Resolved

It was agreed to progress this scheme committee under the 2025/26 capital programme. b) Environment 2 – Uppermill Pond Bank Replacement These works were considered essential and therefore it was agreed to progress this scheme under the 2025/26 capital programme. c) Environment 3 – Ashley Centre Car Park Overcoating Waterproof Membrane The rationale for doing the works in phases was discussed and it was agreed to progress level 1 only for the 2025/26 capital programme. d) Environment 4 – Court Recreation Ground Renewal of 3G Football Pitch It was agreed that this scheme should progress and 3G was confirmed as the best option. Members requested that Environment committee revisit the fees to ensure they are in line with other local pitches and additional income to repay investment. e) Environment 5 – Playground Renovation and Surface Renewal Members agreed that only the most in need playground should progress and recommended Hardwick’s Yard be funded from the budgeted revenue contribution to capital for 2025/26. f) Community & Wellbeing 1 – Playhouse Stage Lighting and Dimmers These works were considered essential to the continued operation of the theatre and therefore it was agreed to progress this scheme under the 2025/26 capital programme. g) Community & Wellbeing 3 – Bourne Hall Replacement of Windows – Phase 2 These works were considered essential to the continued operation of Bourne Hall. To realise economies of scale from combining this scheme with the phase 1 works taking place in 2024/25 Members recommended a report be taken to Full Council in December 2024 to seek approval for the budget in time to coordinate with the tenders which have been received. Following consideration of the above matters and the report’s contents, the Group moved to consider the report recommendations, which were agreed as follows: (1) Provide guidance on which of the final proposals should be taken to the relevant policy committee in January 2025 to seek support for inclusion within the 2025/26 Capital Programme. (2) Identify which schemes should be approved and which should be removed from the list of proposals in section 4.1 of the report.
Word for word from the decision Epsom and Ewell published for this meeting. Source: democracy.epsom-ewell.gov.uk

Follow this further

Built from Epsom and Ewell's papers

What the report saysPro

Report to Financial Strategy Advisory Group

Summary

This report sets out the final proposals for the 2025/26 Capital Programme and seeks guidance as to which of these should be taken to the relevant policy committee in January 2025 to seek support for inclusion within the 2025/26 Capital Programme.

Recommendation (s) The Panel is asked to:

(1) Provide guidance on which of the final proposals should be taken to the relevant policy committee in January 2025 to seek support for inclusion within the 2025/26 Capital Programme.

(2) Identify which schemes should be approved and which should be removed from the list of proposals in section 4.1.

Reason for recommendation

1.1To review and advise which final capital proposals should be taken to the relevant policy committee in January 2025 to seek support for inclusion within the 2025/26 capital programme.

2 Background Financial Strategy Advisory Group 22 November 2024 2.1 On 27 September 2024 Financial Strategy Advisory Group (FSAG) received eight initial capital proposals to be considered for inclusion in the 2025/26 capital programme. The Group assessed each proposal against the agreed criteria detailed in paragraph 3.1.

2.2FSAG requested that seven of the proposals progress to the final stage, and recommended deferral or rejection for not meeting the criteria of the other one. Of the progressed proposals, FSAG requested further information to be included in the final appraisal. This information has been provided in the updated final proposals at Appendix 2.

2.3FSAG are now asked to consider each final proposal and agree which should be recommended to policy committees for inclusion in the 2025/26 capital programme.

3 Criteria for Assessing Capital Proposals

3.1Full Council agreed the Capital Strategy in February 2024, which stipulated the criteria for assessing capital proposals to take account of the limited resources available. With the level of capital receipts projected at £2.375m after funding 2024/25’s capital programme, the Capital Strategy confirmed proposals should only be considered if they meet one of the following criteria:

3.1.1 Where there is a guarantee of the scheme being fully externally funded and is classed as a high priority.

3.1.2 Spend to save projects (see below).

3.1.3 Where it is mandatory for the Council to provide the scheme (eg Disabled Facilities Grants and Health and Safety).

3.1.4 Essential for business continuity, the minimum required to continue to deliver the services of Council (eg minimum level of building maintenance and IT).

3.1.5 Where the scheme is consistent with the Council’s Climate Change Action Plan, subject to affordability, supported by a robust business case and value for money can be demonstrated through a maximum payback period of 10 years.

3.2For the purpose of appraising any of the proposals funded as a ‘spend to save’, the following criteria should be applied;

3.2.1 Payback of the amount capital invested within the project within 5 years (10 years for renewable energy projects).

3.2.2 The return required on capital employed should be linked to the potential cost of borrowing (MRP) rather than potential loss of investment income. Financial Strategy Advisory Group 22 November 2024 3.2.3 Risk of not achieving return on investment is low.

3.2.4 Clear definition of financial cost/benefits of the scheme.

4 Capital Proposals for Consideration

4.1The proposals that FSAG agreed to progress to detailed project appraisal are as follows:

Amount Funding Proposal Title Source (£’000s)

Environment 1 Stew Ponds Removal of Silt 150 Capital receipts

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Final Capital Proposals: 2025/26 Appendix 1Appendix 451 KB Download
PDF
Final Capital Proposals: 2025/26 Appendix 2Appendix 1.8 MB Download
PDF
Final Capital Proposals: 2025/26 Appendix 3Appendix 397 KB Download
PDF
Final Capital Proposals: 2025/26 Appendix 4Appendix 439 KB Download
PDF
Final Capital Proposals: 2025/26Report 258 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 11 attended
ND
Councillor Neil Dallen MBEChair, present
HD
Councillor Hannah DaltonCommittee Member, apologies
LF
Councillor Liz FrostCommittee Member, present
AK
Councillor Alison KellyCommittee Member, present
PO
Councillor Peter O'DonovanCommittee Member, absent
CW
Councillor Clive WoodbridgeCommittee Member, present
AB
Andrew BircherOfficer, in attendance
KH
Kevin HanlonOfficer, absent
SE
Sue EmmonsOfficer, in attendance
TF
Tony FoxwellOfficer, in attendance
SM
Councillor Steven McCormickCommittee Member, in attendance

More from Epsom and Ewell Financial Strategy Advisory Group

All decisions
MeetingDecisionOutcome
27 Sep 2024 Initial Capital Proposals - 2025/26It was agreed that a review of the capital criteria used to assess capital bids would be considered at the next meeti... Agreed Open
26 Jan 2024 Treasury Management Strategy 2024/25Agreed to advise that Abu Dhabi and Qatar should be removed from the list of approved investable countries at section... Agreed Open
24 May 2016 Financial Planning 2017/18Agreed that cost reduction through efficiencies and service expenditure reviews be used as the main tools to achieve ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies