AI summaryEpsom and Ewell Environment Committee approved a £1,060,053 tender process to refurbish or replace eight playgrounds and recreation sites, funded by Strategic CIL.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedUnanimous approval to begin procurement
Money£1,060,053Fully funded by Strategic Community Infrastructure Levy
What happens nextTender processFurther report after procurement to appoint supplier
Who it affectsEight playground sitesAcross the borough
What was decided
The committee approved the start of a tender process for refurbishment or replacement of eight playgrounds and recreation facilities, totalling £1,060,053, funded by Strategic CIL. Report P3
The committee noted that a further report will follow the procurement, asking members to appoint the preferred supplier. Report P4
The committee authorised the Deputy Chief Executive and Director of Environment Housing and Regeneration, with the Director of Corporate Services and Head of Legal Services, to take all necessary steps to give effect to the decision. Report P5
Why
The contract value exceeds £750,000, so under the Council's Contract Standing Orders committee approval is required before procurement starts. Report 1.1
Strategic CIL funding of £1,060,053 was approved at the Strategy and Resources Committee on 25 September 2025 to improve eight playground and recreation facilities for young people and families. Report 2.1
Under the Council's Contract Standing Orders, procurement cannot begin without express permission from the relevant committee. Report 2.3
What happens next
Officers will run a Threshold 3 procurement exercise for works valued between £25,000 and £4,298,086 (excluding VAT). Report 2.4
A further report will come back to the Environment Committee after the procurement to seek approval to appoint the preferred supplier. Report P4
An Equality Impact Assessment and safeguarding considerations will be completed as part of the Threshold 3 procurement report. Report 3.1, P22, P25
The money
£1,060,053 Strategic CIL funding for refurbishment or replacement of eight playgrounds and recreation facilities Report P3, 2.1
Options considered
Chosen: Commence a Threshold 3 RFQ tender process for eight playgrounds at £1,060,053, funded by Strategic CIL. Contract value exceeds the £750,000 threshold requiring committee approval, and funding has already been secured Report P3, 1.1, 2.1
Implications
Financial: No impact on the Council's revenue budget, as the project is fully funded from Strategic CIL. Report 4.1
Legal: Legal support will be needed throughout the project, from either the Council's legal team or external legal advisors, with all contract and compliance matters addressed during procurement. Report 5.1, 5.2
Equalities: An Equality Impact Assessment will be completed as part of the Threshold 3 procurement report. Report 3.1, P22
Community safety: Improved play facilities are expected to have a positive impact on young people and families and help divert young people away from anti-social behaviour. Report 3.2, P24
Who and where
Young people and families across the borough who use the eight named playground and recreation sites Report 2.1, P9, P10, P11, P12, P13, P14, P15, P16
Users of the specific sites: Curtis Road Playground, Warren Rec Playground, Court Recreation Ground play areas, King George V (Poole Road) playground, King George V (Poole Road) MUGA, Alexandra Recreation Ground youth play area, Alexandra Recreation Ground basketball and football zones, and Chessington Road playground Report P9, P10, P11, P12, P13, P14, P15, P16
Timeline
25 September 2025: Strategy and Resources Committee approved release of £1,060,053 Strategic CIL funding for the eight sites Report 2.1, P45
20 January 2026: Environment Committee approved commencement of the Threshold 3 tender process
Following procurement completion: Further Environment Committee report to appoint the preferred supplier Report P4
Plain English for the jargon
Strategic CIL: Strategic Community Infrastructure Levy, a charge used to fund infrastructure
Threshold 3: Procurement process for works between £25,000 and £4,298,086 (excluding VAT)
CSO: Council's Contract Standing Orders, the rules governing how the Council procures contracts
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19
Resolved
Following consideration, the Committee unanimously resolved to: (1) Approve the commencement of a tender process for the refurbishment and replacement of eight playgrounds/recreation facilities to a total value of £1,060,053, funded by Strategic CIL. (2) Note a further report will be brought forward following completion of the procurement process, seeking approval to appoint the Preferred Supplier for the refurbishment and replacement of the eight playgrounds/recreation facilities. (3) Nominate and authorise the Deputy Chief Executive and Director of Environment Housing and Regeneration, in consultation with the Director of Corporate Services and Head of Legal Services to take all necessary steps to bring into effect the recommendations resolved by this Committee.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
To seek the Committee’s approval to commence a Threshold 3 RFQ procurement process for the works to refurbish and replace playgrounds and recreation facilities across the borough, fully funded through Strategic Community Infrastructure Levy (CIL).
Recommendation (s) The Committee is asked to:
(1) Approve the commencement of a tender process for the refurbishment and replacement of eight playgrounds/recreation facilities to a total value of £1,060,053, funded by Strategic CIL.
(2) Note a further report will be brought forward following completion of the procurement process, seeking approval to appoint the Preferred Supplier for the refurbishment and replacement of the eight playgrounds/recreation facilities.
(3) Nominate and authorise the Deputy Chief Executive and Director of Environment Housing and Regeneration, in consultation with the Director of Corporate Services and Head of Legal Services to take all necessary steps to bring into effect the recommendations resolved by this Committee.
Reason for recommendation
1.1In accordance with the Council’s Contract Standing Orders (CSOs), where the value of a contract is more than £750,000 (ex. VAT), Committee approval is required prior to commencing the procurement process. Environment Committee 20 January 2026 2 Background
2.1At the Strategy and Resources Committee on 25 September 2025, approval was granted for the release of £1,060,053 in Strategic CIL funding to improve eight playground/recreation facilities for young people and families across the borough.
2.2The eight sites across the borough that will benefit from these works are:
Curtis Road Playground
Warren Rec Playground
Court Recreation Ground play areas
King George V (Poole Road) playground
King George V (Poole Road) MUGA
Alexandra Recreation Ground youth play area
Alexandra Recreation Ground basketball/football zones
Chessington Road playground
2.3Whilst funding has been secured, in accordance with the Council’s Contract Standing Orders (CSO’s), procurement cannot commence without the express permission of the relevant committee.
2.4This report seeks approval from members to commence the tendering process and complete the Threshold 3 procurement report for works between £25,000 and £4,298,086 (excl VAT),
3 Risk Assessment
Legal or other duties
3.1Equality Impact Assessment
3.1.1 An Equality Impact Assessment will be completed as part of Threshold 3 procurement report.
3.2Crime & Disorder
3.2.1 Improved play facilities have a positive impact on young people and their families and help to divert young people away from anti-social behaviour. Environment Committee 20 January 2026 3.3 Safeguarding
3.3.1 Safeguarding considerations will form part of Threshold 3 procurement report.
3.4Dependencies
3.4.1 None
3.5Other
3.5.1 None
Financial implications
4.1There are no financial implications for the Council’s revenue budget, as this project is fully funded from Strategic CIL.
4.2Section 151 Officer’s comments: Financial implications are included in the body of the report.
Legal implications
5.1All legal matters, including contract preparation and compliance with the relevant legislation and regulations, will be addressed throughout the procurement process.
5.2Legal Officer’s comments: Legal support will need to be provided throughout this project by either the Council’s legal team or external legal advisors.
6 Policies, Plans & Partnerships
6.1Council’s Key Priorities: The following Key Priorities are engaged:
Effective Council
Safe and Well
Green and Vibrant
6.2Service Plans: The matter is not included within the current Service Delivery Plan.
6.3Climate & Environmental Impact of recommendations: None
6.4Sustainability Policy & Community Safety Implications: None
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Questions and Statements from the PublicThere was one statement from a member of the public in relation to agenda item 6 on the agenda, Library of Things at ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.