Community and Wellbeing Committee approved this item on Tuesday 16 January 2024. Below is the council's own wording, with the papers it was decided on.
Following consideration, the Committee resolved (6 for, 1 abstention) to: (1) submit the capital programme for 2024/25 as identified in section 3 of the report to the Council for approval on 13 February 2024; (2) note the provisional forecast of schemes for the capital programme for 2025/26 to 2028/29; (3) note that schemes subject to external funding from Disabled Facilities Grants will only proceed once funding has been received.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
This report summarises the proposed 2024/25 capital programme and a provisional programme for 2025/26 to 2028/29. The Committee’s approval is sought for the programme to be submitted to Council in February 2024.
Recommendation (s) The Committee is asked to:
(1) submit the capital programme for 2024/25 as identified in section 3 of this report to the Council for approval on 13 February 2024;
(2) note the provisional forecast of schemes for the capital programme for 2025/26 to 2028/29;
(3) note that schemes subject to external funding from Disabled Facilities Grants will only proceed once funding has been received.
Reason for recommendation
1.1To seek the Committee’s approval to submit the proposed capital programme for 2024/25 to Council in February 2024 and to inform of the schemes included in the provisional forecast for 2025/26 to 2028/29.
2 Background Community and Wellbeing Committee 16 January 2024 2.1 The Capital Strategy was last agreed by Full Council on 14 February 2023 at which time the capital programme was approved for 2023/24. Schemes for 2024-2028 were provisional pending the annual budget review and an annual assessment of funds for capital investment.
2.2Strategy and Resources provided the Financial Strategy Advisory Group (FSAG) with a remit for the preparation of a capital programme for 2024/25. Under this remit, FSAG assessed all capital bids and recommended a programme for approval to the Policy Committees.
2.3The programme assumed funding from capital receipts, revenue funding, and government grants. The proposed level of investment for the 2024/25 programme is £1,701k, of which £500k is to be funded from a planned contribution from revenue. Combined with funding from the Disabled Facilities Grants, this will allow the forecast available capital receipts to remain at £2.4m at the end of this period. The agreed minimum threshold of capital receipts is £1m.
2.4The receipts forecast assumes a £500k revenue contribution to fund capital schemes in 2024/25, which is subject to the revenue budget being approved at Council in February 2024.
3 Core Programme 2024/25
3.1FSAG recommended that the following schemes should be considered by this Committee for inclusion in the capital programme in 2024/25, subject to the Committee approving the project appraisals.
Proposed Budget 2024/25 Expected Funding Capital Scheme Source £’000 Planned revenue Bourne Hall Roof Replacement contribution/external 306 & Solar Panel Installation funding if available/ capital receipts External funding if Wellbeing Centre Solar Panel 60 available/ capital Installation receipts Wellbeing Centre Windows 60 Capital receipts Replacement The Disabled Facilities Grant 785 Central govt grant Programme Total Community and 1,211 Wellbeing Committee Community and Wellbeing Committee 16 January 2024 3.2 Disabled Facilities Grant is received annually from the Department for Levelling Up, Housing and Communities. The Council has a statutory responsibility to administer the grant. The grant is typically used to make residential adaptations to enable vulnerable residents to maintain independence and remain in their own homes. Such interventions can prevent the need for NHS and/or sheltered housing services. The grant is typically used to:
Improve access to rooms and facilities – eg stairlifts; downstairs bathroom;
Provide a heating system;
Adapt heating or lighting controls to make them easier to use.
4 Provisional Forecast 2025/26 to 2028/29
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Community and Wellbeing Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
Homelessness Expenditure UpdateThe Committee unanimously resolved to: (1) Note the priority actions points which have been taken to manage homelessn...
Options for the Future of the MuseumThe Committee resolved (6 for, 1 abstaining) to: (1) Option 2: Invest in improvement of the Museum (should option 2 b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.