Green 22 45
Amber 7 14
Red 8 16
Information only 3 - Audit, Crime and Disorder and Scrutiny Committee 8 April 2021
TOTAL 52 99*
* Percentages may not add up to 100 due to rounding.
2.5Work against the targets 2020/21 is generally progressing well. Eight targets have however been assigned red status and seven targets assigned amber status. As highlighted to Committee in November, the on- going pandemic response has impacted progress against the target on the potential for a shared Grounds Maintenance service, and slowed progress made against the Communications Review Action Plan. A report to Environment & Safe Communities Committee in January 2021 however, showed that some good progress had been made against the Climate Change Action Plan.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Four Year Plan: Progress Report 2020/21 Appendix 1Appendix | 87 KB | Download |
PDF |
Four Year Plan: Progress Report 2020/21 Appendix 2Appendix | 63 KB | Download |
PDF |
Four Year Plan: Progress Report 2020/21Report | 86 KB | DownloadRead as text |
Follow Audit and Scrutiny Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Use of Urgent Decisions Annual ReportA Member raised the issue of reasons given for taking an urgent decision which he said were conflicting and were appl... | Agreed | Open |
| 19 Mar 2026 | Work Programme - March 2026A Member sought an update and clarification on Community and Wellbeing Committee deferred decision. Following call-in... | Deferred | Open |
| 5 Feb 2026 | Work Programme - February 2026Decision 158 (UD158) and the process in which that was taken. It was an exempt officer decision. That decision could ... | Agreed | Open |
| 25 Jul 2024 | Use of Delegated Powers Annual ReportDecision 118 and 119. A Member of the Committee asked why decision 118 took two months to be authorised and then was ... | Noted | Open |
| 18 Jul 2023 | External Auditor's Annual Report - 2021/22Resolved (5 for, 1 abstained, and the Chair not voting) to: (1) Receive the Auditor’s Annual Report; (2) Note the man... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.