Resolved
Following consideration, the Committee unanimously resolved to: (1) Consider and approve the revised (November 2023) at Appendix 1.
Licensing and Planning Policy Committee approved this item on Wednesday 22 November 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Following consideration, the Committee unanimously resolved to: (1) Consider and approve the revised (November 2023) at Appendix 1.
The Local Development Scheme (LDS) is a project plan that sets out the timetable to produce new or revised Development Plan Documents which will form the Council’s Local Development Plan.
This LDS supersedes the version approved by the Committee on 21 November 2022 and sets out a planning work programme for the Council over a three-year period to 2026. The revised timetable will delay consultation on the Proposed Submission Local Plan (Regulation 19) Consultation by approximately eleven months. This is a direct result of the pause on the Local Plan that applied between 22 March and 24 October 2023.
Recommendation (s) The Committee is asked to:
(1) Consider and approve the revised Local Development Scheme (November 2023) at Appendix 1.
1.1Epsom and Ewell Borough Council is required to prepare and maintain a Local Development Scheme (LDS) in accordance with the Planning and Compulsory Purchase Act 2004 (as amended by the Localism Act 2011)
2.1The purpose of the Local Development Scheme is to set the timetable for the preparation and production of the Borough Council’s Local Plan. Licensing and Planning Policy Committee 22 November 2023 2.2 Progress against the milestones identified in the LDS is monitored through the Authority Monitoring Report. The Local Plan programme may be reviewed to take account of changes to planning or external circumstances which could have an impact on the timetable.
2.3The last Local Development Scheme was published in November 2022 and since this time, the council consulted on a Draft Local Plan (Regulation 18) between 1 February and 19 March 2023. Following the closure of the consultation on the draft Local Plan, an extraordinary Council meeting was held on the 22 March 2023 where the decision was made to pause the Local Plan and to allow specified tasks to be undertaken a motion to pause work on the Local Plan was carried which limited the work that could be undertaken by officers.
2.4On the 24 October 2023, at an Extraordinary Full Council, the decision was made to un-pause the Local Plan and therefore a new timetable needs to be prepared for the Local Plan.
Local Plan Programme
2.5The updated timetable outlines a project plan for the preparation, production and consultation on the new Plan and associated supporting evidence. The timetable identifies key milestones during document production.
2.6The key milestones for the Local Plan are shown below:
Stage Date / Status
Draft Local Plan Public Complete (undertaken February to Consultation (Regulation 18) March 2023)
Proposed Submission Local Plan January / February 2025 Public Consultation (Regulation 19)
Submission to the Secretary of May 2025 State (Regulation 22)
Estimated date of adoption Spring 2026 Licensing and Planning Policy Committee 22 November 2023 2.7 The timetable above is a delay of approximately 11 months compared to the previously approved Local Development Scheme. This is longer than the length of the Local Plan pause (7 months) however this is to enable officers to undertake additional briefing sessions with members concerning Local Plan content and to reflect that due to the pause we missed our initial allocated time slot for Surrey County Council to commence transport modelling work for our Regulation 19 Local Plan.
2.8The timetable has factored in the capacity of external consultants supporting us with the local plan evidence base, contains some contingency and will enable us to fully consider the impacts of future changes to the National Planning Policy Framework (once published).
3 Risk Assessment
Legal or other duties
3.1Equality Impact Assessment
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Local Development Scheme Appendix 1Appendix | 260 KB | Download |
PDF |
Local Development SchemeReport | 225 KB | DownloadRead as text |
Follow Licensing and Planning Policy Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | MotionThe Committee voted (3 for, 5 against,1 abstaining) against the motion. | Decided | Open |
| 22 Sep 2026 | Tandridge District Council Local Plan 2024-2044: Spatial Development Strategy Consultation (Regulation 18)The Committee resolved (5 for, 3 against, 1 abstaining) to: (1) Note the Council’s response to the Tandridge District... | Noted | Open |
| 22 Sep 2026 | Consultation on the Publication Draft of the Kingston Local Plan (Regulation 19)The Committee resolved (5 for, 3 against, 1 abstaining) to: (1) Note the Council’s response to the Kingston Local Pla... | Noted | Open |
| 22 Sep 2026 | Authority Monitoring Report 2025-2026The Committee resolved (8 for, 1 against) to: 1) Note the content of the Authority Monitoring Report for the 2025/26 ... | Noted | Open |
| 22 Sep 2026 | Epsom and Ewell Local Plan (2022-2040) Main Modifications ConsultationThe Committee resolved (7 for, 2 against) to: 1) Note the Inspectors Proposed Main Modifications to the Submission Lo... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.