(1) receive the review of the Building Control chargeable account following the end of the 2020/21 financial year as provided within the report.
Environment Committee decided this item on Tuesday 19 October 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) receive the review of the Building Control chargeable account following the end of the 2020/21 financial year as provided within the report.
This report summarises the Building Control chargeable account for 2020/21.
Recommendation (s) The Committee is asked to:
(1) receive the review of the Building Control chargeable account following the end of the 2020/21 financial year as provided within this report.
1.1Part of the Building Control business is the need to ensure that the costs for delivering the Service is covered in the fee charging schedule. This report relates to the fee charging schedule for the delivery of this service.
2.1Applications for Building Regulations approval attract charges to cover the cost of checking plans and inspecting work on site to verify compliance.
2.2The principles of the charges’ regulations require authorities to ensure that the price charged is an accurate reflection of the costs of carrying out the chargeable Building Control functions and for giving chargeable advice relating to Building Regulations. Authorities should not increase their charges above the level of their costs. The principles in the charges’ regulations require authorities to achieve full cost recovery on their Building Regulation chargeable work and determine standard and individual charges that reflect the cost of the service on individual building projects. Environment and Safe Communities Committee 19 October 2021 2.3 The Building (Local Authority Charges) Regulations 2010 provide that a review of the level of charges is undertaken at the end of the financial year and that a statement is prepared which outlines the chargeable costs, the chargeable income and the amount of any surplus or deficit.
3 The Chargeable Account
3.1The purpose of reviewing the level of charges is to both reflect the actual cost of undertaking the work and to ensure that the service can respond to Building Regulations applications.
3.2The end of financial year review of the Building Regulations chargeable account for 2020/21 (Appendix 1) indicates a deficit of £38k for the year. The non-chargeable element was a cost of £93k, resulting in a total cost of the service to the Council of £131k. The previous year saw a deficit on the chargeable account of £7k, and a cost of £104k for the non- chargeable element, resulting in a total cost of the service to the Council of £111k.
3.3Building Control charges have been increased annually over the past two years and the deficit is not attributed to charges being set too low. The service had seen falling income levels prior to the pandemic due to the difficulty in competing with other providers in the sector. The service has also been impacted by both the pandemic and a regional lack of suitable staff resulting in several vacancies in the team, both of which have impacted income levels.
3.4As a result of the recruitment issues and decline in income, Members agreed at Strategy & Resources Committee in September 2021 to pursue an alternative option for the delivery of the Building Control service in the future.
4 Risk Assessment
Legal or other duties
4.1Impact Assessment
4.1.1 None.
4.2Crime & Disorder
4.2.1 None.
4.3Safeguarding
4.3.1 None.
4.4Dependencies
4.4.1 None. Environment and Safe Communities Committee 19 October 2021 4.5 Other
4.5.1 None.
5.1Section 151 Officer’s comments: The chargeable account was reviewed by the S151 Officer ahead of the statutory deadline of 30 September 2021.
6.1The Council needs to review its charging scheme. For any charging scheme the Council will need to fix their charges based on the 2020/21 accounts.
6.2Legal Officer’s comments: This recommendation concerns the accounting and administration requirement under the 2010 Regs for year end 2020/21 and the statement was properly approved.
7 Policies, Plans & Partnerships
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Building Control Chargeable Accounts Appendix 1Appendix | 329 KB | Download |
PDF |
Building Control Chargeable AccountsReport | 228 KB | DownloadRead as text |
Follow Environment Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jun 2026 | Questions and Statements from the PublicThere was one statement from a member of the public in relation to agenda item 6 on the agenda, Library of Things at ... | Decided | Open |
| 30 Jun 2026 | Declarations of InterestCllr Julie Morris declared a personal interest in agenda item 8 – Free Summer Tennis – and would leave the room for t... | Decided | Open |
| 30 Jun 2026 | Minutes of the Previous MeetingThe Committee confirmed as a true record the Minutes of the Committee held on 4 March 2026 and the Chair signed them. | Decided | Open |
| 30 Jun 2026 | Environment & Sustainability Working GroupFollowing Consideration, it was resolved to: (1) Agree the continuation of the Environment and Sustainability Working... | Agreed | Open |
| 30 Jun 2026 | Car Park Working GroupFollowing consideration the Committee agreed to: (1) Agree to the continuation of a Car Parking Working Group (CPWG).... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.