Revised Community Infrastructure Levy Instalements Policy
ApprovedPlanning3 papers
Licensing and Planning Policy Committee approved this item on Thursday 18 January 2024. Below is the council's own wording, with the papers it was decided on.
Epsom and Ewell Borough Council adopted its Community Infrastructure Levy (CIL) charging schedule on 29 April 2014 to take effect from the 1 July 2014. This introduced a CIL charge for each square metre of floor area in new developments of eligible residential, convenience retail, student accommodation and care homes granted planning permission. The Council’s Community Infrastructure Levy Instalment Policy came into effect on 1 July 2014. The policy is now over nine years old and has therefore been reviewed following a benchmarking process with neighbouring local planning authorities. It is recommended that the CIL instalment policy is updated to increase the thresholds for when CIL liable developments pay in instalments. Following consideration, the Committee unanimously resolved to: (1) Adopt the Epsom and Ewell CIL Instalment Policy (November 2023) attached as Appendix 1 to come into effect on the 1 April 2024 and supersede the current CIL Instalment Policy on this date.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
Epsom and Ewell Borough Council adopted its Community Infrastructure Levy (CIL) charging schedule on 29 April 2014 to take effect from the 1 July 2014. This introduced a CIL charge for each square metre of floor area in new developments of eligible residential, convenience retail, student accommodation and care homes granted planning permission.
The Council’s Community Infrastructure Levy Instalment Policy came into effect on 1 July 2014. The policy is now over nine years old and has therefore been reviewed following a benchmarking process with neighbouring local planning authorities.
It is recommended that the CIL instalment policy is updated to increase the thresholds for when CIL liable developments pay in instalments.
Recommendation (s) The Committee is asked to:
(1) Adopt the Epsom and Ewell CIL Instalment Policy (November 2023) attached as Appendix 1 to come into effect on the 1 April 2024 and supersede the current CIL Instalment Policy on this date. Licensing and Planning Policy Committee 18 January 2024 1 Reason for Recommendation
1.1The proposed changes to the Council’s Community Infrastructure Levy (CIL) Instalments Policy are recommended to reduce the amount of time it takes the council to receive CIL income following commencement of liable developments and reduce the administrative requirements upon the Council in administering CIL.
Background
2.1The process for the introduction and operation of CIL is guided by the Community Infrastructure Levy Regulations which have been amended numerous times since first introduced in 2010. This report relates to the payment of CIL following commencement of a chargeable development and not the CIL rates charged in the borough.
2.2The Council introduced CIL charging on 1st July 2014 and the CIL charges are indexed on an annual basis. To demonstrate the effects of indexation, the current indexed CIL rate for residential dwellings (C3) is £199.27 per square metre for applications determined in 2024, this compares to the rate of £125 per sqm that applied in July 2014 when CIL charging commenced in the borough, an increase of 59%. The CIL rates are forecast to increase again for 2024.
2.3The CIL Regulations set a default requiring full payment of the levy charge within 60 days of commencement of the chargeable amount. However, under Regulation 69B of the CIL Regulations 2010 (as amended) it is permissible for a CIL Charging Authority to establish an instalment policy, offering developers more flexible payment arrangements.
2.4The Councils introduced a Community Infrastructure Levy Instalment Policy that came into effect the same date that CIL charging commenced in the borough, 1 July 2014.
2.5The current instalment policy is detailed in Table 1 below and is triggered on chargeable amounts above £12,500, anything under £12,500 is a single payment due in 90 days.
Table 1 – EEBC Instalment Policy (July 2014)
Total CIL Liability Instalment Policy
Under £12,500 One payment at 90 days after commencement
£12,500 to £50,000 Two equal instalments at 90 and 180 days after commencement
Greater than £50,000 Three equal instalments at 90, 180 and 270 days after commencement Licensing and Planning Policy Committee 18 January 2024 2.6 The commencement of development triggers the payment of CIL and the issuing of a CIL Demand Notice. A key requirement of the Demand Notice is to explain the payment periods in accordance with the adopted instalment policy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Licensing and Planning Policy Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
Authority Monitoring Report 2025-2026The Committee resolved (8 for, 1 against) to: 1) Note the content of the Authority Monitoring Report for the 2025/26 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.