Following consideration, the Committee unanimously resolved to: (1) Submit the capital programme for 2024/25 as identified in section 3 of the report to the Council for approval on 13 February 2024; (2) Note the provisional forecast of schemes for the capital programme for 2025/26 to 2028/29.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
This report summarises the proposed 2024/25 capital programme and a provisional programme for 2025/26 to 2028/29. The Committee’s approval is sought for the programme to be submitted to Council in February 2024.
Recommendation (s) The Committee is asked to:
(1) submit the capital programme for 2024/25 as identified in section 3 of this report to the Council for approval on 13 February 2024;
(2) note the provisional forecast of schemes for the capital programme for 2025/26 to 2028/29.
Reason for recommendation
1.1To seek the Committee’s approval to submit the proposed capital programme for 2024/25 to Council in February 2024 and to inform of the schemes included in the provisional forecast for 2025/26 to 2028/29.
Background
2.1The Capital Strategy was last agreed by Full Council on 14 February 2023 at which time the capital programme was approved for 2023/24. Schemes for 2024-2028 were provisional pending the annual budget review and an annual assessment of funds for capital investment. Environment Committee 23 January 2024 2.2 Strategy and Resources provided the Financial Strategy Advisory Group (FSAG) with a remit for the preparation of a capital programme for 2024/25. Under this remit, FSAG assessed all capital bids and recommended a programme for approval to the Policy Committees.
2.3The programme assumed funding from capital receipts, revenue funding, and government grants. The proposed level of investment for the 2024/25 programme is £1,701k, of which £500k is to be funded from a planned contribution from revenue. Combined with funding from the Disabled Facilities Grants, this will allow the forecast available capital receipts to remain at £2.4m at the end of this period. The agreed minimum threshold of capital receipts is £1m.
2.4The receipts forecast assumes a £500k revenue contribution to fund capital schemes in 2024/25, which is subject to the revenue budget being approved at Council in February 2024.
3 Core Programme 2024/25
3.1FSAG recommended that the following schemes should be considered by this Committee for inclusion in the capital programme in 2024/25, subject to the Committee approving the project appraisals.
Proposed Budget 2024/25 Expected Funding Capital Scheme Source £’000
Ashley Centre Car Park - Planned revenue Barrier Controlled Parking 240 contribution System
External funding if Streetlight Replacement Phase 200 available/ Capital 2 receipts
Total Environment Committee 440
4 Provisional Forecast 2025/26 to 2028/29
4.1FSAG also considered the provisional forecast for the subsequent four years, which has been compiled through drawing information from the Asset Management Plan for buildings and other known capital expenditure requirements. Environment Committee 23 January 2024 4.2 The 2025/26 to 2028/29 provisional forecast for Environment Committee currently comprises the following sums, with individual schemes shown at Appendix 1:
Deferred 2025/ 2026 2027/ 2028/ from Total 26 /27 28 29 previous Provisional Forecast years
£’000 £’000 £’000 £’000 £’000 £’000
Ashley Centre Multi Storey 0 0 0 0 780 780 Car Park
Questions and Statements from the PublicThere was one statement from a member of the public in relation to agenda item 6 on the agenda, Library of Things at ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.