STONELEIGH AND AURIOL NEIGHBOURHOOD PLAN - TO 'MAKE' THE NEIGHBOURHOOD PLAN FOLLOWING A SUCCESSFUL REFERENDUM
AgreedPlanning2 papers
AI summaryEpsom and Ewell councillors formally adopt the Stoneleigh and Auriol Neighbourhood Plan after 93.4% voted yes in the February 2026 referendum, making it part of the statutory development plan.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedUnanimously agreed by the committee
MoneyNo direct financial implicationsPer Section 151 Officer comments
What happens nextPublish Decision Statement on websiteAnd notify qualifying body and interested parties
Who it affectsStoneleigh and Auriol neighbourhood areaPlanning applications decided using the plan
What was decided
The committee agreed the Stoneleigh and Auriol Neighbourhood Plan be formally made (adopted) as part of the statutory Development Plan. Report P7
The committee authorised publication of the Decision Statement (Appendix 1 of the report). Report P8
Why
A referendum on 12 February 2026 returned 93.4% yes and 6.6% no on a 20.7% turnout, triggering the council's duty to make the plan. Report 2.6, P26, P27, 1.1
Under section 38A(4)(b) of the Planning and Compulsory Purchase Act 2004 the council must make the plan within 8 weeks of a successful referendum. Report 1.1, 2.7, 5.1
What happens next
The council will publish the Decision Statement on its website, make hard copies available at local libraries and the council offices, and notify the qualifying body and anyone who asked to be informed. Report 2.9, 5.1
Once made, the plan will be used alongside the Epsom and Ewell Local Plan when determining planning applications in the neighbourhood area. Report 2.8, 5.1
Options considered
Chosen: Formally make the neighbourhood plan and publish the Decision Statement. Statutory duty following a successful referendum with more than 50% voting yes Report 1.1, 2.7, 5.1
Implications
Legal: The plan becomes part of the statutory land use development plan for the defined area with equivalent weight to the Epsom and Ewell Local Plan, and the council is duty bound to use it in determining planning applications. Report 2.8, 5.1
Climate: The plan contains a policy relating to renewable energy and energy efficiency. Report 6.3
Equalities: No equality impact assessment required for this decision. Report 3.1, P34
Who and where
Residents, workers and businesses in the Stoneleigh and Auriol neighbourhood area Report 2.9
Applicants for planning permission in the Stoneleigh and Auriol neighbourhood area Report 2.8, 5.1
Stoneleigh and Auriol Neighbourhood Forum as the qualifying body Report 2.9, 6.5
Timeline
November 2020: Neighbourhood Forum and Neighbourhood Area designated by the council Report 2.1
23 October 2025: Final Examiner's report received by the council Report 2.5
25 November 2025: Committee accepted Examiner's modifications and agreed the plan could proceed to referendum Report 2.5
12 February 2026: Referendum held, returning 93.4% yes on a 20.7% turnout Report 2.6, P26, P27
10 March 2026: Committee formally made the neighbourhood plan
Plain English for the jargon
Make (a neighbourhood plan): The formal step by which a local planning authority brings a neighbourhood plan into legal force, giving it the same weight as the local plan when deciding planning applications.
Decision Statement: A published notice confirming the council has made the neighbourhood plan, required under Regulation 19 and 20 of the Neighbourhood Planning (General) Regulations 2012.
Qualifying body: The organisation that proposed the neighbourhood plan, in this case the Stoneleigh and Auriol Neighbourhood Forum.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item34
Resolved
Following consideration, the Committee unanimously resolved to: (1) Agree that the Stoneleigh and Auriol Neighbourhood Plan be formally made (adopted) as part of the statutory Development Plan. (2) Authorise the publication of the Decision Statement (Appendix 1 of this report).
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
The Localism Act 2011 introduced a right for communities to draw up neighbourhood development plans. Stoneleigh and Auriol Neighbourhood Forum, with support and advice from Epsom and Ewell Borough Council has produced a neighbourhood plan.
The neighbourhood plan has been subject to community and stakeholder engagement and was subject to an Independent Examination during September and October 2025, which concluded with a recommendation by this committee that Neighbourhood Plan should proceed to Referendum.
A Referendum was held on 12 February 2026 with a positive outcome, with the following results based on a turnout of 20.7%:
Yes: 93.4%
No: 6.6%
Recommendation (s) The Committee is asked to:
(1) Agree that the Stoneleigh and Auriol Neighbourhood Plan be formally made (adopted) as part of the statutory Development Plan.
(2) Authorise the publication of the Decision Statement (Appendix 1 of this report). Licensing and Planning Policy Committee 10 March 2026 1 Reason for Recommendation
1.1To formally ‘make’ the Neighbourhood Development Plan for Stoneleigh and Auriol, under section 38A(4)(a) of the Planning and Compulsory Purchase Act 2004, following a positive Referendum on 12 February 2026 and in accordance with the prescribed timescales under section 38A(4)(b) of the Planning and Compulsory Purchase Act 2004.
Background
2.1Stoneleigh and Auriol Neighbourhood Forum has been working to prepare a neighbourhood plan for several years. The Neighbourhood Forum and Neighbourhood Area were designated by the Council in November 2020.
2.2Neighbourhood plans are required to be in general conformity with strategic policies in the Borough’s adopted Local Plan.
2.3The Council has a statutory duty to provide advice and assistance to Neighbourhood Forums that are preparing a neighbourhood plan. Planning officers have had regular contact with Stoneleigh and Auriol Neighbourhood Forum and have provided comments and planning advice throughout the preparation of the Neighbourhood Plan, via meetings and email correspondence. In addition, the council has provided a detailed responses to the two formal consultation stages detailed below:
Draft Neighbourhood Plan (Regulation 14) consultation.
Submission Neighbourhood Plan (Regulation 16) consultation.
2.4There are nine key stages to preparing a neighbourhood plan which are detailed below. Further information on each of the nine stages is contained within our Neighbourhood Planning Guide.
Stage 1 - Designating a neighbourhood area
Stage 2 - Designating a neighbourhood forum
Stage 3 - Preparing a draft neighbourhood plan - evidence gathering and public engagement.
Stage 4 - Pre-Submission publicity and consultation
Stage 5 - Submission of a neighbourhood plan to the Council as the local planning authority
Stage 6 - Independent Examination
Stage 7 – Referendum
Stage 8 - Bringing the neighbourhood plan into force Licensing and Planning Policy Committee 10 March 2026 Stage 9 – Monitoring and review
2.5The final Examiner’s report was received by the Council on 23 October 2025 which completed stage 6 and on the 25 November 2025 this committee accepted and agreed with the Examiner’s proposed modifications to the Stoneleigh and Auriol Neighbourhood Plan and that the plan could proceed to referendum on the 12 February 2026.
2.6The Referendum was held on 12 February 2026 (completing stage 7), with the following outcome based on a turnout of 20.7%:
Yes: 93.4%
No: 6.6%
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Licensing and Planning Policy Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
Authority Monitoring Report 2025-2026The Committee resolved (8 for, 1 against) to: 1) Note the content of the Authority Monitoring Report for the 2025/26 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.