Following consideration, The Committee unanimously resolved to: (1) Note the implications of the budget targets presented to Strategy & Resources Committee on 13 July 2023. (2) Consider how additional income or savings can be generated to address the projected Council wide funding gap of £1.1m in 2024/25, rising to £2.5m by 2027/28. (3) Note that owing to the Council’s projected budget deficit, any additional new revenue growth items (i.e., service enhancements resulting in increased net expenditure) supported by Policy Committees will need to be fully funded from existing budgets. Resolved (6 for, 1 abstention, and the Chair not voting) to: (4) Agree that an additional cost item be added into the Committee’s budget plans for 2024/25 for £40k to cover possible additional independent noise assessment works or other activities that may be required at the Chalk Pit site in Epsom.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
This report informs the Committee of the Council’s revenue budget targets presented to the Strategy & Resources Committee in July. The report seeks guidance on the preparation of the Committee’s service estimates for 2024/25.
Recommendation (s) The Committee is asked to:
(1) Note the implications of the budget targets presented to Strategy & Resources Committee on 13 July 2023.
(2) Consider how additional income or savings can be generated to address the projected Council wide funding gap of £1.1m in 2024/25, rising to £2.5m by 2027/28.
(3) Note that owing to the Council’s projected budget deficit, any additional new revenue growth items (i.e. service enhancements resulting in increased net expenditure) supported by Policy Committees will need to be fully funded from existing budgets.
Reason for recommendation
1.1The recommendations will provide a clear framework for officers to develop a balanced budget for 2024/25, which is a statutory requirement.
2 Background Environment Committee 17 October 2023 2.1 Local authorities face a great deal of financial planning uncertainty over the medium term. This is mainly because central government funding settlements have tended, since the pandemic, to be limited to one-year only. In addition, the economic environment remains highly challenging and difficult to forecast, with elevated inflation impacting demand for services, and the cost of delivering those services.
2.2At its meeting on 13 July 2023, Strategy and Resources Committee agreed the budget targets and workstreams to enable the Council to work towards setting a balanced budget for 2024/25 and over the next Medium Term Financial Strategy four year-period.
2.3The committee noted that excluding any new growth in expenditure, additional annual income/savings of £1.1 million are projected to be needed to achieve a balance budget for 2024/25, increasing to £2.5m by 2027/28.
3 Full Proposals
3.1For financial planning purposes, latest forecasts show that the Council faces a projected budget deficit of £1.1m in 2024/25, rising to £2.5m by 2027/28.
3.2To address this deficit, Strategy & Resources Committee agreed that the following workstreams should be progressed by Directors and Heads of Service:
3.2.1 Officers to be tasked with identifying further efficiencies, although these are becoming harder to achieve after over a decade of austerity.
3.2.2 A base review, which entails reviewing the year end position for 2022/23, identifying any potential savings, additional cost pressures and areas where savings can be developed.
3.2.3 Service Reviews focusing primarily on discretionary services to be undertaken over the next four years with the aim of increasing efficiencies and effectiveness whilst reducing cost.
3.2.4 Review of existing asset utilisation, to realise cost reductions in Council operational buildings and increased income from investment properties.
3.2.5 Investigate income streams to maximise revenue from new and existing services, such as invest to save opportunities. Ensure any new powers are considered to generate additional income for the Council, such as the pending new charging policy for waste. Environment Committee 17 October 2023 3.2.6 Undertake a review of reserves, providing a justification for the level of reserves retained.
3.2.7 A target to increase fees and charges income by 6% in both 2024/25 and 2025/26 (as previously agreed by S&R in July 2022), then by CPI+1% for both 2026/27 and 2027/28. Heads of Service review fees and charges annually to ensure increases are achievable and report fees and charges to policy committees for approval.
3.2.8 To maximise external funding and partnership opportunities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Questions and Statements from the PublicThere was one statement from a member of the public in relation to agenda item 6 on the agenda, Library of Things at ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.