Licensing and Planning Policy Committee approved this item on Thursday 17 October 2024. Below is the council's own wording, with the papers it was decided on.
· Councillor Julie Morris proposed that the Nam Yang Martial Arts application bid is included in the successful bids sent to Strategy and Resources Committee to consider and approve funding for. The proposal was seconded by Councillor Phil Neale. The Committee agreed the proposed amendment (5 for, 2 against, and the Chair not voting). Following consideration, the Committee resolved to; (6 for, 1 abstaining, and the Chair not voting) (1) Approve the recommendations of the CIL Member Working Group by provisionally allocating CIL funding to the projects detailed in Appendix 1, including the addition of the Nam Yang Martial Arts Project; (2) Support a request to Strategy and Resources Committee to approve the funding totalling £2,086,966 from CIL as set-out in this report, with the addition of £161,250 of funding for the Nam Yang Martial Arts Project.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
The Council undertook its annual funding rounds for strategic and neighbourhood CIL between the 7 May and 18 June 2024. During this funding window 5 strategic CIL bids and 23 neighbourhood CIL bids were received.
In accordance with the Epsom and Ewell CIL Spending Protocol (January 2024), all bids received have been subject to an initial stage 1 assessment. Only the bids that passed the Stage 1 assessment were then subject to a stage 2 assessment by the CIL Member Working Group.
Following this process, three Strategic CIL bids (totalling £1,755,000 of strategic CIL funding) and six neighbourhood CIL bids (£331,966 of neighbourhood CIL funding) are presented to this committee for approval.
As the cumulative value of the CIL bids recommended for approval exceeds £50,000, in accordance with the Council’s financial regulations, the recommendations of this committee will be subject to approval of the funding by the Strategy and Resources Committee (S&R).
Recommendation (s) The Committee is asked to:
(1) Approve the recommendations of the CIL Member Working Group by provisionally allocating CIL funding to the projects detailed in Appendix 1;
(2) Support a request to Strategy and Resources Committee to approve the funding totalling £2,086,966 from CIL as set-out in this report. Licensing and Planning Policy Committee 17 October 2024 1 Reason for Recommendation
1.1To ensure the robust and effective expenditure and reporting in line with the Community Infrastructure Levy Regulations 2010 (as amended) and in accordance with the Epsom and Ewell CIL Spending Protocol (January 2024).
Background
2.1Epsom and Ewell’s CIL Charging Schedule came into force on the 1 July 2014 and applies to all liable developments that were granted permission after this date. CIL is payable when work to implement the development commences.
2.2The Community Infrastructre Levy (CIL) is used to mitigate the cumulative impact of development but is rarely sufficient to fund all of the infrastructure that is required to support development of an area. CIL cannot be used to remedy existing deficiencies (unless those deficiencies will be made more severe by new development) undertake maintenance of existing infrastructure, or remedy demands from population growth driven by other factors such as birth rates.
2.3On the 18 January 2024 this committee approved the Epsom and Ewell CIL Spending Protocol which sets out the governance arrangements for spending CIL funds in the Borough.
2.4CIL Regulations require appoprtionment of CIL as follows:
The Strategic CL Portion (70-80%)
The Neighbourhood Portion (15-25%)
The CIL Administrative proportion (5%)
Strategic CIL
2.5Strategic CIL funding can be used to fund infrastructure, including transport, flood defences, schools, hospitals, and other health and social care facilities. Local authorities must spend the levy on infrastructure needed to support development of their area. CIL can be used to increase the capacity of existing infrastructure or provide new infrastructure that is necessary to support development. The clearest way to justify this is to link it to the Council’s Infrastructure Delivery Plan that supports the Local Plan. We cannot use strategic CIL to fund affordable housing as this is still dealt with through s106 obligations.
2.6As of the 30 June 2024 there was £7,621,000 of unallocated Strategic CIL funding available in the borough. Licensing and Planning Policy Committee 17 October 2024 Neighbourhood CIL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Licensing and Planning Policy Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
Authority Monitoring Report 2025-2026The Committee resolved (8 for, 1 against) to: 1) Note the content of the Authority Monitoring Report for the 2025/26 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.